AI Structured Summary
Not yet generated for this judgment
Judgment
Nitin Wasudeo Sambre, J.
This is an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as “Act of 1996”), questioning the judgment dated 01st May, 2025 delivered by the learned Single Judge of this Court in OMP (COMM) 246/2022, whereby the learned Single Judge has confirmed and upheld the arbitral award dated 16th October 2019.
The facts necessary for deciding the present appeal are as under:
A. The appellant claims to be a public limited company engaged in civil engineering, construction, and infrastructure development, having its registered office at Kolkata, whereas respondent no. 1 herein is a private limited company registered under the Companies Act, 1956, having its registered office at Bangalore, State of Karnataka. Respondent no.1 is engaged in the business of bulk material handling systems.
B. Respondent no. 2 owns a 3x150 MW Thermal Power Plant at Haldia, Purba Medinipur, in the State of West Bengal that was formerly known as India Power Corporation (Haldia) Limited.
C. Respondent no. 2 invited bids through a tender process for engineering, procurement, transportation, supply to the site, and insurance of the main plant equipment and accessories, along with balance of plant equipment and accessories, in connection with the aforesaid thermal power plant.
D. One BF Infrastructure Limited (“BFIL”) submitted a proposal and was in turn appointed as the EPC Contractor of respondent no. 2 for the establishment of the aforesaid thermal power plant.
E. Respondent no. 2, later in the year 2012, invited bids for designing, engineering, manufacturing, supply, erection, and commissioning of the coal handling project pertaining to the aforesaid plant.
F. For the same, respondent no. 1 submitted its bid to respondent no. 2, which resulted in the execution of the contract among respondent no. 1, 2 and BFIL, with a project cost of Rs. 47,50,00,000/-. Out of the said contract amount, Rs. 43,00,00,000/- was towards the purchase price of the equipment and the balance amount of Rs. 4,50,00,000/- was for the services rendered.
G. Along with the aforesaid agreement, the parties also agreed to the General Commercial Terms and Conditions dated 20th December, 2013, which contained an arbitration clause which reads thus:
“29.0 ARBITRATION
29.1In the event of any dispute or difference arising out of the execution of the Order/Contract or the respective rights and liabilities of the parties or in relation to interpretation of any provision by the Seller/Contractor in any manner touching upon the Order/Contract, such dispute or difference shall (except as to any matter the decision of which is specifically provided for therein) be referred to the arbitration of the person appointed by the competent authority of the Purchaser.
Subject as aforesaid, the provisions of Arbitration and Conciliation Act, 1996 (India) and statutory modifications or reenactments thereof and the rules made there under and for the time being in force shall apply to the arbitration proceedings under this clause. The venue of arbitration shall be at NOIDA/New Delhi/Delhi.”
H. Later, BFIL, which acted on behalf of respondent no. 2, in turn invited quotations for the work of design, engineering, manufacturing/procurement, transportation, unloading, site storage, erection, testing, commissioning, and performance guarantee testing of equipment in the matter of execution of the aforesaid project.
I. Pursuant to which, the appellant submitted its offer in the form of a quotation, which upon the approval of BFIL, led to the issuance of two Letters of Intent (“LOI”) by the said agency on 10th December, 2013.
J. On 20th December, 2013, the respondent no. 2 issued a Purchase Order in favour of respondent no. 1 for the execution of the aforesaid work, cost of which was estimated at Rs. 43 crores.
K. The said Purchase Order was followed by a Work Order issued by respondent no. 2 to respondent no. 1 for the services of unloading, storing, transportation, etc., for a consideration of Rs. 4.5 crores.
L. As a consequence of above, the appellant herein re-issued a Purchase Order and Work Order on 20th December, 2013 in favour of respondent no. 1 pursuant to directions of respondent no. 2 and BFIL.
M. The aforesaid Work Order and Purchase Order were followed by a Tripartite Agreement dated 06th June, 2014, executed between BFIL, respondent no. 2, and the appellant, whereby BFIL assigned all its rights, obligations, and liabilities arising under the previous agreement in favour of the respondent no. 2.
N. In the aforesaid background, BFIL ceased its existence as the EPC Contractor for the project in question, and the appellant commenced coordination directly with respondent no. 2 for the execution of work in the matter of the project installation.
O. Thereafter, the appellant became the EPC Contractor in place of BFIL pursuant to the Supply Contract executed between the appellant and respondent no. 2 on 03rd July, 2015.
P. The consequence of above was that respondent no. 2 transferred the obligations of BFIL to the appellant, which had been previously assigned to respondent no. 2 under the Tripartite Agreement dated 06th June, 2014.
Q. In the matter of the aforesaid execution of the contract, since disputes arose between the parties, respondent no. 1 took recourse to the arbitration clause and issued a notice dated 14th April, 2017.
R. Respondent no. 1 initiated proceedings under Section 11 of the Arbitration and Conciliation Act, 1996, seeking appointment of a Sole Arbitrator for adjudication of the dispute inter se the appellant and respondent nos. 1 and 2, which came to be allowed vide order dated 18th July, 2017 and a Sole Arbitrator was appointed.
S. The Sole Arbitrator, accordingly, considered the rival claims of the parties and passed an award on 16th October, 2019.
T. The respondent no. 1, herein also preferred a counter-claim for liquidated damages before the Arbitrator.
U. The learned Arbitrator dismissed the counterclaim and disposed of the proceedings with the following observations:
“The Respondent no. 1 or 2 are held jointly and severally liable and thus directed to pay the Claimant a sum of Rs. 6,56,84,982/-(Rs. 5,73,15,078/- + Rs. 83,69,904/-) with interest @ 38.85% under the MSME Act, 2006 from the date of the award till the date of payment. The Respondent no.1 or 2 are directed to pay the sum awarded in favour of the Claimant within 6 weeks from the date of the award. In case this is not done by the Respondents within the period of 6 weeks, the Respondents will be liable to pay the said amount along with interest at the rate of 2% higher than the current rate of interest prevalent on the date of award as per Section 31(7) (b) of the Arbitration and Conciliation Act, 1996 from the date of award to the date of payment.
Both the parties are to bear their own cost of litigation.
The Arbitration proceedings are thus disposed of in terms of this award.
The deficient stamp duty is required by either of the parties to be got ascertained and paid on this Award.”
V. The details of the award as awarded by the learned Arbitrator can be summarized as under:
a. As against the outstanding amount towards supply and services payable by the appellant and respondent no. 2 jointly and severally under the ‘Group of Companies Doctrine’ had been assessed at Rs. 5,73,15,078/-. Insofar as Claim No. 4, viz., the cost incurred by respondent no. 1 for keeping the bank guarantee alive, is concerned, a sum of Rs. 83,69,904/- came to be awarded,
b. The interest component is evaluated at 38.85% on the aforesaid principal amount, i.e., Rs. 5,73,15,078/- plus Rs. 83,69,904/- from the date of the award till the actual date of payment.
c. The appellant and respondent no. 2 were directed to pay the award sum within a period of six weeks, failing which the appellant and respondent no. 2 were directed to pay the award sum at the rate of 2% higher than the current rate of interest prevailing on the date of award, from the date of the award to the date of payment.
W. The appellant, being aggrieved by the arbitral award, preferred proceedings under Section 34 of Act of the 1996, being O.M.P. (COMM) 246/2022, which was dismissed vide the impugned order, as such, the present appeal came to be filed.
SUBMISSIONS OF THE APPLEANT
The learned counsel for the appellant would invite our attention to the scheme of Sections 34 and 37 of the Act of 1996 so as to urge that the learned Single Judge, while exercising powers under Section 34 of the Act of 1996, has travelled beyond the scope of the aforesaid provisions.
He would claim that a perusal of paragraphs 14, 16, 18, and 19 of the judgment in the matter of MMTC Ltd. v. M/s Vedanta Ltd., (2019) SCC OnLine SC 220, would suggest that the appellant was has no privity of contract, could not have been held liable for payments to be made jointly and severally along with the original respondent no. 2.
According to the learned counsel for the appellant, the Tripartite Agreement dated 06th June, 2014 reflects that BFIL was the original EPC Contractor, who was allegedly later substituted by the appellant. To appreciate the scope of work under the contract in question, it was necessary that BFIL, i.e., the earlier EPC Contractor, ought to have been impleaded as a party.
He would further urge that, since the appellant was neither a party to the arbitration agreement nor a consenting party to the arbitration, the appellant ought not to have been held jointly and severally liable along with respondent no. 2 for the payments claimed by respondent no. 1.
From the record, it is sought to be demonstrated that the appellant merely acted as a communicator between respondent no. 1 and 2 and that in view of the recitals of the agreement, no financial liability can be fastened upon the appellant.
It is urged that respondent no. 1 always received payment from respondent no. 2, and the only role attributed to the appellant in the execution of the project in question was that respondent no. 1 would submit its bills along with progress reports to the appellant, and the appellant, in turn, after certifying the same, would submit the same to respondent no. 2 for further processing and release of payments.
It is further urged that the Group Companies Doctrine was not at all attracted in the factual matrix of the present case. According to the learned counsel for the appellant, the appellant is in no way connected with respondent no. 2, either directly or indirectly, but for the extent of acting as a company that facilitated as the EPC Contractor and its role was restricted only to certification of the bills and monitoring of the progress qua the project in question. In such an eventuality, the very essentials of the Group Company Doctrine are not satisfied and that being so, it is urged that the very award and the impugned judgment under Section 34 of the Act of 1996 goes contrary to the scheme of Sections 34 of the Act.
In the aforesaid background, it is urged that, having regard to the settled position of law, at the most, respondent no. 2, could be proceeded against and not the appellant, particularly when the observations go against the public policy of India.
It is claimed that though it is the case of respondent no. 1 that a notice invoking the arbitral proceedings was issued before the commencement of arbitration, however, no such notice was ever received by the appellant, and the appellant was directly impleaded as a party in the proceedings under Section 11 relating to the appointment of the Arbitrator.
It is sought to be pointed out from the record that though the appellant appeared before the learned Arbitrator on the initial five dates, its subsequent appearance was not required, as the appellant under the arbitration agreement was not liable for any such liability.
It is urged that it was the failure of the arbitrator to put to appellant the appropriate notice in relation to the arbitral proceedings and that being so, the arbitrator has passed the award against the appellant without the appellant being proceeded/declared ex-parte or otherwise, according to him, this procedural lapse is a serious illegality rendering the arbitral award illegal.
According to the learned counsel for the appellant, even the award of interest is expressly illegal, as interest at the exorbitant rate of 38.85% has been awarded without there being any basis.
The learned counsel for the appellant so as to substantiate the aforesaid contentions has relied on the following judgments:
Cox & Kings Ltd v. SAP India Pvt. Ltd. & Anr. [(2024) 4 SCC 1]
Hindustan Petroleum Corporation Ltd. v. BCL Secure Premises Pvt. Ltd. [(2026) 3 SCC 711]
Vingro Developers Pvt. Ltd. v. Nitya Shree Developers Pvt. Ltd. [(2024) SCC OnLine Del 486]
Ajay Madhusudhan Patel & Ors. v. Jyotrindra S. Patel & Ors. [(2025) 2 SCC 147
Mittal Pigments Pvt. Ltd. v. Gail Gas Ltd. [(2023) SCC OnLine Del 977]
Lovely Benefit Chitfund & Financev. Puran Dutt Sood & Ors. [ILR (1983) I Delhi 594]
M/s Savio Industrial & Structural Corporation v. Southern Railway [2016 SCC OnLine Mad 30027]
Lion Engineering Consultants v. State of Madhya Pradesh & Ors. [(2018) 16 SCC 758]
State of Chhattisgarh v. Sal Udyod Private Limited [(2022) 2 SCC 275]
MTNL v. Canara Bank [(2020) 12 SCC 767
ONGC v. M/s Discovery [Civil Appeal No. 2042 of 2022]
Bharti Cellular Limited v. Assistant Commissioner of Income Tax [(2024) 8 SCC 608]
Vivek Automobile v. Indian INC. [(2009) 17 SCC 657
Kuchwar Lime & Stone Co. v. Dehri Rohtas Light Railway & Co. Ltd. [1968 SCC OnLine SC 267]
Ssangyong Engineering & Customs Company Ltd. v. National Highway Authority of India [(2019) 15 SCC 131]
Trans Engineers India Private Limited v. Ostuka Chemicals (India) Pvt. Ltd. [O.M.P (COMM) 310/2022, IA No. 11536/2022 & 1013/2023]
SUBMISSIONS OF THE RESPONDENTS
While countering the aforesaid submissions, the learned counsel for the respondent would urge that the claim put forth by the appellant is beyond the scope of interference permissible under Section 37 of the Act of 1996.
According to the learned counsel, the parameters which have been laid down in a catena of judgments defining the scope of Section 37 of the said Act do not permit re-appreciation of the factual matrix, the evidence or the entire case in exercise of powers under Section 37 of the Act.
According to the learned counsel, the burden is on the appellant to demonstrate that the award, so as to judgment under Section 34 of the Act delivered by the learned Single Judge, goes contrary to the public policy of the country.
He would further claim that the grounds which are sought to be canvassed in the present appeal were never urged before the learned Arbitrator. In view of the law laid down by the Apex Court in the matter of Union of India v. Susaka (P) Ltd and Ors. (2017) SCC OnLine SC 1436, it is not open for the appellant to raise the contentions which were not canvassed before the learned Arbitrator.
The further contention of the respondents is that it was the appellant who had issued the Work and Purchase Order to the respondent no. 1 and, in such circumstances, the appellant had also made certain payments to respondent no. 1, which indicates the existence of a contract between the parties.
The very transactions and the Work and Purchase Orders issued by the appellant speak of the appellant being an active and interested party to the contract.
ANALYSIS AND CONCLUSION
Having considered the rival submissions, the foremost issue that warrants consideration is the scope to which the appellant can agitate or canvass its grievance before this Court under Section 37 of the Act of 1996.
Rightly so, the learned counsel for the respondents has raised an objection to the very conduct of the appellant in not resisting the claim before the learned Arbitrator and the grounds were raised for the first time before the Court in proceedings under Section 34 of the Act of 1996.
In the matter of Azizur Rehman Gulam and Others v. Radio Restaurant and Others (2023) SCC OnLine Bom 2320, the Bombay High Court, while dealing with an identical issue, recorded a finding that the Court taking up the proceedings under Section 37 of the Act of 1996 cannot travel beyond the restrictions laid down under Section 34 of the said Act.
In such an eventuality, the Court cannot undertake an independent assessment of the merits of the award and while exercising powers under Section 34 of the Act, the Court cannot exceed the scope of the statutory mandate.
The aforesaid issue stands further endorsed by the Apex Court in the matter of Union of India v. Susaka (P) Ltd. and Ors.(2017) SCC OnLine SC 1436, wherein the Apex Court held that if a plea was available to a party during the arbitral proceedings but was not raised before the learned Arbitrator, such plea is not open to be canvassed either in proceedings under Section 34 or in an appeal under Section 37 of the Act.
The aforesaid judgment is rightly so referred by the learned Single Judge for the purpose of restricting the scope of consideration while dealing with the claim of the appellant in exercise of powers under Section 34 of the Act of 1996. Paragraph 27 of the aforesaid judgement reads thus:-
“27.If a plea is available, whether on facts or law, it has to be raised by the party at an appropriate stage in accordance with law. If not raised or/and given up with consent, the party would be precluded from raising such plea at a later stage of the proceedings on the principle of waiver. If permitted to raise, it causes prejudice to other party. In our opinion, this principle applies to this case. "
The learned Judge, while dealing with the claim of the appellant, has considered issues such as the scope of Section 34 of the Act, the availability of the MSME forum to the party, the merits of the matter, the applicability of the Group Company Doctrine, the restrictions on claims against respondent no. 1, and the award of interest.
As far as the issue relating to the MSME forum and the Group Companies Doctrine, which is sought to be canvassed by the appellant, is concerned, it is the contention of the appellant that it is raising a question of law based on the admitted factual matrix.
According to him, there is an absence of privity of contract with the respondent and, in such an eventuality, the inference drawn that the appellant is part of the group company, i.e., respondent no. 2, is without any basis.
In the case at hand, the status of the present appellant under the Agreement dated 3rd July, 2015 was that of an EPC Contractor.
The nature of the obligations cast upon the appellant, as could be inferred from the recitals of the agreement itself, clearly indicates that the appellant was a party to the proceedings.
Once it could be inferred from the record that the appellant had made payment to respondent no. 1 and along with respondent no. 2, had acted in honouring the contract, towards payment for the execution of work carried out by respondent no. 1, the factual inference drawn for invoking the Group Company Doctrine appears to be justified.
Thus, the reliance placed by the learned Single Judge on the relevant observations contained in paragraphs 96, 123, 127, and 132 of the judgment of the Apex Court in Cox and Kings Ltd. v. SAP India Pvt. Ltd., (2023) SCC OnLine SC 1634, is quite justified.
The relevant paragraphs are reproduced below:-
“96.An arbitration agreement encapsulates the commercial understanding of business entities as regards to the mode and manner of settlement of disputes that may arise between them in respect of their legal relationship. In most situations, the language of the contract is only suggestive of the intention of the signatories to such contract and not the non-signatories. However, there may arise situations where a person or entity may not sign an arbitration agreement, yet give the appearance of being a veritable party to such arbitration agreement due to their legal relationship with the signatory parties and involvement in the performance of the underlying contract. Especially in cases involving complex transactions involving multiple parties and contracts, a non-signatory may be substantially involved in the negotiation or performance of the contractual obligations without formally consenting to be bound by the ensuing burdens, including arbitration. xxx
123.The participation of the non-signatory in the performance of the underlying contract is the most important factor to be considered by the Courts and tribunals. The conduct of the non-signatory parties is an indicator of the intention of the non-signatory to be bound by the arbitration agreement. The intention of the parties to be bound by an arbitration agreement can be gauged from the circumstances that surround the participation of the non-signatory party in the negotiation, performance, and termination of the underlying contract containing such agreement. The UNIDROIT Principle of International Commercial Contract, 201679 provides that the subjective intention of the parties could be ascertained by having regard to the following circumstances:
(a)preliminary negotiations between the parties;
(b)practices which the parties have established between themselves;
(c)the conduct of the parties subsequent to the conclusion of the contract;
(d)the nature and purpose of the contract;
(e)the meaning commonly given to terms and expressions in the trade concerned; and
(J)usages. xxx
127.In Cox & Kings, Surya Kant, J. observed that Reckitt Benckiser fixed a higher threshold of evidence for the application of the Group of Companies doctrine as compared to earlier decisions of this Court. This Court's approach is Reckitt Benckiser is indicative of the fact that the mere presence of a group of companies is not the sole or determinative factor to bind a non-signatory to an arbitration agreement. Rather, the Courts or tribunals should closely evaluate the overall conduct and involvement of the non-signatory party in the performance of the contract. The nature or standard of involvement of the non-signatory in the performance of the contract should be such that the non-signatory has actively assumed obligations or performance upon itself under the contract. In other words, the test is to determine whether the non-signatory has positive, direct, and substantial involvement in the negotiation, performance, or termination of the contract. Mere incidental involvement in the negotiation or performance of the contract is not sufficient to infer the consent of the non-signatory to be bound by the underlying contract or its arbitration agreement. The burden is on the party seeking joinder of the non-signatory to the arbitration agreement to prove a conscious and deliberate conduct of involvement of the non-signatory based on objective evidence. xxx
132.We are of the opinion that there is a need to seek a balance between the consensual nature of arbitration and the modern commercial reality where a non-signatory becomes implicated in a commercial transaction in a number of different ways. Such a balance can be adequately achieved if the factors laid down under Discovery Enterprises are applied holistically. For instance, the involvement of the non-signatory in the performance of the underlying contract in a manner that suggests that it intended to be bound by the contract containing the arbitration agreement is an important aspect. Other factors such as the composite nature of transaction and commonality of subject matter would suggest that the claims against the non-signatory were strongly interlinked with the subject-matter of the tribunal's jurisdiction. Looking at the factors holistically, it could be inferred that the non-signatories, by virtue of their relationship with the signatory parties and active involvement in the performance of commercial obligations which are intricately linked to the subject-matter, are not actually strangers to the dispute between the signatory parties.”
The learned Single Judge has not only referred to certain recitals in the Tripartite Agreement but has also, in law, rightly recorded a finding against the appellant and in favour of respondent no. 1 regarding the applicability of the Group Company Doctrine.
The relevant observations are reproduced below:
“54.Thus, whether the arbitrator has rightly invoked the 'Group of Companies' doctrine is to be seen from factors such as mutual intent, relationship between the signatories and non-signatories, commonality of subject matter, composite nature of transactions and performance of the contract.
55.In the present case, the arbitration clause is encapsulated in the General Terms and Conditions in consonance with the agreement executed between the respondent nos. 1, 2 and BFIL, in the year 2012. The petitioner was not a party to the said contract and the petitioner only became a party in the year 2013 by way of Letter(s) of Intent dated 10.12.2013 issued by the BFIL for the purpose of design, manufacturing, and commissioning of equipment for the complete project on behalf of respondent no. 2. As per the contract executed between the BFIL and the petitioner, the petitioner was to conduct a reliability test of equipment and items for complete Coal Handling System Package. In addition, the petitioner was also appointed for the purposes of checking invoices and clearing them (Ref. Para 65 of the Impugned Award). Thereafter, BFIL exited the said contract and assigned all its rights, liabilities, and obligations in favor of respondent no. 2 by way of the Tripartite Agreement dated 06.06.2014. It is an admitted position that BFIL was appointed as an EPC Contractor by the respondent no. 2. Since, BFIL exited the project, the rights and liabilities of the BFIL was transferred in favor of the petitioner by way of Supply Contract dated 03.07.2015.
56.Admittedly, the role of the petitioner was to issue purchase and work order(s) to respondent no. 1 and also to check the invoices raised by respondent no. 1 and thereafter, recommending payments of the invoices raised to the respondent no. 2. The petitioner played a pivotal role in the overall execution of the project, even though it was not originally a party to the contract(s) between respondent nos. 1, 2, and BFIL. The petitioner was responsible for issuing the purchase and work orders that formed the basis for the invoices raised by the involved parties. Following this, the petitioner reviewed and verified the invoices to ensure their completeness. Only after the petitioner's clearance of these invoices did respondent no. 2 proceed with the release of payments to respondent no. 1. In my view, considering the role, obligations and responsibilities of the petitioner, the petitioner is indeed a veritable party to the contract(s). On this basis, the learned arbitrator has rightly concluded that the petitioner is a group company of respondent no.
2.Therefore, I find no infirmity in the said finding.”
In this background, the contentions raised by the appellant cannot be accepted and are liable to be rejected.
The award of the claim by the learned Arbitrator was based on an analysis of the expert’s report and the obligations under the agreement, so also the conduct of the parties.
The aspect of interest in the matter is based on the status of respondent no. 1 as an MSME registered company.
The learned Single Judge, while dealing with the aspect of interest, has relied upon the judgment of the Delhi High Court in the matter of Indian Highways Management Company Limited v. SOWIL Limited, (2021) SCC OnLine Del 5523 and, from paragraph 72 onwards of the judgment of the learned Single Judge, it has been held that the provisions of Sections 15 and 16 of the Micro, Small and Medium Enterprises Development Act, 2006 (in short “MSME Act”) are independent of Section 18 and that in order to attract the rigour of Sections 15 and 16, it need not be that the dispute redressal mechanism provided under Section 18 of the MSME Act be initiated.
In such an eventuality, the interest contemplated under Section 16 can be granted even in ad hoc arbitration proceedings.
In regard to the award of interest, it was rightly relied upon on the very object with which the statute, viz., the MSME Act, was enacted.
In the aforesaid background, having regard to the overall facts of the matter, viz., the claim put forth by respondent no. 1, the award passed by the learned Arbitrator, the appellant having chosen not to contest the claim on merits and rather had abandoned its right to effectively defend the claim before the learned Arbitrator, its stand before the learned Single Judge under Section 34 of the Act of 1996, and the position of law that the appellant cannot raise a plea, which was not agitated before the learned Arbitrator, in proceedings under Sections 34 or 37 of the Act of 1996, in our opinion, the findings recorded by the learned Arbitrator and that of the learned Single Judge are totally in tune with the provisions of the Act of 1996 and the MSME Act.
That being so, we see no reason to infer that the award or that of the judgment delivered under Section 34 of the Act of 1996 can be termed as going against the public policy of this country.
As such, the appeal lacks merit and stands dismissed.
Parties to bear their own costs.
Pending applications also stand disposed of.
