High CourtsSingle Bench(2003) 04 GUJ CK 0043

Shantilal Ghevarchand Jain vs State of Gujarat

Gujarat High Court · Decided on 29 April 2003

HON’BLE JUDGES
Jayant M. Patel, J
RESULT
Allowed
CASE NUMBER
Special Civil Application No. 10757 of 2002

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

42 paragraphs · 947 words

Jayant Patel, J.—Leave to produce the notification, dated 17.11.2000 issued by the Urban Development & Urban Housing Dept, Govt. of

Gujarat, Gandhinagar.

2.

Rule. Mr. Desai waives service of rule on behalf of respondent Nos 3 & 4 and Mr. K.T. Dave, Ld. AGP waives service of rule on behalf of

respondent Nos 1 & 2. With the consent of learned advocates for parties matter is taken up for hearing.

3.

The only point involved in this petition is that whether the State Govt is justified in sanctioning the scheme so far as the subject matter of land is

concerned interpreting the order, dated 31.7.97 passed by this court in SCA No. 2620/97.

4.

Short facts of the case are that the petitioner had made a representation to the authority for considering his grievance against the finalisation of

TP Scheme. At that stage the petitioner had preferred SCA No. 2620/97 before this court and in the said petition this court ultimately on 31.7.97

after hearing both sides passed the following order:

Heard Mr. Chhaya for the petitioner and Mr. Sompura with Mr. Patel for respondent Nos 1 to 3 and Mr. P.G. Desai for respondent No. 4. The

respondents as well as petitioner have made their submissions.

Rule has already been issued in this matter on 2.4.97. After the matter was heard for some time Mr. Chhaya makes a statement that in pursuance

of the Division Bench judgment reported in Naranbhai Lallubhai Patel Vs. B.S. Oza and Others, the petitioner would like to make a representation

to the State Govt u/s 65 of the Gujarat Town Planning and Urban Development Act. He states that the representation will be made within one

week from today. On the same being made it will be considered and decided in accordance with law expeditiously but preferably within four

weeks from the date of receipt of the same. Till then the Town Planning Scheme will be deemed to have not been finalised with respect to the

concerned plot. This is in view of the statusquo granted earlier on 2.4.97. Rule is made absolute to that extent with no order as to costs.

5.

In view of the fact that the aforesaid operative direction was to consider and decide the representation and such decision was also to be taken

preferably within a period of four weeks from the date of receipt of the same the court had observed that till then the scheme will be deemed to

have not been finalised with respect to the concerned plot and, therefore, the petition was disposed of.

6.

The State Govt as per the aforesaid direction had to decide the representation within stipulated time limit and until the representation is decided

within stipulated time limit the scheme was not to be finalised so far as the plot in question is concerned. However, the notification shows that the

direction is interpreted otherwise by the State Govt in as much as no decision of the State Govt is referred to and on the contrary the operative

sanction of the preliminary scheme at Cl.(ii) states that ""this sanction is subject to final decision of aforesaid order, dated 31.3.97 of this court in

SCA No. 2620/97 and other matters"". In this petition the other proceedings are not much relevant but the aforesaid clearly goes to show that the

State Govt has not considered that the SCA No. 2620/97 was finally disposed of by the court and therefore there was absolutely no justification

nor any justification to make the scheme subject to final decision of SCA No. 2620/97. On the contrary, what was contemplated was that the

authority had to take decision and thereafter the scheme was to be sanctioned. In the present case, the notification is issued on 17.11.2000, i.e.

after the expiry of about 4 weeks and since there is no reference to any decision being taken by the State Govt upon the representation of the

petitioner in my view there is total nonapplication of mind on the part of the State authorities while sanctioning the preliminary scheme so far as the

plot which was the subject matter of SCA No. 2620/97 is concerned.

7.

In view of the aforesaid discussion, it will have to be examined as to whether the whole order for sanctioning the preliminary scheme should be

set at naught or the discretion should be exercised in such a manner which may not disturb the other part of the scheme which is already

sanctioned. As such, since there is no dispute brought on record of the case in these proceedings that in the preliminary scheme which is sanctioned

such irregularities have crept in in addition to subject matter of SCA No. 2620/97 on the part of the Govt, I am of the view that instead of

disturbing the whole order sanctioning the scheme, the following directions would meet with the ends of justice:

(i) The State Govt shall consider and decide the representation which was already made by the petitioner pursuant to the order, dated 31.7.97

passed in SCA No. 2620/97 as early as possible preferably within a period of two weeks from the date of receipt of writ of this court.

(ii) After the decision is rendered by the State Govt and if it ultimately results into modifying the preliminary scheme proper declaration shall be

made by the State Govt in accordance with law within a period of one month thereafter.

(iii) Till the State Govt takes decision as indicated earlier the statusquo qua the land in question shall be maintained by both sides.

8.

Petition is allowed to the aforesaid extent. Rule is made absolute accordingly. There shall be no order as to costs.