Tribunals and CommissionsDivision Bench(2024) 01 RERA CK 4322

Sh. Sunil Kumar Baweja vs M/s Diamond Multistate Co-operative Group Housing Society Limited

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 30 January 2024

RESULT
Disposed Of
CASE NUMBER
Com/03/10/2022
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

41 paragraphs · 1,923 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

A complaint was filed in FORM ‘M’ on 20.10.2022 by Sh. Sunil Kumar Baweja (hereinafter referred as “Complainant”) stating that in the year 2018, he had approached M/s Diamond Multistate Co-operative Group Housing Society Limited (hereinafter referred to as “Respondents or Respondent Society”) for booking of a residential unit in the Respondents project, “Delhi Co-operative Housing Scheme”, L-Zone, Dwarka, Delhi. This project was promised to be developed by the Respondents under the Land Pooling Policy (LPP) of DDA.

2.

The Respondents issued welcome letter dated 03.04.2018 for the proposed flat of 820 sq. ft. area to the Complainant.

3.

The Complainant has paid Rs.3,50,000/- (Rupees Three Lakh Fifty Thousand only) to Respondents against the proposed flat of 820 sq. ft. area in their project “Delhi Co-operative Housing Scheme” in two instalments. However, the Respondents have refunded Rs.50,000/- in April,2022.

4.

The Complainant has stated that since the Respondents do not have any license and/or approval from the concerned Authorities for construction of the project and as project is delayed, he is seeking refund from the Respondents.

5.

A preliminary hearing in the case was held on 28.11.2022 and a notice to the Respondents was issued on 20.02.2023.

6.

The matter was further heard in several hearings dated 20.04.2023, 06.07.2023, 29.08.2023 and 21.11.2023. The Respondents filed their written submission on 26.07.2023.

7.

We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of Respondents are summarized as under:

i.

The Respondents have been in the business of construction and development for more than a decade and have successfully delivered projects in the NCR region and are developing many projects which are nearing completion in accordance with the law.

ii.

In the year 2017, the Respondents launched project namely ‘Delhi Co-operative Housing Scheme’. The Complainant approached the Respondents for booking a residential apartment in the said project and accordingly signed and executed booking application form out of his own free will.

iii.

The Respondents have every intention to develop the said project but owing to the government policies, procedural and administrative factors which are beyond the control of the Respondents, they could not obtain 'Land Transfer Certificate' from DDA which is a pre-requisite for developing the project.

iv.

As soon as the Respondents realized that the project is delayed, an option was given to the investors to either stay invested and await for requisite clearances from the competent authorities or opt for a refund. The Complainant opted for refund.

v.

The Respondents have refunded part payment of Rs.50,000/- to the Complainant and is willing to refund the balance amount of Rs.3,00,000/-(Rupees Three Lakh Thousand only) to the Complainant with a bonafide intention in monthly equitable instalments.

vi.

The Respondents submitted that the Complainant has sought relief of refund of the amount paid and not alongwith interest. Therefore, the Complainant is entitled to refund of Rs.3,00,000/- only.

Analysis and Consideration:

8.

A perusal of the documents available on record shows that the Respondents have issued two receipts dated 03.04.2018 and 17.04.2018 acknowledging deposits of Rs.2,00,000/- and Rs.1,50,000/-, respectively. Hence, payment of Rs.3,50,000/-(Rupees Three Lakh Fifty Thousand only) by the Complainant to the Respondents is a recorded fact.

9.

During hearing of the case, the Complainant submitted that the Respondents have refunded part payment of Rs.50,000/- to him in April, 2022. Now, he is seeking refund of balance amount of Rs.3,00,000/-.

10.

The Real Estate (Regulation and Development) Act, 2016 (hereinafter referred as “the RE (RD) Act, 2016 or Act”) has been enacted to ensure efficiency and transparency in real estate sector. The Act has made it obligatory for promoters to complete the project within stipulated time.

11.

In the RE (RD) Act 2016, an exhaustive definition of "promoter" is provided section 2. The sub-clause (iv) of clause (zk) of section 2 defines “promoter” as:

“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”

12.

The Respondent Society is a Multi-State Co-operative Society, which advertised membership, made members for their housing projects and collected monies from them. The Respondents thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.

13.

The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.

14.

An allottee/house buyer can seek refund of amount invested/deposited with the promoter under section 18 of RE (RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest including compensation and also under section 12 of RE (RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the project either through advertisement or otherwise.

15.

The Respondents in their reply have submitted that Complainant has sought relief of refund of the amount paid and not alongwith interest. Therefore, the Complainant is entitled to refund of Rs.3,00,000/- only.

16.

In the present complaint, the Complainant intends to withdraw from the project on the ground of delay and is seeking refund of the balance amount paid to the Respondents in respect of above-mentioned unit.

17.

Section 18 (1) of the Act deals with the situation if the promoter fails to complete or give possession either in terms of the agreement for sale or complete the project by the date specified therein etc. Under this section, the allottee/ homebuyer holds an unqualified right to seek refund of the amount with interest at such rate as may be prescribed. It also clearly states that in case the allottee/ home buyer does not wish to withdraw from the project he shall be paid interest for every month of delay, till the handing over of the possession, at such rate as may be prescribed.

18.

Under section 18(1) of the RE (RD) Act, 2016 which reads as under:

“Section 18: - Return of amount and compensation

18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —

(a). in accordance with the terms of the agreement for sale or, asthe case may be, duly completed by the date specified therein; or

(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”

19.

It is pertinent to mention here that the preamble of Act states that the Real Estate Regulatory Authority is established with the purpose of regulation and promotion of real estate sector and to protect the interest of consumers in real estate sector. If the Complainant has sought relief of refund but did not mention refund along with interest in his complaint, it does not take away his right to get the interest along with refund of the amount paid to the Respondents that too five or four years back. Section 18 clearly states that if any allottee wishes to withdraw from the project, he shall be indemnified by the refund along with interest at the prescribed rate. Therefore, the contention of the Respondents that the Complainant is only entitled for refund and not interest alongwith it is rejected in the interest of justice.

20.

As stated earlier, section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:

“Section 12:-Obligations of promoter regarding veracity of the advertisement or prospectus

Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”

21.

The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainant but also misled him at the time of allotment itself by concealing information that they do not have any license or approval from the concerned authorities for construction of project and that no housing project can be developed on agricultural land proposed to be purchased by them. They also did not disclose the risks associated with the project to the society members including the Complainant. It is a pure simple case of giving part information and cheating the members of public at large.

22.

On perusal of the documents on record and submissions made by the parties, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. And, therefore, the Complainant is entitled to get the refund of the amount paid by him alongwith interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of sections 18 and 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016.

23.

The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., Civil Appeal Nos. 6745-6749 of 2019).

24.

In the light of the aforesaid, we direct the Respondents, M/s Diamond Multi State Co-operative Group Housing Society Limited to refund the balance principal amount, Rs.3,00,000/- (Rupees Three Lakh Only) to the Complainant, Sh. Sunil Kumar Baweja, within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.

25.

The case is disposed of accordingly.

26.

No order as to costs.