AI Structured Summary
Not yet generated for this judgment
Judgment
O R D E R
28.01.2022: Heard counsel for the Appellant as well as learned counsel appearing for the Resolution Professional. This Appeal has been filed against the order dated 14.07.2021 passed by the Adjudicating Authority (National Company Law Tribunal) New Delhi, Court-IV by which the application filed by the Appellant being I.A. No. 2880/2021 has been rejected. The Appellant claims that he has an Agreement to Sell from the Corporate Debtor dated 06.08.2019. The Corporate Insolvency Resolution Process was initiated on 19.09.2019. Appellant filed an application for exclusion of property from the assets of the Corporate Debtor. In the Application being I.A. No. 2880/2021 following prayers have been made:
“A. Issue an appropriate order or direction to the Resolution Professional to exclude the commercial property bearing No. SCO/24 in Wave Courtyard, Cont’d…/ Wave One Project, Sector 18 from the insolvency resolution plan of the Corporate Debtor; Alternatively;
B. Issue an appropriate order or direction to the Resolution Professional to make the payment of legitimate outstanding of the Application of Rsl2,30,04,651/- with interest @12% p.a. from 08.08.2019 to the date of realization in accordance with law and within the time stipulated by this Hon’ble Tribunal;
C. Any other or further order(s) as may be deemed fit and proper in the facts and circumstances of the case may also be passed.”
Adjudicating Authority has rejected the application filed by the Appellant. The Appellant claims to be aggrieved by the order of rejection passed by the Adjudicating Authority.
Learned counsel for Appellant submits that he had supplied to the Resolution Professional all relevant documents. The transaction has been found to be preferential in nature and Appellant has been recognized as Operational Creditor.
The Appellant admittedly has not been holding the property as owner which is claimed to be excluded from the process. We, thus, do not find any error in the order of the Adjudicating Authority rejecting application of the Appellant for exclusion of the property.
Learned counsel for the Appellant lastly contended that his claim is yet to be verified by the Resolution Professional. It was also submitted that resolution plan has not yet been approved. Counsel for the Resolution Professional submits that even the claim is not yet been filed by the Appellant. We, thus, are of the view that no error has been committed by the Adjudicating Authority in dismissing the application filed by the Appellant. We find no merit in the Appeal. Appeal is dismissed.