Tribunals and CommissionsDivision Bench(2020) 11 RERA CK 2963

Sh. Rahul Mehrotra & Anr. vs DLF Retail Developers Ltd.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 4 November 2020

CASE NUMBER
Comp. No.16/2020 (Case heard via Video Conference)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

4 paragraphs · 241 words

Heard Counsels for the Parties.

The Counsel for the Respondent raised the issue of maintainability of the complaint on the ground that the completion certificate of the project was obtained before commencement of the Real Estate (Regulation& Development) Act 2016 which was contested by the counsel for the complainant. During the course of hearing, it was pointed out by the counsel for the complainant that there is a change in the plan of the Unit which was offered to the complainants at the time of booking and now at the time of offer of possession and respondent is not providing him copy of present plan of the Unit. It was further submitted by the Complainant that there is a dispute of about Rs.25 Lac which the respondent is asking to be deposited at the time of taking over possession. At this stage, the Counsel for the Respondent submitted that they are having the break-up of the said amount and they are asking the interest as per observations/directions of Hon’ble National Consumer Dispute Redressal Commission’s order. Let the Respondent may file copies of both the plans stated above and the documents related to demand raised for deposit of additional amounts within a period of two weeks.

At this stage, Counsels for both the Parties have made a joint request for long adjournment as they are moving toward settlement of dispute amicably.