Judgment
Essentially the matter pertains to seeking refund of amount paid along with compensation on account of delay in handing over possession of the unit in question.
It is undisputed that in terms of the agreement entered into between the parties, the unit in question ought to have been handed over on 26.03.2014. However, there has been delay and the OC was also received only on 22.12.2014 and, thereafter, offer of possession was made.
On the Appellant filing a complaint before the learned State Commission in CC/183/2021 seeking refund, the learned State Commission vide order dated 03.01.2024 inter alia directed as follows:
'13. Keeping in view the facts of the present case and the extensive law as discussed above, we direct the Opposite Party to refund the entire amount paid by the Complainant i.e., Rs. 1,05,87,241/- along with interest as per the following arrangement:
A. A simple interest @ 6% p.a. calculated from the date on which each installment/payment was received by the Opposite Party till 03.01.2024 (being the date of the present judgment);
B. The rate of interest payable as per the aforesaid clause (A) is subject to the condition that the Opposite Party pays the entire amount on or before 03.03.2024;
C. Being guided by the principles as discussed above, in case the Opposite Party fails to refund the amount as per the aforesaid clause (A) on or before 03.03.2024, the entire amount is to be refunded along with an interest @ 9% p.a. calculated from the date on which each installment/payment was received by the Opposite Party till the actual realization of the amount.
14.In addition to the aforesaid and taking into consideration the facts of the present case, the Opposite Parties are directed to pay a sum of:
A. Rs. 5,00,000/- as cost for mental agony and harassment to the Complainants; and B. The litigation cost to the extent of Rs. 2,00,000/-."
It is the specific submission of the learned counsel for the OP/ Respondent that they have complied with the order of learned State Commission as on 22.02.2024.
The present Appeal has been filed by the Complainant/Appellant seeking enhancement of the compensation on the grounds that the compensation @ 6% awarded by the learned State Commission is very less and that the Complainant is entitled for 15% of interest.
Heard learned counsels for both the parties in detail and perused the records.
As regards rate of interest liable paid in the event of delay, Para 18(a) of the terms of the agreement entered into between the parties:
“18 (a) In case the Company is not able to hand over the possession to the Allottee(s) in terms of the timelines as stated in clause 16(a)(i) [provided however contingencies stated in clause 16(b) have not occurred], in such an event the Allottee(s) shall be entitled to an interest calculated at 9% p.a. (simple interest) on the amount(s) paid by the Allottee(s) for such period of delay.”
The matter pertains to refund on account of delay in handing over possession. Therefore, the Complainant is entitled for compensation for the amount paid to the OP as per the terms of agreement. In addition, reliance placed on the order of Hon’ble Supreme Court in the case of Experion Developers Pvt. Ltd. Vs. Sushma Ashok Shiroor, in Civil Appeal No.6044 of 2019 decided on 07.04.2022, it was held as under:-
“We are of the opinion that for the interest payable on the amount deposited to be restitutionary and also compensatory, interest has to be paid from the date of the deposit of the amounts. The Commission in the Order impugned has granted interest from the date of last deposit. We find that this does not amount to restitution. Following the decision in DLF Homes Panchkula Pvt. Ltd. Vs. DS Dhanda and in modification of the direction issued by the Commission, we direct that the interest on the refund shall be payable from the dates of deposit. Therefore, the Appeal filed by purchaser deserves to be partly allowed. The interest shall be payable from the dates of such deposits.
At the same time, we are of the opinion that the interest of 9% granted by the Commission is fair and just and we find no reason to interfere in the appeal filed by the consumer for enhancement of interest.”
As regards the order of the State Commission dated 03.01.2024 awarding Rs. 5,00,000/- as cost for mental agcny and harassment as well as Rs. 2,00,000/- as cost of litigation, we rely on the judgment of Hon’ble Supreme Court in DLF Homes Panchkula Pvt. Ltd. Vs. D.S. Dhanda, in CA No.4910-4911 of 2019 decided on 10.05.2019 has held that multiple compensations for singular deficiency is not justifiable.
Therefore, the order of learned State Commission with respect to award of Rs. 5,00,000/- as cost for mental agony and harassment is set aside. And Rs.2,00,000/- as cost of litigation is reduced to Rs. 1,00,000.
ORDER
The OP/Respondent is directed to refund the amount deposited by the Complainant along with interest @ 9% per annum from the dates of respective deposits till the date of final payment, within a period of 60 days from today.
In the event of delay, the interest rate liable to paid on the balance amount is @ 12% per annum for such delayed period.
The OP is also directed to pay Rs. 1,00,000/- as cost of litigation, in total.
It is made clear that the amount already paid by the OP to the Complainant is liable to be deducted from the total amount due.
With these directions, FA/72/2024 is disposed of.
All pending applications, if any, are also disposed of accordingly.