AI Structured Summary
Not yet generated for this judgment
Judgment
A complaint was filed in FORM ‘M’ on 10.12.2024 by Sh. Sudhir Pandey and Mrs. Meenu Tiwari (hereinafter referred to as ‘Complainants’) under section 31 read with section 18 of Real Estate (Regulation and Development) Act, 2016 (herein after referred as RE(RD) Act, 2016 or the Act) stating that they booked a 3BHK flat in 2015( herein after referred to as ‘subject unit’) in the housing project, ‘Antrix Victorian County’ (hereinafter referred to as ‘the project’) promoted by ‘Antrix Society’, (hereinafter referred to as ‘the Respondents or Respondent Society) in L-Zone,Dwarka, New Delhi.
The Complainants booked a 3BHK Apartment admeasuring 1600 sq. ft. on 19th Floor of Tower-2 in the subject project and paid a sum of Rs.10,97,020/-(Rupees Ten Lakh Ninety Seven Thousand and Twenty Only) to the Respondents.
The Complainants placed on record copies of letter dated 12.02.2015 and receipts of money collected by the Respondents for constructing of flats in their project ‘Antrix Victorian County’.
The Complainants submitted that the Respondents have failed to deliver possession of the said flat as promised by them. Therefore, they seek refund of Rs.10,97,020/- (Rupees Ten Lakh Ninety Seven Thousand and Twenty Only).
A preliminary hearing in the case was held on 03.02.2025. A Notice of complaint was sent to the Respondents on 31.12.2024 via registered post and on 17.01.2025 via e-mail.
The matter was subsequently heard on 03.03.2025, 07.04.2025, 19.05.2025, 06.08.2025, 09.09.2025 and 11.11.2025. The Respondents filed their reply on 09.09.2025 during the course of proceedings.
The Arguments and Submissions made on behalf of the Respondent Society are summarized as under:
The Respondents are in the business of construction and development in the Real Estate Sector.
The Respondents launched a project namely ‘Victorian County’. The Complainants approached the Respondents for booking a Residential Apartment in the said project and accordingly they signed and executed booking application form out of their own free will.
The Respondents had every intention to develop the said project but owing to the government policies and procedural and administrative factors beyond their control, the Respondents could not obtain the ‘Land Transfer Certificate’, which was a prerequisite for developing the project. As soon as the Respondents realized that the project was being delayed, they gave an option to existing investors/allottees to either stay invested and await the requisite clearances from the competent authorities or, in an alternative opt for a refund.
The Respondents are ready to refund the entire principal amount of Rs.10,97,020/- (Rupees Ten Lakh Ninety Seven Thousand and Twenty Only) to the Complainants in equal monthly installments.
I have heard the arguments of the Ld. Counsels of both the parties and perused the documents on record.
Analysis and Consideration
A perusal of the documents available on record shows that the Respondents have issued two receipts dated 12.02.2015 acknowledging deposit of Rs.2,00,000 (Rupees Two Lakhs Only) and Rs.5,51,100/- (Rupees Five Lakh Fifty One Thousand and One Hundred Only) and one receipt dated 18.03.2025 acknowledging deposit of Rs.3,45,920/- (Rupees Three Lakh Forty Five Thousand Nine Hundred Twenty Only). Hence, a total payment of Rs.10,97,020/- (Rupees Ten Lakh Ninety Seven Thousand and Twenty Only) by the Complainants to the Respondents is a recorded fact.
The Real Estate (Regulation and Development) Act, 2016 has been enacted to induce professionalism and standardization in the real estate sector, paving the way for catalyzing investments and accelerating growth of the sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a real estate project. The Real Estate (Regulation and Development) Act, 2016 is a special law enacted to address issues in the real estate sector. Therefore, all disputes between home buyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, Section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.
An exhaustive definition of "promoter" is provided under section 2(zk) of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as “RE (RD) Act, 2016 or Act”) which is reproduced below:
“2.(zk) “promoter” means,-
i)a person who constructs or causes to be constructed an independent building or a building consisting of apartments, or converts an existing building or a part thereof into apartments, for the purpose of selling all or some of the apartments to other persons and includes his assignees; or
ii) a person who develops land into a project, whether or not the person also constructs structures on any of the plots, for the purpose of selling to other persons all or some of the plots in the said project, whether with or without structures thereon; or
iii) any development authority or any other public body in respect of allottees of-
(a)buildings or apartments, as the case may be, constructed by such authority or body on lands owned by them or placed at their disposal by the Government; or
(b)plots owned by such authority or body or placed at their disposal by the Government, for the purpose of selling all or some of the apartments or plots; or
iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or
v)any other person who acts himself as a builder, coloniser, contractor, developer, estate developer or by any other name or claims to be acting as the holder of a power of attorney from the owner of the land on which the building or apartment is constructed or plot is developed for sale; or
vi) such other person who constructs any building or apartment for sale to the general public.
Explanation.- For the purposes of this clause, where the person who constructs or converts a building into apartments or develops a plot for sale and the persons who sells apartments or plots are different persons, both of them shall be deemed to be the promoters and shall be jointly liable as such for the functions and responsibilities specified, under this Act or the rules and regulations made thereunder;”.
The Respondents, thus, fall well within the definition of promoter and are therefore under all the obligations and liabilities mentioned in the Act and Rules thereunder under.
The statement of objects and reasons of RE(RD) Act, 2016 clearly states that the Act attempts to balance the interests of homebuyers and promoters by imposing certain responsibilities on both. It also seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual obligations, set minimum standards of accountability towards each other and a fast-track dispute resolution mechanism.
An allottee/home buyer can seek refund of amount invested with the promoter along with interest under section 18 of RE(RD) Act, 2016, if the promoter fails to complete the project by the date specified in Agreement to Sale and also under section 12 of RE(RD) Act, 2016 for providing misleading information.
These sections read as under:
“Section 18. Return of amount and compensation.-
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building,
(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus.-
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
In the present complaint, the Complainants intend to withdraw from the said project and are seeking refund of the amount deposited along with interest from the Respondent Society in respect subject unit under section 18(1) of the RE(RD) Act, 2016 on account of delay.
The Respondents, in complete disregard to their duties, not only failed to handover the subject unit but also misled them by concealing information regarding availability of land for raising the Project.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authority has exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).
On perusal of the documents on record and submissions made by both the parties, I am of the view that the Respondents are in contravention of both section 18 and section 12 of RE (RD) Act, 2016. Therefore, the Complainants are entitled to get the refund of the amount paid by them along with the interest at prescribed rate @ 10.80% p.a. (i.e., MCLR plus 2%) as per provisions of section 18 and section 12 of RE (RD) Act, 2016 read with Rule 15 of the NCT of Delhi (Real Estate Regulation and Development) (General) Rules, 2016 respectively.
In the light of the aforesaid, I am of the view that Complainants are entitled for refund of the amount proved to be deposited with the Respondent Society. Accordingly, I direct the Respondents Antrix Society to refund Rs.10,97,020/- (Rupees Ten Lakh Ninety Seven Thousand and Twenty Only) to the Complainants Shri. Sudhir Pandey and Mrs. Meenu Tiwari, along with interest at the rate of 10.80% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return within 45 days of issuance of this order.
The case is disposed of accordingly.
No order as to costs.