High CourtsSingle Bench(2024) 12 DEL CK 1874

Shayan Lahiri vs Mr Pramod Kumar Jain President, Rajat Jain Cooperative Group Housing Society & Anr.

Delhi High Court · Decided on 24 December 2024

HON’BLE JUDGES
Manoj Jain, J
RESULT
Disposed Of
CASE NUMBER
CONT.CAS(C) 1300/2024

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

11 paragraphs · 409 words

CM APPL. 76427/2024 (exemption)

Exemption allowed subject to all just exceptions.

CONT.CAS(C) 1300/2024 & CM APPL. 76426/2024 (early hearing)

1.

Respondent No.1 i.e. President of the Cooperative Group Housing Society in question has moved the present application seeking early hearing.

2.

It is submitted that the “Balcony Extension Project” is underway as per DDA guidelines. It is a time-bound process and the Management Committee has already on boarded the Contractor for construction. It is submitted that when the matter was taken up by this Court on 21.08.2024, the respondents were directed to maintain status-quo. It is submitted that the above said order of status-quo is coming in the way of the respondent Society to raise construction to extend the balconies of the other residents.

3.

Learned counsel for the petitioner has joined the proceedings through video conferencing and submits that each block has ten stories and the petitioner is resident of first floor and while extending the balcony of the other residents situated at upper floors, there might be some damage caused to the balcony of the petitioner and as per the order passed by learned Division Bench on 08.05.2024, the respondents have to ensure that such damage is to be repaired immediately.

4.

During course of the arguments, learned counsel for the respondent Society submitted that he has requisite instructions in this regard to ensure repair/restoration and moreover, the above said order dated 08.05.2024 is also very clear and in case there is any damage to the balcony of the petitioner, the respondent Society is required to ensure that such damage is repaired and the balcony is restored to its original position as it existed when the construction in the above said block had started. He also states that before doing any construction in the above said block, the photographs shall be taken and would be shared with the petitioner as well to repel any apprehension in the mind of petitioner.

5.

Learned counsel for the petitioner submits that in view of the above statement and assurance given by the respondent Society, he does not press the present contempt petition.

6.

In view of the above, while vacating the above said status-quo order, in view of the statement made by learned counsel for the petitioner today, the present petition is disposed of as not pressed.

7.

Needless to say, the respondent Society shall remain bound by the above said assurance/statement.

8.

The next date of 16.05.2025 is cancelled.