AI Structured Summary
Not yet generated for this judgment
Judgment
Navin Chawla, J
This petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’) has been filed by the
petitioner challenging the Award dated 24.08.2017 passed by the Sole Arbitrator in the Arbitration Proceedings held between the parties.
The disputes between the parties relate to the Award of work of earth work in filing, embankment and cutting, provision of the blanketing material,
construction of bridges and other allied works between K.M 49.00 to K.M 74.4 on Rewari - Jhajjar - Rohtak section in connection with Rohtak -
Jhajjar - Rewari new railway line in favour of M/s Subhash Chander & Co. (the predecessor of the petitioner, herein).
The entire work were required to be completed within 18 months from the date of issue of acceptance letter dated 04.07.2007 i.e. on or before
03.01.2009. The work was, however, completed on 28.02.2011. During the execution of the work, the respondent granted the first Extension of Time
vide its letter dated 12.02.2009 without levy of penalty and with the benefit of Price Variation Clause (PVC). Thereafter, further extension was
granted vide letters dated 04.08.2009, 07.08.2009, 10.03.2010 and 20.06.2010, again without penalty, however, without the benefit of PVC. By letter
dated 17.03.2011, ex post facto extension was granted by the respondent, again without penalty, however, without the benefit of PVC. The second
and final Addendum cum Corrigendum to the Contract Agreement was executed between the parties on 14.10.2011 and the final payment of
Rs.54,59,691/- was released in favour of the petitioner.
The petitioner, inter-alia claiming that, as the delay had occurred due to the reasons attributable to the respondent, therefore, the petitioner was
entitled to the extension of time with PVC, raised various claims and this Court vide order dated 10.02.2014 passed in Arb. P.234/2013 appointed the
Sole Arbitrator to adjudicate the disputes that had arisen between the parties.
The Arbitrator by way of the Impugned Award has rejected all the claims of the petitioner.
The primary contention of the petitioner against the Impugned Award is that the Arbitrator has failed to consider that the delay in execution of the
work was for the reasons attributable to the respondent and it is for this reason that, while granting extension of time, the respondent had not levied
any penalty on the petitioner. The challenge to the Impugned Award on this aspect can be better appreciated from the following paragraph of the
petition:
“The inference drawn by the Ld. Arbitrator is not based on the facts and material placed on record and it is against the public policy as
brought out at para 6, the delay in completion was due to non release of drawings, non completion of the bridges work interested to other
agencies. The inference of the Arbitrator that the claimant did not protest against the denial of price variation clause till February,2012 is
in correct. The protest were made vide letters dated 13-8-2010, 22-11-2010, 10-1-2011 and 17-5- 2011. Copies of letters dated 13-8-2010,
22-11-2010 and, 10-1-2011 are collectively Annexure-M hereto. It may be mentioned here that even in letter dated 29-11-2010 (Annexure-
G) also it has been confirmed by the respondent that the request for PVC made by the claimant vide letter dated 13-8-2010 was being
examined and accordingly action will be taken.â€
I am unable to agree with the submission made by the learned counsel for the petitioner. The Arbitrator in his Impugned Award has considered the
entire correspondence exchanged between the parties. The Arbitrator has also, on merit, considered the reasons given by the petitioner for claiming
that the delay had occurred due to defaults of the respondent. The Arbitrator has relied upon the declaration submitted by the petitioner in the
prescribed Proforma Declaration “Annexure-C†of the tender declaring that the petitioner had made itself conversant with the condition like
Topography of air, Soil strata at site of work, sources and availability of construction materials, etc. The Arbitrator has further found that it was the
petitioner who had failed to carry out the work with expedition even after the supply of L-Section of KM 49 to KM 60 by the respondent to the
petitioner. The Arbitrator has further discussed the evidence led by the parties even in relations to the other area of land handed over by the
respondent to the petitioner and concluded that the petitioner had been unable to show the engagement and deployment of sufficient manpower and
machinery at the site of the work. The Arbitrator concluded that in absence of such evidence, it must be held that the petitioner had not deployed
adequate machinery and manpower for execution of the earth work and embankment in terms of the Letter of Acceptance dated 04.07.2007 and
Contract Agreement dated 13.02.2008 and delay in the execution of the work is directly attributable to the petitioner.
As far as the delay in supply of drawing of bridges by the respondent is concerned, the Arbitrator has again discussed in the Impugned Award the
effect thereof and the correspondence exchanged between the parties to re-emphasize that the delay in execution of the work was directly
attributable to the petitioner. Paragraph 49 of the Impugned Award is reproduced herein below:
“49. There is no doubt that there was some delay in supply of drawings of the bridges required to be constructed but the claimant cannot
take advantage of the same because M/s.Subhash Chander & Co. failed to carry out the work in accordance with terms and conditions of
LoA and the Contract Agreement and could construct only 35 minor bridges and that too after grant of four extensions and one post facto
extension on the basis of written requests made by M/s. Subhash Chander & Co, While granting first extension vide letter dated 12.02.2009
the competent authority had taken cognizance of the fact that there was some delay on the part of the respondent in supplying the drawings
of bridges and this is the precise reason why the benefit of price variation clause was given to the claimant and a sum of Rs.64,89,807.54
was paid in terms of price variation clause. However, all subsequent extensions were granted without the benefit of price because the
concerned authority was convinced that M/s. Subhash Chander & Co. had failed to carry out the work with a due diligence. This is amply
proved from letters dated 04.08.2009 (Annexure R-2/ 2) dated 17.08.2009 (Annexure R-2/1), 10.03.2010 (Annexure R-2/3), 29.06.2010
(Annexure R-2/4), 17.03.2011 (Annexure R-2/5). Apart from these letters, the concerned authority had made request to the claimant vide the
letters dated 30.07.2008 (Exhibit RW-1/7), 27.12.2008 (Exhibit RW-1/8), 22,01.2009 (Exhibit RW-1/9), 30.10.2009 (Exhibit RW-1/10),
23.07.2010 (Exhibit RW-1/11), 09.08.2010 (Exhibit RW-1/12), 12.11.2010 (Exhibit RW-1/13), 20.10.2010 (Exhibit RW-1/14), 29.11 2010
(Exhibit RW-1/15), 25.07.2011 (Exhibit RW-1 /16) and 29.09.2011 (Exhibit RW-1/18). When the claimant made representation dated
12.05.2011 for grant of the benefit of PVC on extended period of contract, the Headquarter Office of the Northern Railway specifically
rejected, the same vide letter dated 22.06.2011 (Annexure R - 6) by pointing out that approved section was finalized in November 2007. The
drawings of the bridges were given in stages to commensurate with the progress of the work at the site and complete set of drawings were
given in February 2008, but even then the progress of bridges were very poor and took it nearly three years to complete the same. It was
also mentioned that some investigation was got done by M/s Subhash Chander & Co. as non-schedule item, but it was in no way
handicapped in constructing tile bridges when there was no loss on account of idling of labour, payment due to PVC and in fact the work of
the progress was very poor. It is quite interesting to note that M/s Subhash Chander & Co. did not protest against the denial of the benefit
of price variation clause in second, third, fourth and fifth extensions till February 2012 . This goes a long way to show that delay in the
execution of work was directly attributable to claimant.â€
It cannot, therefore, be said that the Arbitrator has failed to consider the evidence led before him. As far as the plea that the inference drawn by
the Arbitrator from the documents is incorrect, it is only stated to be rejected. This Court in exercise of its power under Section 34 of the Act does not
sit as a Court of Appeal against the Arbitral Award. The Arbitrator is the final Judge of the evidence led before him. He is the ultimate master of the
quality and quantity of the evidence to be relied upon and it is not for this Court to re-assess or re-appreciate such evidence (Associate Builders v.
Delhi Development Authority, (2015) 3 SCC 49).
Even on facts, I do not find the view taken by the Arbitrator to be incorrect in any manner, so as to call any interference from this Court in
exercise of its power under Section 34 of the Act.
In respect of denial of claim no.4, the petitioner in this petition has alleged that the Arbitrator has erred in rejecting the said claim placing reliance
upon the Clause 39.6 of the special-data and specification of the tender condition which formed part of the Contract Agreement. The petitioner has
contended that the said claim has been rejected by taking wrong interpretation of the said clause. In Associate Builders (supra), the Supreme Court
has cautioned that construction of the terms of the contract is primarily for the Arbitrator to decide unless the Arbitrator construes the contract in such
a way that it could be said to be something that no fair-minded or reasonable person could do. The petitioner has not been able to make out a case
falling under the above exception and therefore, the Impugned Award, so far as it rejects the claim no.4 of the petitioner, cannot be faulted.
The next challenge of the petitioner is to the rejection of claim no.5 by the Arbitrator. This claim was for extra payment for bringing material from
Rajasthan resulting in additional costs to the petitioner. The Arbitrator has, after discussing the evidence led by the parties, held that the Circular dated
28.02.2010 issued by the Director Industries and Commerce, Mines and Geology, Haryana cannot be relied upon by the claimant in support of its
claim for extra expenditure incurred in procuring the material from Tiba Basi in Rajasthan. The Arbitrator has further discussed the evidence led by
the petitioner in support of quantification of the said claim and held that there was a serious doubt on the authenticity of the documents relied upon by
the petitioner in support of said claim and even otherwise there was no evidence on record to show that the material allegedly transported by M/s
Ashok Kumar and M/s Prem Engineers had actually been unloaded at the site of the work in Jhajjar, Haryana and used by the petitioner for
embankment. The petitioner, by way of the present objection is again wanting this Court to re-appreciate the evidence that was led before the
Arbitrator. Such exercise cannot be done by this Court in exercise of its power under Section 34 of the Act. I see no merit in the challenge to the
above findings.
In view of the above, I find no merit in the present petition and the same is accordingly dismissed with no order as to cost.
