Supreme CourtFull Bench(1998) 11 SC CK 0038

Sector 14 Residents Welfare Association and Others vs State of Delhi and Others

Supreme Court Of India · Decided on 16 November 1998 · Citation: (1998) 8 AD 453 : AIR 1999 SC 308 : (1998) AIRSCW 3707 : (1998) 8 JT 129 : (1998) 6 SCALE 209 : (1999) 1 SCC 161 : (1998) 2 SCR 695 Supp : (1998) 8 Supreme 477 : (1999) 1 UJ 123

HON’BLE JUDGES
V.N. Khare, J · S.P. Kurdukar, J · B. N. Kirpal, J
RESULT
Allowed
CASE NUMBER
Writ Petition (C) No. 914 of 1996

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

45 paragraphs · 797 words
1.

In respect of the up gradation of sewerage management systems in the trans-Yamuna area of Delhi and Sectors 14, 14-A, 15, 15A, 16, 16-A and 17 of NOIDA this writ petition was filed in this Court. By Order dated 6 January, 1998 this Court constituted a Committee of five persons headed by Shri P.K. Kaul, former Cabinet Secretary as its Chairman to examine all the issues in detail and to submit a report.

2.

The Committee submitted its interim report on 5.03.1998. In October 1998 the said Committee has submitted its final report relating to status and options for up gradation of the sewerage management systems in the aforesaid areas.

3.

Copies of the said report were given to the learned counsel for the parties and no objection to the same has been received.

4.

We have gone through the report and, in our opinion, it merits acceptance. Apart from indicating the status of the system as of today, the said report at pages 40-44 gives the action plan for the works which are required to be undertaken and the organisations responsible for undertaking each work. At page 44 the Committee has drawn up a time frame with regard to the various activities mentioned in the action plan.

5.

As per the action plan suggested by the Committee, the authorities who are responsible for the implementation thereof have been mentioned. The persons who can be held accountable in respect thereof are as under :

Name of the Authority

Person Accountable

1.

Delhi Jal Board

(i) Chairman; and (ii) Member Secretary

2.

Delhi Flood Control & Irrigation Department

Chief Secretary, Delhi

3.

Municipal Corporation of Delhi

Chairman

4.

Delhi Development Authority

Vice-Chairman

5.

U.P. Pollution Control Board

Chairman

6.

G.D.A.

Vice-Chairman

7.

Delhi Pollution Control Board

Chairman

8.

NOIDA Administration

Chairman

9.

U.P. Jal Nigam

Chairman

10.

U.P. Industrial Development Corporation

Chairman

11.

Min. of Urban Development Govt. of NCT of Delhi

Chief Secretary, Delhi

6.

As already noticed, the time frame which has been suggested mentions that activities at Sr. Nos. 1-9 of the action plan should be completed before 31st December 1998, the activities at Sr. Nos. 10-22 are to be completed before 31.03.1999, the activities at Sr. Nos. 23 & 24 are to be completed before 30.09.1999 and activities at Sr. Nos. 25 to 34 are to be completed before 31.03.2000.

7.

We see no reason to change the time frame except that as far as activities Nos. 1 to 9 are concerned, we extend the time for completing the same by 31st January, 1999.

8.

The Central Government had u/s 3 of the Environment Protection Act constituted an Environment Pollution (Prevention and Control) Authority under the Chairmanship of Shri Bhure Lal. It will be appropriate that the monitoring of the implementation of P.K. Kaul Committee's report in the manner indicated in the action plan of the said report is undertaken by the said Bhure Lal Committee which is a statutory committee having powers to issue directions. We, therefore, direct that copies of this Order as well as of the interim and final report of the P.K. Kaul Committee be forwarded within a week to Shri Bhure Lal with a direction that the said Committee will ensure that various works mentioned in the action plan are undertaken as per schedule. The Committee will have full authority to issue appropriate directions to the various organisations who have been mentioned as being responsible for implementing different items of works as per the action plan. The Bhure Lai Committee will also examine the recommendations contained in paragraphs 5.1, 8.6 and 8.7 and other relevant paragraphs of the said report and issue such orders or directions as it may deem fit and proper.

9.

It is made clear that if any organisation fails in carrying out the directions so issued the persons mentioned as being accountable will have to satisfy this Court as to why appropriate action should not be taken for non-implementation of the directions issued. If for any reason any of these authorities are not in a position to implement or carry out any of the directions so issued, liberty is granted to approach this Court in this behalf. Subject to any orders which may be passed by this Court the directions given by Bhure Lal Committee shall be final and binding on all. Copies of the reports and this order be also sent to the aforesaid organisations.

10.

To come up for further directions in February, 1999. Spare copies of the report of the P.K. Kaul Committee shall be filed in the Registry by the Delhi Administration within one week and the Registry shall forward the copies of the report of P.K. Kaul committee and this order to the respective organisations within one week thereafter.