High CourtsSingle Bench(2026) 09 DEL CK 7918

Supratik Infra Ventures Pvt Ltd vs Shri Chandrashekar Pandurang Tumsare & Ors.

Delhi High Court · Decided on 16 September 2026

HON’BLE JUDGES
Om Prakash Shukla, J
RESULT
Partly Allowed
CASE NUMBER
O.M.P. (COMM) 95/2024 & I.A. 3919/2024
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

69 paragraphs · 2,740 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

The present petition has been preferred under Section 34 of the Arbitration and Conciliation Act, 19961 assailing the Arbitral Award dated 05.02.2024 passed in Arbitration Case No. DIAC/3896/04-22 by the learned Sole Arbitrator2.

2.

In a nutshell, the present dispute arises from a development arrangement between a developer and the landowners. The Petitioner is the developer, and the Respondents are the landowners.

3.

The dispute originates from a Development Rights Agreement dated 12.10.2010 (“Agreement”) under which the Petitioner paid Rs.3.50 crore to Respondent Nos. 1 and 2 in consideration of development rights over their land, subject to the landowners fulfilling specified conditions precedent.

4.

Admittedly, the conditions precedent were not fulfilled. The Petitioner sought either performance of the Agreement or refund of Rs.3.50 crore, together with interest and damages. The Respondents, however, maintained before the learned Arbitral Tribunal that the 2010 Agreement had been superseded by subsequent agreements and, in any event, that the claim was barred by limitation.

5.

The learned Arbitral Tribunal ultimately accepted the objection on limitation, holding that the cause of action arose in 2010 and that no extension of time or continuous negotiation thereafter had been proved.

6.

Now, coming to the present proceedings, the Petitioner’s principal grievance concerns the rejection of its claim for refund of Rs.3,50,00,000/- together with interest.

7.

Learned counsel for the Petitioner submits that the learned Arbitrator erred in holding that limitation commenced on 15.11.2010 and ignored material indicating that the contractual relationship continued thereafter. Learned counsel for the Petitioner contends that payment of Rs.3.50 crore was completed only on 22.03.2013 and that discussions regarding sale of the project land continued in 2017.

8.

According to the Petitioner, therefore, the agreement clearly remained subsisting beyond 2010, and the finding on limitation rests on a failure to consider vital evidence.

9.

Learned counsel for the Petitioner further submits that the learned Arbitrator effectively rewrote Clause 5.1 of the Agreement by requiring any extension of the Closing Date to be communicated in writing.

10.

It is submitted that Clause 5.1 conferred upon the Petitioner the right to extend the Closing Date at its sole discretion and prescribed no particular form, much less a written notice, for exercising that discretion, unlike other provisions of the Agreement that expressly required written communication.

11.

The Petitioner therefore contends that the learned Arbitrator introduced a contractual requirement to which the parties had never agreed.

12.

In support of the submission that the contractual arrangement continued beyond 15.11.2010, the petitioner relies upon the following circumstances:

(i)

The first instalment of Rs.3,50,00,000/- is stated to have been fully paid only on 22.03.2013.

(ii)

Following non-fulfilment of the conditions precedent by the Closing Date, discussions are stated to have continued regarding sale of the project land under Clauses 6.4.1 and 6.4.2 of the Agreement, as reflected in an e-mail dated 08.05.2017.

(iii)

Agreements to sell were executed on 02.07.2018 and 13.10.2020 in respect of the Respondents’ land, with the Petitioner participating as a confirming party.

(iv)

In one of those transactions, the Petitioner states that it received Rs.50,00,000/- from the purchaser as part payment towards the land of Respondent No. 2.

13.

On the strength of the above foundation, learned counsel for the Petitioner submits that the contractual arrangement could not have been treated as having conclusively and automatically ceased on 15.11.2010 without examining these documents.

14.

Per contra, learned Counsel appearing for the Respondent No.1 opposes the petition and submits that the scope of interference under Section 34 is narrow. It is contended that the learned Arbitrator examined the evidence and the contractual provisions and arrived at a plausible view on limitation.

15.

According to the learned Counsel for the Respondent No.1, the Agreement expressly fixed 15.11.2010 as the Closing Date and stipulated the consequences of non-fulfilment of the conditions precedent. It is argued that the Agreement could not have continued in the absence of a subsequent written agreement extending the contractual period.

16.

It is further submitted that the Agreement contains provisions dealing with termination and the consequences of non-fulfilment, including Clauses 5.1, 5.2, 6.4, 6.4.1, 6.4.2 and 15. According to the Respondent No.1, time was of the essence, and 15.11.2010 was contractually fixed as the point at which the arrangement came to an end.

17.

It is further argued that a caution notice dated 23.10.2020 could not revive a claim that had already become time-barred. Learned counsel also submits that the Petitioner did not place the alleged legal notice dated 18.02.2019 on record and that reliance on later correspondence is insufficient to extend limitation.

18.

Learned counsel also relies upon subsequent events concerning the Respondents’ lands, including the sale of land by Respondent No. 3 and the attachment and auction of Respondent No. 2’s land, to contend that specific performance is no longer possible. It is further stated that the title of Respondent No. 1 remains subject to an encumbrance and that civil proceedings concerning the property are pending before the Civil Judge, Senior Division, Nagpur.

19.

Finally, learned Counsel for the Respondent No.1 submits that the Petitioner invoked the dispute nearly ten years after the Closing Date and that permitting such a claim would defeat the express contractual stipulation as to time.

20.

I have heard learned counsel for the parties at length and perused the record.

21.

Keeping in mind the limited scope of interference under Section 34 of the Act and the material placed before this Court, the following questions arise for determination:

(i)

Whether the learned Arbitrator’s conclusion that the Petitioner’s claim for refund of Rs.3,50,00,000/- became time barred on 15.11.2010 is sustainable on the material relied upon in the arbitral proceedings.

(ii)

Whether, in arriving at that conclusion, the learned Arbitrator failed to consider material documentary evidence having a direct bearing on the accrual of the cause of action and the subsistence of the parties’ contractual relationship.

22.

The case of Respondent No.1 proceeds on a straightforward proposition, that the Agreement stipulated 15.11.2010 as the Closing Date, and since the conditions precedent were required to be fulfilled by that date, their non fulfilment brought the contractual arrangement to an end. On that basis, 15.1.2010 is treated as the definitive date from which limitation commenced.

23.

In my view, however, that proposition cannot be considered in isolation from the subsequent conduct pleaded and documented by the Petitioner.

24.

In this regard, Clauses 5.1 and 5.2 are the relevant provisions and are reproduced below:-

5. CONDITIONS PRECEDENT

5.1

The Development and Sales Rights of the Project Land be and is hereby transferred in favour of the Developer by virtue of this Agreement, as per Clause 4.1 above. However the Land Owners have to fulfill the all the conditions precedent ("Conditions Precedent") enumerated herein below to the satisfaction of the Developer (or, where permissible under Applicable Law, waved in writing by the Developer at its sole discretion) before the "Closing Date", which shall take place no later than November 15th, 2010 or at any other date as may be extended by the Developer at its sole discretion.

a. The Land Owners shall have obtained all the rights, title, ownership and interest in Project Land from the respective original land owners and submitted original the Project Land to the title deeds pertaining PUR Developer;

b. Conversion of status of the Project Land from 'agriculture' to 'non-agriculture' use by virtue of which Project Land shall be capable of being developed Into Project, and delivery of original copy of such conversion certificate to the Developer;

c. The Developer (its legal/financial advisors) shall have completed a comprehensive legal (including certification. in respect of clear and uncontested title and have been provided evidence by the Land Owners that there is no threatened or pending litigation over the Project Land that may impact the Project), financial, technical, environmental, geo-technical (Including soil and ground water tests) and other due diligence of the Project Land, as may be deem fit by the Developer In its sole and absolute discretion.;

d. The Land Owners should have Issued No-Objection certificate in a format provided in 'Schedule III' of this Agreement, in favor of the Developer stating that the Land Owners does not have any objection, if the Developer or any of their Affiliate or contractually engaged firm associated with them undertakes any real estate activity in India in any manner whatsoever, with any third party;

e. The Land Owners should have provided necessary documentary evidence to the Developer to the effect that the Project Land has a appropriate access via 100 ft. wide existing Umred Road;

f. The Land Owners should have provided a certificate in O.M.P. (COMM) 95/2024 Page 7 of 13 favour of the Developer in the format provided in 'Schedule IV' certifying that the Project Land is a Contiguous (defined hereinafter) piece of land and the same is capable of being developed into the Project. "Contiguous" in relation to any piece/parcel of land shall mean a continuous piece/parcel that is a simple polygon or circular/oval in shape and shall specifically exclude any piece/parcel that, in the sole determination of the Developer: (a) includes one or more sub-parcels owned by third parties other than the Land Owners; (b) contains serpentine or irregularly shaped sub-parcels on which development appropriate to the Business Plan cannot be performed; or (c) incorporates one or more narrow strips of property on which either reasonable road access cannot be provided or improvements in accordance with the Business Plan cannot be constructed;

g. The Land Owners should have delivered to the Developer necessary approvals and consents procured by the Land Owners for commencement of project development activities;

h. The Land Owners shall provide an undertaking and Indemnity to the Developers that they have compiled. with all Applicable Laws (Including without limitation, all laws relating to zoning and environmental Impact) and regulations in relation to the Project Land;

i.

Execution by the Parties of the Transaction Documents necessary to consummate the proposed transaction, including an undertaking by the Land Owners In favour of the Developer agreeing to create a mortgage, to execute all corporate or personal guarantees, escrow agreement, Indemnities, sureties or similar Instruments, as and when required by the Developer, in favour of the Developer and/or financial banks/institution, for any financial assistance for construction and development of the Project;

j. There shall not have occurred any material adverse effect' in the business, operations, properties, prospects, assets, or condition of the Land Owners and Project Land and no event has occurred or circumstance exists that is reasonably likely to result in such a 'material adverse effect'.

k. There shall not be in effect on the Closing Date, any actual or threatened litigation, writ, judgment, injunction, decree, or similar order of any court restraining, enjoining, or otherwise preventing consummation of any of the proposed transaction contemplated by this Agreement;

l. Any other Conditions Precedent as may be added by the Developer in its discretion; m. Issuance of a Conditions Precedent compliance certificate by the Lands Owner in favour of the Developer stating that all the condition precedent as mentioned in clauses 5.1(a) to 5.1(m) has been duly satisfied by the Land Owners.

5.2

In case the Conditions Precedent mentioned herein above are not fulfilled, the Developer, in their sole discretion, shall have the right to terminate this Agreement as per Clause 15.2.

25.

The conclusion that the Agreement “automatically came to an end” on 15.11.2010, as accepted by the learned Arbitral Tribunal and urged by Respondent No. 1, is difficult to sustain on the language of Clause 5.2.

26.

Clause 5.2 does not provide that failure to fulfil the Conditions Precedent automatically terminates the Agreement. Instead, it provides that, if the Conditions Precedent are not fulfilled, the Developer “shall have the right to terminate this Agreement as per Clause 15.2.”

27.

The language of Clause 5.2 thus confers an option or right to terminate, it does not provide for automatic termination. In my view, the clause cannot reasonably be construed otherwise.

28.

This construction is also consistent with Section 55 of the Contract Act, 1872 under which, even where time is of the essence, failure to perform by the specified date renders the contract voidable at the option of the promisee rather than automatically void. I am of the view that no reasonable person would read or interpret this clause as the arbitral tribunal did.

29.

The next aspect concerns the learned Arbitral Tribunal’s finding that an extension of the Closing Date had to be evidenced by a written communication. I feel that this finding is also vulnerable under the contours of Section 34.

30.

Clause 5.1 itself stipulates that Closing Date may be extended by the Developer at its “sole discretion” and, on its terms, does not require such extension to be in writing.

31.

The Supreme Court in Kailash Nath Associates v. DDA3, while considering Section 63 of the Contract Act, recognised that an extension of time need not necessarily be reduced to writing and may, depending upon the terms of the contract, be established through conduct and forbearance.

32.

Accordingly, the learned Arbitrator could certainly require proof that the Developer had in fact exercised its discretion to extend time. However, imposing an independent requirement that the extension in writing, when the Agreement does not appear to prescribe such a requirement, would amount to adding a term to the contract and cannot be sustained.

33.

In my view, Clause 5.1 cannot reasonably be read as making a written communication a condition precedent to an extension of the Closing Date.

34.

The learned Arbitral Tribunal further held that, post 2010, there was no material on record indicating correspondence between the parties.

35.

Although this Court, while exercising jurisdiction under Section 34, cannot re-appreciate the evidence as if sitting in appeal, the present case cannot be treated as one in which there was no material as all based on the parties’ post-2010 conduct. I am of the view that this case is certainly not one of “no evidence”.

36.

As noticed in paragraph 12 above, the documents relied upon by the Petitioner are materially different from mere reminders issued after expiry of limitation. Prima facie, they are capable of indicating that the parties continued to act under, or otherwise recognise, the contractual arrangement after 15.11.2010.

37.

This Court, exercising jurisdiction under Section 34, is not called upon to determine the precise date on which the cause of action accrued. It is sufficient to note that the Agreement did not, by its terms, automatically terminate on 15.11.2010,. The Developer had a contractual power to extend time, and the subsequent documents relied upon by the Petitioner were capable of bearing on whether the parties continued to treat the arrangement as subsisting.

38.

Viewed in that light, the limitation finding adopted by the learned Arbitral Tribunal cannot be regarded as a plausible view on the material identified above.

39.

The Award proceeds on the erroneous premise that nothing occurred between 15.11.2010 and 2020 and consequently treats 15.11.2010 as the automatic breaking point. However, the Agreements to Sell in 2018 and 2020, as well as Respondent No.1's purported termination in 2019, do not appear to have been considered.

40.

If these documents formed part of the arbitral record, their relevance to the issue of limitation ought to have been considered.

41.

The mere stipulation of a Closing Date in the Agreement does not, without examining the contractual scheme and the parties’ subsequent conduct, conclusively determine every question concerning limitation.

42.

Accordingly, the limitation finding, insofar as it proceeds on 15.11.2010 as the necessary and automatic date of accrual without adequate consideration of the material referred to above, cannot be sustained.

43.

For the foregoing reasons, this Court finds that the challenge to the finding on limitation deserves to be accepted to the limited extent indicated above.

44.

The impugned award dated 05.02.2024 is accordingly set aside to the extent that Claim No. 2, namely the claim for refund of Rs.3,50,00,000/-, was rejected solely on the basis that the cause of action necessarily accrued on 15.11.2010, without adequate consideration of the subsequent documentary material relied upon by the Petitioner.

45.

The said issue shall stand restored for fresh adjudication in accordance with law, including determination of the legal effect of the Closing Date under the Agreement.

46.

The petition is accordingly allowed in part in the above terms.

47.

There shall be no order as to costs.