Tribunals and CommissionsDivision Bench(2024) 04 NCLAT CK 3720

SBL Construction Pvt. Ltd. vs IVRCL Ltd.

National Company Law Appellate Tribunal, CHENNAI Bench · Decided on 24 April 2024

CASE NUMBER
Company Appeal (AT) (CH) (Ins) No.128/2024

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

11 paragraphs · 523 words

ORDER

The works contract was executed by the Central Public Works Department for construction of academic cum residential building for IIT Bhuvaneswar on 17.08.2013 with the Corporate Debtor. The Respondent company is said to have entered into the sub contract agreement with the appellant on 04.12.2013.

The Central Public Works Department had terminated the building contract on 17.08.2023, consequently, the sub contract dated 04.12.2013 would too automatically stand terminated.

The dispute which arose from termination of contract was taken before the arbitral tribunal in relation to the work executed and the arbitral tribunal rendered the award on 11.08.2017.

The applicant who was sub contract had filed a claim before the Resolution Professional on 15.03.2019. The applicant has also submitted the claim before the liquidator on 21.08.2019 and the same has neither been rejected nor admitted.

The arbitral award was questioned in C.O.P. No.250/2017 and the same was dismissed the arbitral award as of now has become final.

In the proceedings pending before the National Company Law Tribunal by way of CP(IB) No.294/7/HDB/2017. The applicant on 27.02.2023 had filed an IA No.448/2023, seeking direction for the respondent to release the applicant’s claim amount.

On this IA No.448/2023, the Adjudicating Authority invited the objection by an order of 19.02.2024 which was supposed to be filed within 7 days. Even before expiry of 7 days’ time period as granted on 19.02.2024. The Impugned Order has been passed on 23.02.2024 i.e. within 4 days of filing of IA No.448/2023. As a result of the order dated 23.02.2024, IA No.448/2023 was dismissed.

The Impugned Order has been passed on 23.02.2024 even before the expiry period of 7 days, as it was directed to be granted by the order dated 09.02.2024 i.e. even prior to the parties could file their Written Submissions, which was otherwise supposed to be filed by 26.02.2024.

Upon the question being raised by this Tribunal, the Respondent Counsel was unable to give any logical answer as to why it was preponed by the Adjudicating Authority, though the time was granted for 7 days to file the Written Submissions, which would had otherwise expired on 26.02.2024 and the Judgment was delivered much before expiring of 7 days, because the Written Submission was directed to be filed by the Parties by an order of 19.02.2024. On this account, since it creates a doubt with regards to Judgment which was rendered by preponing the date. The Impugned Order is hereby set aside and the Appeal would stand remitted back to the National Company Law Tribunal, Hyderabad Bench, to reconsider the IA No.448/2023, as preferred in CP(IB) No.294/7/HDB/2017 and would be reconsidered on its merits and to pass an appropriate order in accordance with Law.

It is made quite clear the we have not made any observation, on merits while quashing the impugned order, thus the entire issue as raised in IA No.448/2023, shall be decided exclusively on its own merit by the National Company Law Tribunal, Hyderabad Bench. The Registry is directed to furnish the copy of this order and to inform to the National Company Law Tribunal, Hyderabad Bench, within a period of one week from today.