Tribunals and CommissionsFull Bench(2022) 11 RERA CK 0816

Smt. Meeta Gulati vs M/s Parsvnath Developers Ltd.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 29 November 2022

CASE NUMBER
Com/10/08/2022, Com/08/08/2022, Com/03/08/2022

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

11 paragraphs · 288 words
1.

All three cases were heard together being of similar nature.

2.

Adv. Mayank Aggarwal appeared on behalf of the Complainants and submitted that he has already served the copies of the complaints along with all documents to the Respondents. He also filed proofs of service.

3.

We note that the office of Authority had also sent the notice along with copies of the complaints to the Respondents on 18.10.2022.

4.

Adv. Aishwary Jain appeared on behalf of the Respondents and stated that the Respondents have yet not received the copies of the complaints and other documents. He, however, admitted receipts of copy of last order passed by this Authority.

5.

Ld. Counsel for Complainants reiterated that he had e-mailed the complaints to the Respondents and confirmed the same by filing affidavit as proof of service. The submissions made by the Ld. Counsel for Respondents were not found convincing.

6.

Since, no replies have been filed by the Respondents we impose cost of Rs. 5,000/- in each case for delay in filing the reply.

7.

We once again direct office to send copies of complaint along with all documents in all the three cases to the Ld. Counsel for the Respondents within next ten days.

8.

Respondents to file replies to the complaints by 15.01.2023 with copies served on the Complainants. Complainants to file rejoinders, if they wish by 31.01.2023, with copies served on the Respondents.

9.

Ld. Counsel for the Complainants is also directed to visit the site and submit a status report on the project by 15.01.2023.

10.

Office is directed put up Project File No. F1/(4)/PR/2017 before the Authority for examination.

11.

All cases are posted for further hearing on 16.02.2023 (Thursday) at 11:30 a.m.