AI Structured Summary
Not yet generated for this judgment
Judgment
The petitioner is before this Court seeking extension of a
bank guarantee which has been issued by the 1st and 2nd
respondents in favour of the 3rd respondent. The bank
guarantee is issued specifically with respect to the
construction and supply of Ro-Ro-barge which contract was
awarded by the 3rd respondent to the petitioner.
The learned Senior Counsel appearing for the
petitioner submits that the work is almost completed and the
barge would be ready for delivery within two months. The
petitioner has also applied for extension of two months before
the 3rd respondent. In the meanwhile the bank guarantees
expire on 30.7.2017 and 3.8.2017. In the circumstance of the
bank guarantee expiring and the contract having not been
fully satisfied the 3rd respondent would invoke the same, in
which event the grant of further two months time would also
be put in jeopardy.
The learned Counsel for the respondent/Bank on
instruction submits that already SARFAESI proceedings have
been initiated against the petitioner for recovery of about
Rupees Fourteen Crores from the cash credit facility availed by
the petitioner and defaulted. The existing fund based facility
comes to a total of Rs.11.97 crores which has been defaulted
and interest has further accrued on the same. The non-fund
based facility being a letter of credit of Rupees Three crores
and the bank guarantees totaling Rupees Ten crores also have
been issued in favour of the petitioner. The bank guarantees
cannot be renewed since the other loans are said to be
defaulted and proceedings initiated.
The learned Counsel for the 3rd respondent was
directed to get instructions, which has been placed before me.
It is submitted by the 3rd respondent that the bank guarantees
were furnished against release of supply order and advance
payments to the petitioners of more than half the total
contracted amount has already been made. It is also
submitted by the 3rd respondent that the petitioner has not
met the supply order obligations, as on day, and has requested
for extension of delivery period. For considering extension of
delivery period as a pre-requisite, the bank guarantees should
also be extended. The Bank however is unwilling to extend the
bank guarantees.
The learned Senior Counsel submits that the total
dues as stated by the Bank of Rupees Fourteen Crores, is only
on a recall of the facilities granted to the petitioner. In fact the
defaulted amounts could be cleared by satisfaction of the
arrears which would be less than Rupees two crores. It is
undertaken that the entire amounts due from the 2nd
respondent, which is more than Rupees two crores would be
paid to the respondent/Bank.
In such circumstances, it is directed that the
respondents 1 and 2 consider the extension of the bank
guarantees for a further period of two months taking into
consideration all these aspects and also the fact that otherwise the petitioner would also not be able to satisfy the contract, if
the further time sought for is declined by the NPOL. This is a fit
case where the bank should take into account the over all
consideration of not putting a entrepreneur into total jeopardy
by re-calling a loan at a crucial juncture of a contract. In such
circumstances, the respondent/Bank shall consider the issue
immediately and issue a communication to the 3rd respondent.
The petitioner shall also file an undertaking before
the respondent/Bank that the entire amount received from the
3rd respondent would be paid to the 1st and 2nd respondents,
which if made a condition, the 3rd respondent shall comply with
that, on a communication being issued from the 1st and 2nd
respondents.
The Writ Petition is disposed of with the above directions.
