AI Structured Summary
Not yet generated for this judgment
Judgment
The Issue – Applicant’s case
Grievance in this application is against violation of environmental norms in setting up of a construction project – “Saviour Park”, Plot No. 108, Katori Mill, Loni Road, Mohan Nagar, Ghaziabad, UP, by Respondent No. 10 – Savfab Buildtech Pvt. Ltd., without valid Environmental Clearance (EC) and without requisite safeguards. It is further stated that EC conditions and environmental norms are being violated.
Case set out in the application is that the applicant is association of apartment owners. The project site plan was approved by the Ghaziabad Development Association (GDA) on 21.06.2011. The project falls under category 8(b) of the EIA Notification dated 14.09.2006. Proposed built up area was 1,55,000.00 sqm. State Level Environment Impact Assessment Authority (SEIAA), UP granted EC dated 04.03.2013. However, in violation of EC conditions, the Project Proponent (PP) started construction and selling of the flats to general public and also handing over possession before completion of construction. Further, EC for expansion was granted on 04.03.2021 without requisite appraisal. The PP has violated EC conditions by constructing 1102 units against 980 units sanctioned vide EC dated 04.03.2021. There is no arrangement for safe disposal of waste water and solid waste and there is violation of EC conditions in use of the diesel generators sets and maintenance of noise emission standards, effluent management and sagacious use of water including ground water and other measures to safeguard adverse impact on environment. Completion certificate has been granted on 07.04.2018 for Tower D-1 and partial completion certificate for Block- D-2 and Block D-3. The PP has dug out several groundwater extraction borewells to use fresh water in the construction process as well as for drinking purposes without requisite NOC from Central Ground Water Authority (CGWA). This is against the statement by the PP in Form-1 and Form-1A dated 03.12.2019 that no ground water will be extracted. Further violations of EC conditions alleged by the applicant are:
“(a) General Condition no 1, 15, 17, 37, 58 —The Project Proponent failed to regularly monitor the parameters related to groundwater, soil, ambient noise and DG sent noise and as pointed out by Dr. Susheel Kumar, the reports related to these parameters should have been sent on a regular basis to the MoEF&CC as part of statutory reporting, however this was never followed.
(b) General Condition no. 4 & 7 - The Project Proponent failed to submit Land use certificate, surface hydrology report and water regime report to the MoEF&CC.
(c) General Condition no. 11 - The Project Proponent failed to submit STP water bills claimed to be used for construction work to the MoEF&CC for suitable verification.
(d) General Condition no. 12 & 20 – The Project Proponent failed to submit Hazardous waste authorization certificate to the MoEF&CC.
(e) General Condition no 24- The Project Proponent failed to follow the green building concept suggested by the Indian Green Building Council, which is a part of CII-Godrej GBC since 2013.
(f) General Condition no 31 - The Project Proponent failed to place Environmental awareness related hoardings.
(g) General Condition no 38 —The project proponent failed to submit the justification for selecting alternate technologies to chlorination (for disinfection of wastewater) including methods like Ultraviolet radiations, ozonation etc. since 2013.
(h) General Condition no. 39 - The Project Proponent failed to submit detailed plantation details, including the area covered, number and species of trees planted etc. to the MoEF&CC.
(i) General Condition no. 41- The Project Proponent failed to submit structural stability certificate to the MoEF&CC. This is a critical violation as the entire basement area of the project is severely affected with heavy seepage and large number of cracks are visible in many pillars upon which structural stability of all the towers resides. The Residents of the Project have made several complaints to the Respondent No. 9; however, no action has been taken by the Project Proponent or the Respondent No. 9. The said issue has also been highlighted in the local newspapers. Copy of the photos depicting seepage and cracks in the Project is annexed herewith and marked as ANNEXURE-A-19. Copy of the newspaper clippings is annexed herewith and marked as ANNEXURE-A-20. Copy of the Minutes of the meeting held between the representatives of the residents, Project Proponent and Respondent No. 9 on 21.11.2019 is annexed herewith and marked as ANNEXURE-A-21.
(j) General Condition no 54 - The project proponent has failed to indicate that the cost of environmental activities is part of the overall project cost and additionally there is complete lack of highlighting the management issues and involvement of residents is completely ignored.
(k) General Condition no. 66 - The project proponent has failed to monitor groundwater downstream of rainwater harvesting pit nearest to STP for bacterial contamination and additionally has failed to provide hand pumps for sampling.
(l) General Condition no. 72 - The project proponent has failed to undertake Rapid EIA status for three months during the non-monsoon period as per the latest norms of the MoEF&CC.
(m) General Condition no. 72 - The project proponent has failed to obtain ISO: 14001 certification and also failed to include all general and specific conditions mentioned under this in the environmental manual to be prepared for the certification purposes and compliances.
(n) General Condition no 73 -The project proponent has failed to create corpus of funds for implementation plan under social corporate and environmental responsibility of 2% of total project cost. This condition was to be fulfilled by the Project Proponent within 1 month of EC, failing which the EC was deemed to be cancelled. The Respondent No. 2 & 3 not only failed to cancel the original EC of the Project Proponent in spite of the above violation but also grated a new EC for expansion and modification. This clearly shows that the Respondent No. 2 & 3 are hand in gloves with the Project Proponent.
xxx ………………………………..xxx …………………………….xxx
(a) General Condition 29 - The Project Proponent failed to submit a detailed report showing how much power of institution can be provided through solar energy so that use and polluting effect of DG sets can be minimized. The Project Proponent also did not make provision of solar energy as an alternative source of energy with the illumination of common areas, street lighting, gardens.
(b) General Condition 35 - The Project Proponent failed to submit report on the energy conservation measures confirming energy conservation norms finalize by the Bureau of Energy Efficiency (BEE)to incorporate details about building materials and technology, R and U factors, etc.
(c) General Condition 46 - The Project Proponent failed to ensure that all street and park lighting area least 50% solar-powered.
(d) General Condition 47- The Project Proponent was under obligation to install solar water heater with a maximum possible capacity and additionally in spite of repeated requests to the Builder, no provision for centralized water heating system has been made as Residents at an individual level cannot install solar heaters as it requires a centralized facility, such as building rooftops.
xxx ………………………………..xxx …………………………….xxx
(a) General Condition 16 - The Project Proponent has failed to install Wind breaking walls and dust-prevention curtain sat the ongoing construction site which severely affects the air quality of the surrounding area.
(b) General Condition 23 - The project Proponent has installed fully impermeable pavements at various locations across the project area where the provision of interlocking tiles was there for environment protection as the said impermeable pavements do not permit the water to seep through and in turn stops groundwater recharging and also do not allow suitable aeration and nutrition to the trees.
(c) General Condition 32 & 52 - The Project Proponent has illegally sold parking areas with no demarcation of appropriate guest parking and even the approved layout plan does not indicate designated parking areas for guests which in turn creates traffic congestion inside and outside the project area and also leads to air pollution which is in violation of the norms provided by the MoEF&CC and the building by laws.
(d) General Condition 39 - The Project Proponent has failed to follow the green belt norms across the plot boundary. A significant stretch of the project boundary is fully paved with concrete obstructing any possibility of developing a green belt in the future as well. This also compromises the air quality as well as allows noise levels to increase beyond the permissible attenuation factor(s). A copy of the photographic evidence showing violation of green belt norms is annexed and marked herewith as Annexure A-24.
(e) Specific Condition 1 & General Condition 55 - The Project Proponent has failed to provide detailed plans which was to be submitted within 1 month of the EC for safe disposal of STP sludge along with mention of ultimate disposal location, quantitative estimates and measured proposed.
(f) General Condition 61 - The Project Proponent has failed to construct roads in the project area with the use of suitably processed plastic waste.
(g) General Condition 63 - The Project Proponent has failed to give a plan about the safe disposal of biomedical waste arising out of a proposed dispensary at the project site.”
The applicant filed a representation dated 15.04.2021 to SEIAA, UP with copies thereof to MoEF&CC, State PCB and CGWA but no remedial action has been taken.
Procedural History – investigation of facts independent Committee
The matter was earlier considered on 13.08.2021. The Tribunal directed remedial action against violations. Two Committees were constituted – (i) a two-member committee comprising Additional Secretary, MoEF&CC, to be nominated by the Secretary MoEF&CC and the Chairman, CPCB to conduct functional audit of SEIAA, UP to find out how frequent blatant violations are taking place and how the situation can be remedied and (ii) a joint Committee of MoEF&CC, CPCB, SEIAA, UP, State PCB and District Magistrate, Ghaziabad to verify the factual aspects with regard to the alleged violations by undertaking visit to the site interacting with stake holders including PP.
Operative part of the order is reproduced below:-
“1to3…xxx……………………………xxx……………………………….xxx
We have heard learned Counsel for the applicant. We have also considered the question whether in absence of an appeal against the EC, the issue raised in the application can be gone into. Learned Counsel submitted that if the Tribunal finds it appropriate, the application may be treated as an appeal against EC dated 04.03.2021 as appeal will be within extended limitation period in view of orders of the Hon’ble Supreme Court, extending limitation during pandemic. He further submitted that in any case, action against violation of EC conditions is within the scope of jurisdiction under Sections 14 and 15 of the NGT Act, de hors the appellate jurisdiction. Learned Counsel for the applicant also submitted that there is large scale violation in construction projects. The constructions start before EC, built up area is expanded, groundwater is illegally extracted, proper waste management and other safeguards are not provided, open spaces are not provided and third party rights are created. Inspite of such rampant violations, ex post facto EC is granted without adequate appraisal of mitigation measures. Reference has been made to the judgments of the Hon’ble Supreme Court in Goel Ganga Developers India Pvt. Ltd. v UOI 2018) 18 SCC 257, Alembic Chemicals v Rohit Prajapati 2020 SCC OnLine SC 347 and Keystone developers v. Anil Tharthare (2020) 2 SCC 666.
Reliance has been placed on order of this Tribunal dated 24.05.2021 in Appeal No. 34/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors., wherein this Tribunal noted rampant and continuous violation of environmental norms in completion of construction projects without valid ECs and the regulatory authorities failing to prevent such violations by requiring demolition or payment of compensation. This is not checked, rule of law cannot be upheld. Reliance has also been placed on order of this Tribunal dated 08.06.2021 in OA No. 13/2021 (WZ), Shashikant Vithal Kamble v. M/s. Key Stone Properties & Ors. The relevant part of the said order is reproduced below:
4 “2. The said order further directed disconnection of water and electricity connections of the building. Ignoring these developments, the State Level Environment Impact Assessment Authority (SEIAA), Maharashtra issued Environmental Clearance (EC) on 24.01.2020 in violation of mandate of prior EC in terms of EIA Notification dated 14.09.2006 and judgments of the Hon’ble Supreme Court inter alia in Alembic Chemicals v Rohit Prajapati 2020 SCC OnLine SC 347, Keystone developers v. Anil Tharthare (2020) 2 SCC 666, Goel Ganga Developers India Pvt. Ltd. v UOI (2018) 18 SCC 257 and Bengaluru Development Authority v. Sudhakar Hegde & Ors. (2020 SCC OnLine SC 328
From the above, prima facie it appears that EC has been granted in violation of law and without any application of mind. This is not for the first time we have come across this situation. Such allegations are frequent. In Appeal No. 34/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors. which was taken up for hearing on 24.05.2021, we directed SEIAA to review its working of mechanically granting Ex-post facto EC, in violation of law. The Tribunal also constituted an expert committee to look into the violations of that particular project and recommend remedial action. The observations therein are:
“ xxx…………………xxx…………………………………..xxx
It is submitted that the construction project is illegal being without the mandatory prior EC. Ex-post facto EC is not substitute for prior EC as evaluation of impact on environment cannot be fully gone into as held by the Hon’ble Supreme Court in the case of the same PP viz. Goel Ganga Developers India Pvt. Ltd. v UOI (2018) 18 SCC 257. There are further judgements of the Hon’ble Supreme Court to the same effect in Alembic Chemicals v Rohit Prajapati 2020 SCC OnLine SC 347 and Keystone developers v. Anil Tharthare (2020) 2 SCC 666. If the construction project is without prior EC, the project has either to be demolished or if it is found that environmental damage can be restored, the project can be permitted on payment of assessed compensation on polluter pays principle which needs to be spent for restoration of the environment. The authorities have thus failed to follow the binding law.
Since we are coming across the grievance of continuous violation of environment norms in construction projects being completed without prior EC and the SEIAA, Maharashtra is neither requiring demolition nor payment of assessed compensation to comply with the rule of law and protection of environment, it will be appropriate to require the SEIAA, Maharashtra to review its working in the light of the judgments of the Hon’ble Supreme Court and violations frequently being alleged, including the present case. A proper SOP be laid down for grant of EC in such cases so as to address the gaps in binding law and practice being currently followed. The MoEF may also consider circulating such SOP to all SEIAAs in the country. In this regard, we may refer to the directions in the earlier order of this Tribunal dated 1.2.2021 in OA 837/2018, Sandeep Mittal vs. MoEF, wherein it was inter-alia, directed:
“MoEF&CC may give due attention for proper constitution of SEIAAs in the States to ensure the projects of category ‘B’ and ‘B-1’ are properly scrutinized.”
The MoEF&CC may file its action taken report in the matter before the next date.
We also constitute a joint Committee of MoEF&CC, CPCB, and Maharashtra State PCB to look into the present matter and suggest a remedial action plan for the present case, including the quantum of compensation to be recovered, as far as possible within three months. The CPCB and State PCB will be nodal agency for coordination and compliance. Another connected matter between same parties for a different project being Appeal No. 32/2020(WZ) is also being dealt with by a separate order today and this direction will also apply to the said case. Infact, to avoid duplication if the SEIAA, Maharashtra itself reviews all such cases, to avoid unnecessary and repeated litigation. The Committee may conduct proceedings online but if possible, visit the site. The Committee may also interact with the concerned parties. The report of the joint Committee may be filed by e-mail at [email protected] preferably in the form of searchable PDF/ OCR Support PDF and not in the form of Image PDF before the next date. While submitting the report to this Tribunal, a copy of the report thereof be also forwarded to the PP and the applicant who may file their comments, if any, before the next date by e-mail.”
Since the allegations of this nature are frequently being made before this Tribunal and prima facie there appears to be fundamental flaw in working of the SEIAA in question, resulting in defeating the statutory mandate of prior EC and directions of the Hon’ble Supreme Court, we direct constitution of a two-member Committee comprising Additional Secretary, Ministry of Environment, Forest and Climate Change (MoEF&CC), nominated by the Secretary MoEF&CC and the Chairman, Central Pollution Control Board (CPCB) to conduct functional audit of SEIAA, Maharashtra to find out how such frequent blatant violations are taking place and how the situation can be remedied. The Committee will be free to take assistance from any other expert/institution and interact with the stake-holders. This is necessary for protection of environment. If mechanically ex post facto ECs are granted by SEIAA, the purpose of requiring prior EC will be defeated. The ‘Precautionary’ and ‘Sustainable Development’ principles considered in the above judgments of the Hon’ble Supreme Court will be rendered nugatory. Precautions during the course of construction and compliance of conditions after constructions will be rendered difficult. EC is not a mechanical exercise. It may be after application of any mind and granted only after evaluation of impact and efficacy of mitigation measures proposed. Conditions imposed must be faithfully observed and monitored. If there is any violation, steps must be taken for restoration of damage at the cost of the project proponent. The persons manning SEIAA who have acted illegally need to be made accountable in civil and criminal law. It is further surprising in the present case that inspite of order of State PCB to disconnect water and electricity, it is not clear how the project is functioning. Present status of compliance of environment norms in the project and remedial action against non-compliances also needs to be ascertained.
Accordingly, apart from a Committee for the conduct of functional audit of functioning of SEIAA in the matter of grant of ECs, there is need to conduct audit of compliance of environmental requirements in the project in question by an independent Expert Committee. For this purpose, we constitute a four-member Expert Committee comprising nominees of MoEF&CC, CPCB, IIT Bombay and Member Secretary, State PCB. The Committee will be at liberty to take assistance from any other expert/institution. The CPCB and State PCB will be nodal agency for coordination and compliance. The Committee may visit the site and conduct the proceedings online, wherever necessary and also interact with the stakeholders. The functional audit report as well as the Expert Committee report about status of compliance in the project may be furnished within three months by e-mail at [email protected] preferably in the form of searchable PDF/ OCR Support PDF and not in the form of Image PDF before the next date with an advance copy to the PP for its response, if any, before the next date. Copy of second report about status of compliance of the project may be furnished to the PP in advance for its comments, if any, before the next date. Copy of the first report about functional audit may be furnished to the MoEF&CC also for its response in terms of action taken before the next date.
The first Committee may also consider the orders of this Tribunal dated 24.05.2021 in Appeal No. 32/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors. and Appeal No. 34/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors. inter alia requiring SEIAA, Maharashtra to review its working in the light of Supreme Court judgements and frequent violations alleged in the grant of EC and also in the gaps in compliance of EC conditions. The second Committee may also coordinate and work in tandem with the joint Committee constituted in Appeal No. 32/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors. and Appeal No. 34/2020(WZ), Tanaji B. Gambhire v. Chief Secretary Government of Maharashtra & Ors.”
We are of the view that on the pattern of above orders passed by this Tribunal in Appeal No. 34/2020(WZ) and OA No. 13/2021 (WZ), apart from considering the remedial action against violations, two-member Committee comprising Additional Secretary, MoEF&CC, to be nominated by the Secretary MoEF&CC and the Chairman, CPCB need to conduct functional audit of SEIAA, UP to find out how frequent blatant violations are taking place and how the situation can be remedied. The Committee will be free to take assistance from any other expert/institution and interact with the stake-holders. SEIAA, UP has to review its working in the light of judgments of the Hon’ble Supreme Court and in the light of frequent and rampant violations. Considering the report, an appropriate SOP may to be laid down by the MoEF&CC to deal with such ECs which may be circulated to all SEIAAs.
Apart from above, remedial action appears to be necessary under Section 15 of the NGT Act after verification of factual position. Accordingly, we also constitute a joint Committee comprising of MoEF&CC, CPCB, SEIAA, UP, State PCB and District Magistrate, Ghaziabad. CPCB and SEIAA, UP will jointly be the nodal agency for coordination and compliance. Joint Committee may give its report covering issues mentioned in para 2 above and availability of basic infrastructure facilities like sewerage and solid waste management. Meeting of the joint Committee may be held within 15 days from today to take stock of the situation. The joint Committee may visit the site and interact with the stakeholders including the PP to verify the status of compliance. Based on the facts found, the statutory authorities may take remedial action including stopping creation of third party rights and further construction activities, if the same are found to be in violation of law. Needless to say that if adverse action becomes necessary, the same may be taken by following prescribed procedure. The report of the joint Committee report may be furnished to this Tribunal within three months by e-mail at [email protected] preferably in the form of searchable PDF/ OCR Support PDF and not in the form of Image PDF, and if the report is adverse to the PP, a copy thereof may be furnished to PP for its response, if any, before the next date.”
Report of the Committee dated 27.1.2022 finding violations and Order of the Tribunal dated 4.2.2022 on consideration thereof
The matter was last considered on 04.02.2022 in the light of report of the joint Committee dated 27.01.2022, after undertaking visit to the site confirming the violations. The Tribunal noted that consents under the Water (Prevention and Control of Pollution) Act, 1974, the Air (Prevention and Control of Pollution) Act, 1981 were granted before grant of EC and EC for expansion was granted overlooking the expansion work already executed and in violation of conditions of original EC. The Tribunal observed that as per applicable procedure, violation cases were required to be appraised by MoEF&CC and not by SEIAA. The compensation suggested did not cover the pre-expansion period.
Thus, it was found that the recommendations of the joint Committee were required to be re-visited after ascertaining the consents with regard to disposal of waste, operation of DG sets, functioning of RWH systems and greenery. Operative part of the order is reproduced below:-
“
The report confirms violations of the environmental norms and shows that regulatory authorities have not monitored the project activities. The PP has disregarded environmental laws. However, the Committee has also not mentioned about the existence of sewer line in the area and the mode of disposal of sewage, quantity of solid waste generated and disposed.
It is thus prima facie clear that the State PCB has issued consents under the Air (Prevention and Control of Pollution) Act, 1981 and the Water (Prevention and Control of Pollution) Act, 1974 even before grant of EC. EC for expansion has been granted on 04.03.2021 overlooking the violations which are already undertaken, including expansion work. In such cases, as per the procedure laid down, violation case is required to be appraised by the MoEF&CC. The violations do not end with the procedural aspects. There violations of environmental norms have also been found. The Committee has not responded to all the violations alleged by the applicant noted in the earlier order. Recommendations for the compensation ignore the period of violations and only relate to the period post inspection. In respect of violation of ground water extraction, the violations have been taken only on the date of application to the CGWA. The joint Committee may need to revisit its recommendation accordingly. The Committee may also ascertain the mode of disposal of sewage and solid waste and compliance in operation of DG sets, functioning of RWH systems and maintenance of greenery. The environment compensation should be the liability of the PP and not the flat owners. PP is given opportunity to respond to these observations before this Tribunal as well as before the Committee within one month.
In view of prima facie violations of serious nature, mentioned herein above, we restrain the PP from creating any third-party rights till the next hearing.”
The Tribunal also noted that the report about functional review of SEIAA, U.P has not been furnished which was required to be furnished.
Consideration of the matter today - Further Report of the Committee on factual aspects of violations dated 29.04.2022 and the report of the Committee about functional audit of SEIAA UP dated 02.05.2022
In pursuance of above, the joint Committee has filed its revised report dated 29.04.2022. MoEF&CC has filed its report on 02.05.2022 with regard to functional audit of SEIAA U.P. SEIAA, U.P has filed its reply on 20.04.2022. The Project Proponent (PP) has filed I.A No. 104/2022 for re-call of order dated 04.02.2022 and reply to the joint Committee report dated 27.01.2022. We will refer to the same at appropriate place in the order.
We have heard learned counsel for the parties and considered the material on record.
First question to be considered is the issue of violation of the environmental norms by the PP and remedial action required. Further question is also about the failure of the SEIAA, U.P to function as per the mandate as found in the report in respect of functional audit.
Consideration of issue of violations by the PP and the remedial action
With regard to the first question, we take up for consideration the joint inspection report dated 29.04.2022. The joint Committee comprised of the MoEF&CC, CPCB, State PCB, SEIAA, U.P and District Magistrate. There is no question raised about credibility of the Committee nor about contents of the report. The Committee has undertaken visit to the site after due notice to the PP as well as the applicant. It has also considered the documents furnished by the PP and the applicants. The status of EC violations has been given in a tabular form. The violations include expansion of project without prior EC, violation of EC conditions such as inadequacy of the plantations, absence of safeguards in construction of basement, failure to utilize solar energy, absence of requisite parking, absence of safe disposal of STP sludge, non-functioning of STP, not providing the requisite funds in terms of the EC conditions for out of CSR, illegal extraction of ground water. The Committee recommended levying of environmental compensation for the violations including expanding the project without prior EC, apart from suggested compensation of Rs. 12.80 Crores approx. for violation of maintaining STP and Rs. 7.43 Crore approx. for illegal extraction of ground water. Relevant extracts from the report are:-
“3. Observations
On the basis of inspection of project “Saviour Park” conducted by Joint Committee on 23/09/2021 and going through the submissions made by the applicant and project proponent following observations are made:
a.. M/s Savfab Buildtech Pvt. Ltd has set-up. Saviour Park” at Plot No. 108, Katori Mill, Loni Road, Mohan Nagar, Ghaziabad, UP.
b. As per the submitted documents by PPs, it has been reflected that PPs have obtained the CTE from UPPCB vide letter no. F08023/C-1/NOC/G-752/2012/6 dated 26.07.2012, before obtaining the Environmental Clearance dated 04.03.2013.
c. PPs have obtained the CTO from UPPCB for previous EC and existing CTO is valid till 31.07.2025. CTE for expansion project is rejected by UP PCB.
d. The documents submitted by the applicant indicate that, PP got the approval for the site plan from Ghaziabad Development Authority on 21.06.2011, followed by Prior Environmental Clearance from SEIAA, UP on 04.03.2013 and Environmental Clearance for expansion from SEIAA, UP on 04.03.2021.
e. The total project cost of project is 251 Crores after expansion as per EC dated 04.02.2021.
f. PP has informed that approximately 3044.5 Kg of solid waste would be generated per day.
g.. Approx 800 flats are occupied and 800 families are currently residing in project. Approximately.
h. Assuming four person in one family.
Current Sewage generation and Solid Waste generation are estimated as follows:
A. Assuming Consumption of 135 LPCD
Approx. sewage generation is 135*0.8*4*800 = 345.6 KLD
B.Approx Solid Waste Generation is 800*4*0.5 = 1600 kg
i. Sewage is being discharged into municipal drain.
j. Project Proponent is supplying water to township through bore wells but has not obtained any approval from CGWA.
k. Rain Water Harvesting pits were found clogged and filled with mud and stagnant water.
Results of sample analysis obtained from pit of RWH is tabulated below:
pH
COD
BOD
TSS
NH3 - N
PO43- - P
TC
FC
8.0
155
17
72
09
0.54
16 X 107
35 X 106
l. The 400 KLD STP operated by M/s Savfab Buildtech Pvt. Ltd in apartment is not functioning properly
a. Media was not visible in aeration tank.
b. Filter press was found not in use.
c. The sample obtained from STP outlet is not complying the prescribed standards:
pH
COD
BOD
TSS
NH3 - N
PO43- - P
TC
FC
Inlet
7.5
325
114
208
11
1.24
17 X 1011
11 X 1011
Outlet
7.3
251
49
73
23
0.87
17 X 106
17 X 106
Standards
-
250
30
100
-
-
-
-
m. During the site visit, entire basement area of the project was found affected with seepage and large number of cracks was visible in many pillars upon which structural stability of all the towers resides.
n. Violation of Environment Clearance Conditions: As per the available office record, the project was inspected by MoEF&CC, IRO, Lucknow on 30.05.2019 to review the status of stipulated EC conditions granted by SEIAA, U.P. on 04.03.2013. Subsequently, a letter of non-compliances was sent to PPs vide letter no. VII/Env/SCL-UP/510/2019/422 dated 13.08.2019. The certified compliance report indicating various non-complainces with detailed monitoring report was also sent to PPs with a copy to SEIAA, UP vide letter no. VII/Env/SCL-UP/510/2019/423 dated 13.08.2019. However, no response has been received to IRO, Lucknow against the above mentioned letter. Additionally, PPs have obtained the Expansion EC from SEIAA, U.P. vide letter no. 788/Parya/SEAC/6057-5683/2019 dated 04.03.2021. Further, PAs are irregular in submitting the compliance report to MoEF&CC, IRO, Lucknow since 2019 onwards.
The detailed status of EC conditions violations, which was alleged by the applicant are given below as:
S.
No.
Environmental Clearance Conditions of previous EC
Observations of the Joint Committee
Part A – General Condition:
1
It shall be ensured that all standards related to ambient environmental quality and the emission/effluent standards as prescribed by the MoEF are strictly complied with.
Six monthly Compliance report not submitted by Project Proponent since 2019. STP outlet water is not complying the prescribed standards. Hazardous waste authorization was not obtained by Project Proponent
4
The proposed land use shall be in accordance to the prescribed land use. A land use certificate issued by the competent Authority shall be obtained in this regards.
Submitted by PP.
7
Surface hydrology and water regime of the project area within 10 km should be provided.
Project proponent has not been submitted surface hydrology report and water regime of project but informed that it is submitted before SEAC.
11
Obtain necessary clearance from the competent authority on the abstraction and use of ground water during the construction and operations phases.
Project Proponent has not provided copy of NOC from CGWA. There are approx. 03-04 no s. bore well inside premises .CGWA permissio n has not been obtained by project proponent.
12
Hazardous/inflammable/explosive materials likely to be stored during the construction and operations phases shall be as per standard procedure as prescribed under law, necessary clearances in this regards shall be obtained.
PAs has not obtained the authorization for Hazardous waste disposal from UPPCB.
15
The emissions and effluents etc. from machines, instruments and transport during construction and operations phases should be according to the prescribed standards. Necessary plans in this regard shall be submitted.
DG set installed with acoustic enclosure. Additional DG set found installed without adequate stack height. PP should obtain CTO for all DG set installed in premises.
16
Water sprinklers and other dust control measures should be undertaken to take care of dust generated during the construction and operation phases. Necessary plans in this regard shall be submitted.
Partially complied during visi
17
Suitable noise abatement measures shall be adopted during the construction and operation phases in order to ensure that the noise emissions do not violate the prescribed ambient noise standards. Necessary plans in this regard shall be submitted.
No details provided by Project Proponent.
20
Hazardous/solid wastes generated during the construction and operations phases should be disposed off as prescribed under law. Necessary clearances in this regards shall be obtained.
Hazardous waste authorization was not obtained. Details not provided regarding disposal of STP sludge
23
Pavements shall be so constructed as to allow infiltration of surface run-off of rain water. Fully impermeable pavements shall not be constructed. Construction of pavements around trees shall be as per scientifically accepted principles in order to provide suitable watering, aeration and nutrition to the tree.
Not complied
24
The green building concept suggested by Indian Green Building Council, which is a part of CII- Godrej GBC, shall be studied and followed as far as possible
No details provided
29
Make suitable provision for using solar energy as alternative source of energy, solar energy application should be incorporated for illumination of common areas, lighting for gardens and street lighting in addition to provision for solar water heating. Present a detailed report showing how much percentage of backup power for institution can be provided through solar energy so that use and polluting effects of DG sets can be minimized.
During inspection, Joint Committee not found solar energy utilization.
31
Educate citizens and other stakeholders by putting up hoarding at different places to create environmental awareness.
Details not provided. Sufficient hoarding not visible during visit.
32
Traffic congestion near the entry and exit points from the roads adjoining the proposed project site must be avoided. Parking should be fully internalized and no public space should be utilized.
No arrangement made for internal visitor parking causing traffic congestion near entry and exit point.
35
A report on the energy conservation measures confirming to energy conservation norms finalize by Bureau of Energy Efficiency should be prepared incorporating details about building materials and technology, R and U factors, etc.
Details not provided.
37
The DG sets to be used during construction phase should use low sulphur diesel type and should confirm to Environmental Protection Rules prescribed for air and noise emission standards.
DG Set with acoustic enclosure found. No information available w.r.t use of low Sulphur diesel.
38
Alternate technologies to chlorination (for disinfection of waste water) including methods like Ultraviolet radiation, Ozonation, etc. shall be examined and a report submitted with justification for selected technology.
PP has not submitted the STP adequacy report till date
39
The green belt design along the periphery of the plot shall achieve attenuation factor confirming to the day and night noise standards prescribed for residential land use. The open spaces inside the plot should be suitably landscaped and covered with vegetation of indigenous variety.
PP has submitted that about 419 nos. of plant species are planted within the premises. However, the plantation found during the site visit was inadequate around the project premises. PP is required to submit the details of the area covered for plantation and should also planted the plant species of thick canopy with long lives.
41
The building should be designed so as to take sufficient safeguards regarding seismic zone sensitivity
Seepage observed in basement during Joint committee inspection. An independent structure audit to be carried out by PP.
46
It shall be insured that all street and parks lighting is solar powered. 50% of the same may be provided with dual (solar/electrical) alternatives
No utilization of solar energy was found during joint committee inspection
47
Solar water heater shall be installed to the maximum possible capacity. Plans may be drawn up accordingly and submitted with justification
Arrangement/infrastructure for utilization of solar energy not found during joint committee inspection.
52
Parking areas should be in accordance with the norms of MoEF, Government of India. Plans may be drawn up accordingly and submitted.
Residents informed that visitor parking is not provided leading to traffic congestion at entry and exit point.
54
The environment management plan should also include the breakup costs on various activities and the management issues also so that the residents also participate in the implementation of the environment management plan.
Project Proponent has submitted following information :
“ Environmental management plan has been drawn up and is being implemented with a capital cost of 159.0 lakhs and a recurring cost
of Rs. 23.0 Lakhs in the following components.
• Solid waste management. Capital Cost
10.0 Lakhs. Recurring cost 2.0 Lakhs/year.
• Environmental monitoring. Capital cost
4.0 lakhs. Recurring cost 2.0 lakhs/year.
• Horticulture/green area. Capital cost
15.0 Lakhs. Recurring 3.0 lakhs/year.
• Fire fighting.Capital cost 20.0 lakhs.Recurring cost Rs. 4.0 Lakhs/year.
• Health safety and Energy. Capital cost15.0 Lakhs. Recurring cost 2.0 lakhs/year.
• Sewage Treatment plant.Capital cost95.0 lakhs. Recuring cost 10.0 lakhs/year.”
55
Detailed plans for safe disposal of STP sludge shall be provided along with ultimate disposal location, quantitative estimates and measures proposed.
No details provided by PP. Filter press found in unused condition
58
The DG sets shall be so installed so as to conform to prescribed stack heights and regulations and also to the noise standards as prescribed. Details should be submitted.
Additional DG set found installed without adequate stack height. PP should obtain CTO for all DG sets installed in premises.
61
The use of suitably processed plastic waste in the construction of roads should be considered.
Not complied.
63
Dispensary for first aid shall be provided.
No details provided by Project Proponent.
66
Ground water downstream of rain water harvesting pit nearest to STP should be monitored for bacterial contamination. Necessary hand pumps should be provided for sampling. The monitoring is to be done both in pre and post monsoon season
No information provided. Contamination found in sample obtained from RWH pit.
72
Project proponent shall endeavor to obtain ISO: 14001 certification. All general and specific conditions mentioned under this environmental clearance should be included in the environmental manual to be prepared for the certification purposes and compliance.
Not complied.
73
2% of total project cost should be reserved to create a corpus of funds for implementing plan under social corporate and environmental responsibility and proposals submitted within a month of issuance of environmental clearance. Failing which the environmental clearance deemed to be cancelled.
Not complied. No documentary evidence submitted for compliance of condition. PP has only informed that they have reserved funds .
Specific Conditions
Observation of Joint Committee
1
The project proponent shall be responsible for
management/disposal of sewage/sewage sludge till necessary arrangements are provided by the Ghaziabad Development Authority. Necessary plan in this regards may be submitted within a month.
Sewage Treatment Plant is not functioning properly and is not treating and reusing grey water as per EC conditions. No information provided related to Sludge disposal and filter press was found in unused condition
Assessment of environment compensation for the damage to the environment
In compliance to the directions of Hon’ble NGT, Joint committee has carried out assessment to calculate lump sum Environmental Compensation as per approved formula. Details of Environment compensation imposed are given below:
4.1 Environmental Compensation for Non complying STPs.
v Name of Unit: M/s SAVFAB Buildtech Pvt. Ltd.
Violation is assumed from Date of Partial Completion certificate, as STP is not complying the prescribed standards and unused filter press indicate violation from long duration.
PP has obtained first Partial Completion certificate on 04/07/2015 and STP was found non complying during visit on 23/09/2021. So Lump Sum Environmental Compensation is calculated for 2274 days’ violation .
Ø The Environment Compensation is calculated based on the following formula
Ø Environmental Compensation = P.I x N x R x S x LF
Ø Where, EC = Environmental Compensation
Ø P. I = Pollution Index of Industrial sector = 100 for Red Category
Ø N = No of days of Violation = 2274 days approximate (Period from 04/07/2015 to 23/09/2021)
Ø R = Factor in rupees = 250, Category of the Unit: RED
Ø S = Factor for scale of operation = Scale of the Unit: Large, 1.5 for Large
Ø L.F = location Factor = 1.5 for Ghaziabad and nearby area,
Ø
v Environmental Compensation = 100x 2274 x 250 x 1.5 x 1.5 = 12,79,12,500 Rupees. On the basis of above calculations Environmental Compensation of Rupees 12,79,12,500 /-Tweleve Crore Seventy Nine Lakh, Twelve thousand, Five hundred only.) is to be levied on M/s SAVFAB Buildtech Pvt. Ltd.
4.2 Environmental Compensation for illegal extraction of ground water
Assuming violation from date of application in 2010 to CGWA to date of inspection 23.09.2021 for 03 nos. of bore wells), as no other details are available. EC may be increased, till PP obtain approval for bore wells and if additional bore wells found by CGWA/Local authority.
ECGW = Water Consumption per Day x No. of Days x Environmental Compensation Rate for illegal extraction of ground water (ECRGW)
Pump Yield = 18 m3/hr . (From CGWA application)
Daily Consumption = 18 x 7 = 126 m3 (From CGWA application) ECRGW = 45 Rs./m3 (Ghaziabad in over exploitation region) EC to be levied = 45 x 126 = 5670 Rs./day
Total time period = 4368 days Then, ECGW = 5670 x 4368 = 24,766,560
Calculated ECGW = 24,766,560 Rs. For one bore well. Total EC for three bore well = 24,766,560 * 3 =7,42,99,680
= Rs Seven Crore, Fourty Two Lakhs Ninty Nine thousand, Six hundred Eighty Only.
Conclusion
Applicant claimed, that expansion was initiated before obtaining the Environmental Clearance for expansion from SEIAA, UP on 04.03.2021 on the basis of copy of Progress report submitted by the builder to RERA available on portal of UP RERA. CPCB vide letter dated 08/11/2021 has sought details of progress report submitted by Project proponent from UP RERA to verify the allegations and data is received from UP RERA. Based on data received from UP RERA and Project Proponent it is observed that PP has Prima Facie started constructed for expansion project before obtaining EC.
Project proponent is extracting Ground Water without permission
Project Proponent has not obtained Hazardous waste authorization
Project proponent is not operating STP as per consent conditions.
Project Proponent is not managing solid waste as per EC conditions.
Seepage was observed in basement, which may have affected structural stability of the project. An expert should be engage by Project Proponent to assess structural safety.
Parking facility for visitors not allocated and it causes traffic congestions at outside of society.
6.0 Joint Committee’s Recommendations
Following recommendations have been made by the Joint Committee Members:
i. Project Proponent has prima facie violated Environmental Clearance conditions and has started constructed for expansion project before obtaining EC. Hon’ble NGT may include UP RERA in Joint Committee for further investigation. Hon’ble NGT may impose additional Environmental Compensation as per direction of Hon’ble NGT in 661/2018, 764/2018 and Goel Ganga Developers Vs UOI).
ii. With regard to violation of STP functioning, M/s Savfab Buildtech Pvt. Ltd. shall deposit compensation of Rs 12,79,12,500 (Twelve Crore Seventy Nine Lakh, Twelve thousand Five hundred only.(If assuming violation from date of first Partial Completion certificate date 04/07/2015 to date of inspection on 23/09/2021. Environmental Compensation is calculated for 2274 days’ violation).
iii. With regard to withdrawal of ground water, M/s Savfab Buildtech Pvt. Ltd. shall deposit compensation amount of R s. Seven Crore Fourty Two Lakh Ninty Nine Thousand Six Hundred Eighty Only (7,42,99,680) only (Assuming violation from date of application in 2010 to CGWA to date of inspection 23.09.2021 for 03 nos. of bore wells), as no other details are available.EC may be increased if additional borewell found by CGWA/Local authority.
iv. M/s Savfab Buildtech Pvt. Ltd shall engage third party expert for determining structural stability and taking corrective actions.
v. Project Proponent to comply with all EC conditions and seek approval from CGWA for use of bore well.
vi. Project Proponent to comply with provision of Solid Waste Management Rules, 2016 and EC conditions for Solid Waste Management and to ensure proper collection, segregation, and treatment of biodegradable waste in compost as per EC conditions.
vii. Project Proponent to allot parking for visitors as per norms of MoEF&CC to avoid traffic congestion outside society.
viii. Project Proponent to obtain authorization for Hazardous waste and remove additional gensets (not included in consent and installed in society without adequate stack height).
ix. The grey water should be treated- up to tertiary level in decentralized STP and treated water should be reused as per Environment Clearance conditions.
x. PPs should comply and submitted the compliance status report to MoEF&CC IRO, Lucknow for the stipulated conditions of EC granted by SEIAA, UP for Saviour Park on 04.03.2013 and its expansion project on 04.03.2021 on regular basis.
The Hon’ble Tribunal may issue appropriate directions as it deems fit, which the Committee is bound to comply with.”
The stand of the PP does not dispute that there are violations as found. However, PP has stated that it has taken certain steps in the matter as follows:-
“
(i) Non Submission of Surface Hydrology Report and Water Regime:
In terms of the EC, the Project Proponent, vide letter, dated 27.07.2019 submitted the land use certificate, surface hydrology report and water regime report with Dr. Susheel Kumar, Ministry of Environment, Forest and Climate Change. This letter has been duly acknowledged and stamped by the Ministry. Therefore, there is no violation with respect to submission of the above mentioned Reports.
True Copy of letter dated 27.07.2019 is marked and annexed as ANNEXURE R-2.
(ii) Non use of alternate technology for disposal of solid waste:
The Project Proponent has been using two methods for disposal of solid waste-
(a) Solid waste disposed of through STP; &
(b) Solid waste being disposed of through an Organic Waste Convertor (OWC). The Project Proponent has been using the present Organic Waste Convertor since December 2021.
Apart from the above mentioned technologies used, the Project Proponent has also executed Work Order, dated 14.12.2021, wherein the Project Proponent has engaged a vendor for single point collection, secondary segregation and disposal of all solid wastes generated including installing, operating and maintaining Organic Waste Composting Machine for the project. Hence, the answering Respondent is using alternate technology for disposal of solid waste. Photograph of the Organic Waste Convertor is marked and annexed hereto as ANNEXURE R-3.
True Copy of the Work Order, dated 14.12.2021 is marked and annexed hereto as ANNEXURE R-4.
(iii) Non use of recycled water and water from local municipal authority and exploiting groundwater for construction and operational purpose:
Firstly, the Project Proponent since November 2015 till February 2018 have been using treated water from STP for construction purpose. Thereafter, the answering Respondent installed a STP at the Project premises. It is submitted that the Project Proponent uses the treated water from STP in its premise for construction activities. True Copy of the invoices for STP water utilized by Respondent No.10 from November 2015 to February 2018 is marked and annexed as ANNEXURE R-5 (Colly).
Secondly, insofar as the groundwater is concerned, it is extracted from borewells. It is pertinent to point out here that the only requirement under the EC for extraction and use of ground water was that the answering Respondent had to obtain clearance from the competent Authority.
On 04.08.2018, the answering Respondent had applied for NOCs to extract water from bore wells with the CGWA. However, the same was rejected on 16.12.2020 by the CGWA on the ground that Uttar Pradesh Government has its own regulations for groundwater and directed the answering Respondent to apply for NOCs from the Ground Water Department, Government of Uttar Pradesh. Thereafter, on 03.09.2021, the answering Respondent submitted applications with the Ground Water Department, Government Of U.P. for permission to extract water from 3 borewells. On 05.01.2022, NOC was issued by the Ground Water Department for 2 borewells. The answering Respondent expects that the NOC for the remaining borewell will be issued shortly. In this manner, the answering Respondent has adhered to the terms of the EC. Furthermore, the groundwater is not used for construction purpose and only for domestic use by the residents of the Project.
(iv) The Sewage Treatment Plant is not functioning properly and is not treating and reusing grey water. Analytical Results of water samples collected from STP and RWH pit indicate that most of the parameters are exceeding the limit. Mixing of sewage effluent into the storm water drain cannot be ruled out:
As on date, the Sewage Treatment Plant is fully functional. It is submitted that the Project Proponent recycles and uses water from the STP for horticulture and construction activities. Further, the answering Respondent is ready if the samples are collected from STP and RWH pit and tested.
(v) No information provided for sludge disposal and filter press was found in unused condition:
On 13.08.2019, the Ministry of Environment, Forest and Climate Change, Regional Office (Central Region) (“MOEFC”) sent a Compliance Report to Member Secretary, SEAC, Directorate of Environment for the project developed by answering Respondent. Perusal of Serial No.55 of the Compliance Report makes it evident that the detailed plans for the disposal of STP sludge have been complied with. The tertiary level treated domestic waste-water by STP is used for flushing, gardening and water sprinkling and compost used as manure for horticulture at site.
True Copy of the Compliance Report of the Ministry of Environment, Forest and Climate Change, Regional Office (Central Region) are marked and annexed hereto as ANNEXURE R-6.
(vi) Maintenance of 3 RWH structures were in poor condition. All RWHs were choked and analytical results of water samples collected from RWH pit indicate presence of sewage in RWH pit:
It is submitted that there are 6 Rainwater Harvesting systems in the project. The Rain Water Harvesting systems are in compliance with the designs as provided by the Groundwater Department. The Compliance Report of MOEFC (marked Annexure R-6) at Serial 14 states that the answering Respondent has complied with the design.
Further, it is submitted that the Project Proponent regularly monitors the conditions of the Rain Water Harvesting pit. The Rainwater Harvesting Pit is cleaned in the pre monsoon period and after every rain and storm. The answering Respondent is ready for inspection of the RWH pit. However, it is pertinent to point out that a storm line drain which connects to the RWH is there in every balcony. The balconies are not meant to be used for washing clothes or to discharge domestic waste. However, the residents of the Project have connected their washing machines to the balcony and the discharge from the washing machine and other domestic discharges are released into the storm line drain. This may lead to mixing of rain water with domestic effluents. While the Project Proponent regularly and repeatedly advices the residents against such practices, it may be noted that these are manifestations of existing behavioral patterns of society. Any change in such patterns requires regular counseling and time for change. While the Project Proponent continues to work with the residents, it expects that over time these changes will happen.
(vii) Project Proponent has failed to construct roads in project area with the use of suitably processed processed plastic waste:
It is submitted that while one of the terms of the EC is that suitably processed plastic waste in the construction of roads should be considered. However, the internal roads have been constructed as per the Fire Departments norms, taking into account the movement of fire tenders and the requirement of R.C.C. roads designed for a particular pressure (usually, in excess of 60 tonnes per square meter). It is submitted the Project Proponent would have violated norms of Fire Safety had it constructed roads with use of suitably processed plastic waste. Further, the language of the term is directory and not mandatory.
(viii) Spent / Used oil from DG set is the hazardous material generated at the site. Project Proponent has not obtained hazardous waste disposal authorization:
The Project Proponent is a member of Sheetla Waste Management Project (hereinafter referred as “SWMP”), which is an organization the answering Respondent has engaged for the disposal of hazardous and biomedical waste. By virtue of the membership to SWMP, the Project Management has a tie up, dated 18.11.2021 with the SWMP for safe disposal of hazardous and bio medical waste. True Copy of the duly signed form, dated 18.11.2021 for engagement of Sheetla Waste Management Project for disposal of hazardous waste is marked and annexed as ANNEXURE R-7.
(ix) Project Proponent has not provided designated visitors parking and instead is allowing visitors parking on common road which is generating traffic congestion near entry and exit point:
It is submitted that parking areas have been provided in the project in terms of the EC. The Compliance Report of MOEFC (Annexure R-6) records compliance of the same in Serial 32 and
It is respectfully submitted that the parking facility has been provided as per the sanction lay out plan in accordance with the norms of MOEF.
(x) Project Proponent is not utilizing solar energy for street and park lighting. No source of renewable energy has been observed at project site:
On 17.01.2022, the Project Proponent has installed solar panels generating 40 KW of solar power. The solar power generated from the panels is supplied to the main electricity grid connection of the project. It is submitted that the street and park lighting requires around 25KW of power. The Project Proponent also uses CFL based lighting in the common areas in order to reduce the consumption of power by 20%.
True Copy of the work completion and handing over certificate, dated 17.01.2022 is marked and annexed as ANNEXURE R-8.
(xi) Project Proponent has not submitted report on the energy conservation:
It is submitted that the Project Proponent, as recorded in Serial
35 of the Compliance Report of MOEFC (Annexure R-6), has undertaken to provide the report on energy conservation after the completion of the project. It is submitted that the energy conservation report can only be accurate once the said Project is completely constructed. The answering Respondent undertakes to submit the Report on completion of the project.
(xii) Project Proponent has installed additional Gensets, which are not of adequate stack height:
On the date of the inspection the said Gensets were only being tested and were not fully operational. The Gen sets installed at present are fixed at an adequate height.
Photographs of the gen set are marked and annexed hereto as ANNEXURE R-9.
(xiii) Project Proponent has not provided details regarding Environment Management plan and Cost of environmental activities:
The Project Proponent in its Environmental Impact Assessment Report that was submitted to the SEAC, has provided for certain CSR activities from page 202 onwards of the document. The Project Proponent undertook to provide creche facilities for the construction workers and also undertook to facilitate Corporate Environment Responsibility. The Project Proponent further undertook to plant trees along the main road and median. The Project Proponent has undertaken to spend Rs.213 Lakh till the completion of the project in CSR and CER activities. The answering Respondent undertakes to provide Environment Management Plan and Cost of Environmental Activities as per the directions of this Hon’ble Tribunal.
(xiv) Project Proponent has not provided details / copy of agreement with recycler to handle / dispose hazardous waste (waste oil from DG sets) and STP sludge, plastic waste, e-waste and biomedical waste etc., generated at project site:
The alleged violation observed in this Para has been dealt with by the answering Respondent in the previous Paras. The contents of Para 7 (v) and 7 (viii) above may be read as part and parcel of the present para as the same is not being repeated herein for the sake of brevity.
(xv) Project Proponent has not provided copy of NOC from CGWA:
(xvi) On 04.08.2018, the answering Respondent had applied for NOCs to extract water from bore wells with the CGWA. However, the same was rejected by the CGWA on the ground that Uttar Pradesh Government has its own regulations for groundwater. Accordingly, the Project Proponent was directed to apply for NOCs from the Ground Water Department, Government of Uttar Pradesh. Thereafter, on 03.09.2021, the answering Respondent, in terms of the EC, submitted applications with the Ground Water Department, Government Of U.P. for permission to extract water from 3 borewells. On 05.01.2022, NOC bearing No. REG013555 and REG048660 were issued by the Ground Water Department for 2 borewells. The answering Respondent expects that the NOC for the remaining borewell will be issued shortly. In this manner, the answering Respondent has adhered to the terms of the EC. Furthermore, the groundwater is not used for construction purposes and only for domestic use by the residents of the Project.
(xvii) True Copy of NOCs bearing No. REG013555 and REG048660 issued by the Ministry of Ground Water, Government of Uttar Pradesh are marked and annexed as ANNEXURE R-10 (Colly.).
(xviii) 9. Apart from the above, the answering Respondent has obtained Structural Stability Certificate, dated 05.02.2012, issued by Prof V.K. Gupta from IIT Roorkee. It is submitted that the Project Proponent could not have got the Completion Certificate without the structural stability certificate.”
From the above, it is seen that there is no dispute about violations of prior EC which is mandatory. Also, there is no dispute regarding malfunctioning of the STP earlier. Though, about the ground water issue, it is claimed that permission has been granted for extraction on 05.01.2022, the past violations remain undisputed. The permission granted is for two bore-wells while three have been functioning. Moreover, bore-wells are allowed only for drinking purposes and not for commercial/construction purposes. The PP has also filed I.A No. 102/2022 for re-call of order dated 04.02.2022 restraining it from creating third party rights.
Finding and Directions
In view of violations of serious nature found by the joint Committee noted above and only stand of PP being subsequent partial compliance which is yet to be verified by the statutory regulators, the PP is held to have violated the requirement of prior EC as well as conditions of EC. The report of the joint Committee is accepted. Compensation assessed for violating STP norms and illegal ground water extraction is approved. Recommedations for further remedial action be carried by the PP and overseen by the statutory regulators as per law. Apart from liability for being prosecuted as per the provisions of the EP Act, 1986 and to pay compensation determined by the Committee which we have approved, the PP is held liable to pay further compensation for violating requirement of prior EC and CTE on the principles laid down inter-alia in MC Mehta, (1987) 1 SCC 395, Sterlite (2013) 4 SCC 575 and Goel Ganga (2018) 18 SCC 257. Having regard to the nature and extent of violations and project cost, the compensation is determined at Rs. 40 Crores, taking the project cost at Rs.800 crore. The precise cost of the project is not on record but cost of expansion is mentioned in EC to be Rs. 250 crore. We take the total cost at Rs.800 having regard to the size of the total project (850 flats already constructed) as shown by the report of the MoEF&CC filed on 02.05.2022, as follows:
“1. Unit has obtained CTE for existing project (Total Built up area 1,55,000 sqm) vide letter dated 26/07/2012.
RO, Ghaziabad, UPPCB reported that unit has obtained CTO for existing project (Total 850 flats against 980 flats, built up area 1,55,000sam) vide letter dated 17/09/2020. During inspection for CTOon 26/07/2020, a total of 850 flats were observed as constructed, which is less than as permitted in CTE. No violation was noticed during inspection.”
The entire amount of compensation be deposited with the State PCB within two months. In case, deposit is not made, it will be open to the statutory authorities to take coercive measures including, black listing of the PP, attaching and selling its property in accordance with law. The PP will not be allowed to create any further third party right till compliance of all the recommendations, verified by authorities and till payment of compensation, which burden will not be passed on those who have already purchased the flats assuming the project to be compliant. We further notice that the built up area of the project is 1550000 sq.m i.e. more than 1,50,000 sq.m, requiring the project to be appraised as category ‘B1’ project in terms of Entry 8(b) of the EIA Notification dated 14.09.2006. If the project has been appraised only as ‘B’ project, the same is violation of norms and atleast ex post facto appraisal may be made taking the project as BI, if not already done on that basis. The PP may ensure compliance with all the deficiencies found in the report within three months failing which, the statutory regulators will be at liberty to levy further compensation and take further coercive measures.
It is seen from the analysis reports of samples collected from RWH and STP that there are high FCs in breach of laid down parameters. Further, sewage is entering into drain and there is no sewerage system. It is possible that such conditions exist in other residential and commercial complexes also. Thus, SPCBs need to carefully grant CTE and CTO, laying down the mode of disposal in the light of draft notification of MoEF&CC dated 25.2.2022.
Report about functional audit
We now consider the report of the Committee on functional audit of SEIAA, U.P reproduced as under:-
“Chapter 7
Functional Audit of SEIAA, Uttar Pradesh
Data and Information were received from SEIAA, Uttar Pradesh in parts vide E-mails as follows:
· Email dated 08.12.2021 (Annexure-7)
· E-mail dated 24.01.2022 (Annexure-10) and in continuation
· further vide dated 03.02.2022
· E-mail dated 11.03.2022 (Annexure-26)
The information and data have been analysed and the details and observations are as follows:
7.1 Existing Mechanism for grant of EC within SEIAA, Uttar Pradesh
7.1.1 Application format
It is submitted by SEIAA, UP that the Application Format is the same as prescribed in EIA Notification dated 14/09/2006 (as amended thereof).
7.1.2 Type of Format for Consolidated Statement
It is submitted by SEIAA, UP that the Application Formats are as per the categories prescribed in EIA Notification, 14/09/2006 (as amended thereof).
7.1.3 Procedure of processing of application
It is submitted by SEIAA, UP that procedure as prescribed in EIA Notification, 14/09/2006 (as amended thereof) is followed for processing of application.
7.1.4 Involvement of SPCB, Local Bodies, Town and Country Planning Department
It is submitted by SEIAA, UP that interaction with other enforcement agencies including SPCB, Local Bodies, Town & Country Planning Dept takes place during the appraisal of project. Many a times, it becomes necessary to coordinate with concerned department to verify the factual status of the project. Also, in many cases, litigation against the project is filed in the Hon’ble Court(s) by the social community or by the project proponent itself making the concerned departments as the pro-forma party or may be impleaded as the case may be. Ground status of the project in question is required to be answered in compliance of the Hon’ble Court(s) orders. Hence, other enforcement agencies are coordinated including SPCB, Local Bodies, Town & Country Planning Dept. etc.
7.1.5 Stepwise flowchart and time-lines for issue of Environment Clearance by SEIAA and institutional mechanism for coordination with SPCB, Municipal Bodies, Town Planning and other designated bodies involved in sanctioning building construction projects at local level.
It is stated by SEIAA that the process adopted is as per EIA Notification, 2006 (as amended thereof).
The Committee is not satisfied with the reply of SEIAA.
7.1.6 Procedure of sanction of plan by Town and Country Planning. Does the approval process for Building Construction by the Town Planning Department / Municipal Bodies also includes examining whether EC has been granted? Whether there is any requirement of CTE / CTO before sanctioning or issuing of Occupancy certificate by concerned Agencies/ Authorities?
It is stated by SEIAA that the matter is related to Housing and Urban Planning Department UP.
The Committee is not satisfied with the reply of SEIAA.
7.1.7 Necessary Clearances/ NOCs/ Licences etc. required for processing application SEIAA, UP submitted that, Clearances/ NOCs/ Licences etc. are required as prescribed in EIA Notification, 14/09/2006 (as amended thereof).
The Committee is not satisfied with the reply of SEIAA.
7.1.8 Coordination /Information Exchange between SEIAA and Local Authorities – Sharing of Environment Clearance Document issued by SEIAA or CTE/CTO issued by SPCB with the Town Planning/ Municipal Bodies or any other designated body responsible for approving the building plan
It is stated by SEIAA that EC letter issued to the concerned project proponent for the very project. The copy of the same with enclosure for Information and necessary action are issued to:
· Advisor, IA Division, Ministry of Environment, Forests & Climate Change, Govt. of India, Indira Paryavaran Bhawan, JorBagh Road, Aliganj, New Delhi.
· Additional Director, Regional Office, Ministry of Environment & Forests, (Central Region), Kendriya Bhawan, 5th Floor, Sector-H, Aliganj, Lucknow.
· District Magistrate (Concerned District).
· The Member Secretary, U.P. Pollution Control Board, TC-12V, Paryavaran Bhawan, VibhutiKhand, Gomti Nagar,Lucknow.
7.1.9 Prescribed timelines - Max and Min.for issuing of Environmental Clearance
Timeline is as prescribed in EIA Notification, 14/09/2006 (as amended thereof)
The Committee felt that the SEIAA has not been able to provide the complete information as desired.
7.1.10 Specific Methodology for Building Projects SEIAA, UP submitted that, Methodology for Building Projects is as prescribed in EIA Notification, 14/09/2006 (as amended thereof)
The Committee is not satisfied with the reply of SEIAA.
7.1.11 Mechanism for Compliance Monitoring
It is submitted by SEIAA that the mechanism for compliance monitoring has been well defined in the office order issued vide file no. J-11013/10/2009-IA.I dated 30/09/2009 wherein it has been mentioned that:
“The Monitoring Cell in IA Division is the nodal point for monitoring and compliance of the stipulated conditions imposed on the industrial units/infrastructural projects including CRZ, while granting Environmental Clearance (EC). A copy of the EC is endorsed to the concerned Regional Office of the MoEF&CC for monitoring the compliance of the stipulated conditions, besides to the concerned State Pollution Control Board (SPCB) and Central Pollution Control Board (CPCB).”
For the aforesaid purpose, after the grant of EC, letter is issued to the concerned project proponent for the very project and the copy of the same together with enclosure are endorsed to the following for information and necessary action:
· Advisor, IA Division, Ministry of Environment, Forests& Climate Change, Govt. of India, Indira Paryavaran Bhawan, Jor Bagh Road, Aliganj, New Delhi
· Additional Director, Regional Office, Ministry of Environment& Forests, (Central Region), Kendriya Bhawan, 5th Floor, Sector-H, Aliganj, Lucknow
· District Magistrate, (Concerned District)
· The Member Secretary, U.P. Pollution Control Board, TC-12V, Paryavaran Bhawan, VibhutiKhand, Gomti Nagar, Lucknow.
And more specifically, SEIAA/SEAC, appraises the violation category cases as per the EIA Notification dated14/09/2006 (as amended thereof) read along with notification dated 14/03/2017 and 08/03/2018. The SEIAA/SEAC, stipulates the implementation of Environmental Management Plan, comprising remediation plan and naturaland community resource augmentation plan corresponding to the ecological damage assessed and economic benefit derived due to violation as a condition of environmental clearance. The conditions stipulates that:
The project proponent is asked to submit bank guarantee of Rs. (The sum levied) equivalent to the amount of remediation plan and natural and community resource augmentation plan within 15 days to the SPCB.
The Committee felt that SEIAA needs to expedite the action in this regard.
7.1.12 Imposition of Environmental Compensation
It is stated by SEIAA that, as per CPCB guidelines, compensation is imposed by State Pollution Control Board.
The Committee is not satisfied with the reply of SEIAA.
7.1.13 What is the Checklist? Standardized TOR? Is it same for all types of projects or project-wise varies?
It is submitted by SEIAA that, for different categories, Standard ToRs have been prescribed by MoEF&CC. SEAC/SEIAA follows the same. However, in some cases wherein, additional environmental information regarding the project is required which are not covered in the standard ToR’s in that case additional ToR is suggested to be carried out during the study for EIA of the project
7.2(i) Why are construction projects of the State not following provisions of EIA Notification, 2006?
It is stated by SEIAA, UP that, every project has to follow EIA Notification, 2006.
The Committee is not satisfied with the reply of SEIAA.
(ii) Do other Enforcement agencies take cognizance of requirement of prior EC or EC conditions?
It is informed that, the concerned Regional Office of the Ministry/SPCB takes cognizance of requirement of prior EC or EC conditions.
The Committee is not satisfied with the reply of SEIAA.
(iii) Why are such frequent blatant violations taking place and how can the situation be remedied?
SEIAA, UP has expressed disagreement with the above statement. They have submitted that, SEIAA/SEAC processes more than 700 cases/year and violation have been observed only in 2-3 cases/year which cannot be considered as frequent blatant violations.IT has also been stated that SEIAA is facing shortage of manpower. The situation can be improved only by providing adequate resources to SEIAA. SEIAA/SEAC are the bodies constituted by Govt. of India therefore Govt. of India should take responsibility of providing sufficient resources to discharge their responsibilities in a more efficient and transparent manner which is an incorrect statement considering that the expenses of SEIAA is to be borne by the State government / State Pollution Control Board which has sufficient resources for providing adequate manpower.
7.3 Analysis of Violation Cases received by SEIAA during Window Period
Some information has been received from SEIAA, UP in different phases (Annexure 26A, 26B& 26C). Same have been analyzed as follows:
Table 7.3.1 (a): List of Cases received during window Period i.e. from 14.03.2017 to 13.09.2017 and from 14.03.2018 to 13.04.2018.
S.
N.
Project
Title
Sector
Date
of Applicatio n for EC
Committe
e Meeting Date
Committee
Decision
Reply
Received against query raised by SEAC
Authority
Meeting Date
Authority
Decision
Reply
Received against query raised
Categor
y of
Violatio n
Whethe r Expansi on
/New
Final
status/Dat e of Grant
of EC
1
2
3
4
5
6
4
8
9
10
14
1.
Construction of Proposed Group Housing and
Staff Quarters at U
PSRTC Campus, Vikas Nagar, Kanpur, U.P.
8(a)
Building Constructi on
22/03/201
8
2/5/2018
21/08/201
8
Information asked from PP
Recommende d for EC
30/07/201
8
16/05/20
8
31/08/20
18
Agreed with SEAC
Grant
…
New
EC Issued on 14/09/208
2.
Proposed Group Ho
using Project "KW
Srishti" at Khasra
8(b)
Building Constructi on
15/01
/2019
19/02
/2019
Recommende d for EC
……………
.
03/07/20
19
Grant
……..
Expansi on
EC Issued on 08/04/201
9
No.- 1125/1, 1125/2
&1125/3,Village- Noor Nagar, Pargana- Loni, Raj
Nagar Extension,District-
Ghaziabad,U.P.,M/s Dingle Buildcons
Pvt. Ltd.
3.
Proposed
Group Housing Project at Plot No.- 139, Block- H,
Scheme- 1, Fazalganj, Kanpur,
U.P.,M/s Tapasya Projects Ltd.
Building Constructi on
EC (T
OR)
Application
Received dated 12/04/201
8
……..
……..
……..
……..
……..
……..
New
ToR's
Granted vide letter dated 09/03/201
9 but EC Application Not Received
4.
Residential Complex "Gulmohar Residency" at Khasra No.-527/1,
519, Village- Kanawani, District- Ghaziabad, U.P.,M/s SVP Builders (I) Ltd.
Building Constructi on
21/06/201
9
……..
……..
……..
……..
……..
……..
New
Delisted due to non
-
submission of reply
by PP/Absent
5.
Proposed Group Ho
using Project "Platinum Premier" at
Khasra No.- 304,294, 295& 296
of Village- Pehladgarhi&Khasra No.-194 of Village- Makanpur Sector- 9, Vaishali Ext., District-
Ghaziabad, U.P.
Building Constructi on
EC (TOR)
Application
Received dated 13/04/201
8
……..
……..
……..
……..
……..
……..
New
Delisted due to non- submission of reply
6.
Affordable Housing Project located at Plot No.-GH-05,
Sector -10, Greater Noida,District GautamBudhaNagar U.P.,M/s Greater Noida Industrial
Development Authority
8(a)
Building Constructi on
28/11/201
9
19/12/201
9
Defer in view of order passed by Hon'ble
NGT in OA
No. 1038/2018
Recommende d for EC
01/06/202
0
1/2/2020
26/02/202
0
01/07/202
0
21/09/202
0
Agreed with SEAC Grant
Discussed the P.P. letter dated 16/06/2020
and directed that the matter
shall be referred to MoEF&CC
Directed to take further
Action as per decision taken in SEIAA
New
EC Issued on 25/11/202
0
meeting dated 26/02/2020
7.
Affordable Housing Project located at Village-
GohodiBacheda,
Sector Mu II, Greater Noida, District-
Gautam Budha Nagar, U.P.,M/s Greater Noida Industrial
Development Authority
8(b)
Building Constructi on
27/11/201
9
19/12/201
9
16/01/202
0
Defer in view of order passed by Hon'ble
NGT in OA
No. 1038/2018
Recommende d for EC
01/06/202
0
1/2/2020
26/02/202
0
20/08/202
0
15/10/202
0
Agreed with SEAC
Information from PP
Information not satisfactory
Grant
13/07/202
0
30/09/202
0
New
EC Issued on 15/12/202
0
8.
Affordable Housing Project located at Plot No.-GH-03A,
Omicron, Greater Noida, Di
strict- Gautam BudhaNagar,U.P.,M/ s Greater Noida Industrial Development Authority
8(a)
Building Constructi on
29/11/201
9
19/12/201
9
16/01/202
0
Defer in view
of order passed by Hon'ble
NGT in OA No. 1038/20
18Recommen d for EC
01/06/202
0
1/2/2020
26/02/202
0
01/07/202
0
21/09/202
0
Agreed with SEAC Grant Discussed the
P.P. letter dated 16/06/2020
and directed that the matter
shall be referred to MoEF&CC Directed to take further action
New
EC Issued on 25/11/202
0
as per
decision taken in SEIAA
meeting dated 26/02/2020
9.
Affordable Housing Project
located at Plot No.
-GH-02,Omicron 1A, Greater Noida, District-
GautamBudhaNagar
,U.P.,M/s Greater Noida Industrial
Development Authority
8(a)
Building Constructi on
28/11/201
9
19/12/201
9
16/01/202
0
Defer in view
of order passed by Hon'ble
NGT in OA No. 108/20 18
Recommende d for EC
01/06/202
0
1/2/2020
26/02/202
0
01/07/202
0
21/09/202
0
Agreed with SEAC
Grant Discussed the
P.P. letter dated 16/06/2020
and directed that the matter
shall be referred to MoEF&CC
Directed to take further action
as per decision taken in SEIAA
meeting dated 26/02/2020
New
EC Iss ued o n 25/ 11/20
20
10
Affordable Housing Project located at
8(a)
27/11/201
9
19/12/201
9
Defer in view
01/06/202
0
1/2/2020
26/02/202
0
Agreed with SEAC Grant
New
EC Issued on
Plot No.-L & M, Sector- 12
, Greater Noida, Di
strict- Gautam BudhaNagar, U.P., M/s Greater Noida Industrial
Development Authority
Building Constructi on
16/01/202
0
of order passed by Hon'ble
NGT in OA
No. 1038/2018
Recommende d for EC
01/07/202
0
24/09/202
0
Discussed the
P.P. letter dated 16/06/2020
and directed that the matter shall be referred to MoEF&CC
Directed to take further action as per
decision taken in
SEIAA meeting dated 26/02/2020
25/11/202
0
111.
Environmental Clearance for the Ansal Town Project located at Village - Jatoli, Meerut Bypass, Roorkee Road,
Meerut,U.P. - 201308 (Under Violation Notification da
ted 14th March, 2017) byM/s Ansal Housing
Building Constructi on
EC (T OR)
Application
Received dated 13/09/201
7
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply by PP/
Abse nt
& Construction Ltd.
12
Proposed Affordable Housing at Sector- 22 D,Village- Ballukhera
, YEIDA,Yamuna Expressway
Industrial Development Authority, District- Gautam Budh Nagar
, U.P.
Building Constructi on
EC (T OR)
Application
Received dated 28/07/201
7
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply by PP/
Absent
13
Expansion of Logistic Park (Warehouse) Project at Gata No.-18
8 and 198, located at Village Sikandrabad Dehat, District- Bulandshahar, U.P.,(
Under Violation Notification dated 1
4 March2017) by M/s VRY Industrial Park LLP
8(a)
Building Constructi on
25/06/201
9
24/07/201
9
11/10/201
9
PP Absent
Recommende d for EC
29/08/201
9
16/08/201
9
20/11/201
9
01/01/202
0
Agreed with SEAC Defer
in view of order passed by Hon'ble
NGT in OA No.1038/
2018 Grant
New
EC Issued on 24/02/202
0
14
Proposed
Group Housing Project "VinayakApartment" at
Sector- 7B, MajholaYojna- 4, Part-II,Delhi Road, District- Moradabad, U.P., M/s Maya Nagar
SahkariAwas Samiti Ltd,
8(a)
Building Constructi on
25/06/201
9
24/07/201
9
11/10/201
9
PP Absent
Recommende d for EC
29/08/201
9
16/08/201
9
20/11/201
9
01/01/202
0
Agreed with
SEAC Defer in view of order passed by Hon'ble
NGT in OA No.1038/2018
Grant
New
EC Issued on 24/02/202
0
15
Combined Residential and Non- Residential Campus for 32 Battalion PAC, at Kanp ur Road,District-
Lucknow,U.P., M/s
Provincial Armed Constabulary
Building Constructi on
EC (T OR)
Application
Received dated 19/08/201
7
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of Reply by PP/Absent
16
Proposed
Group Housing Project "Chimera" located at Khasra No.- 1134, N
Building Constructi on
EC (T OR)
Application
Received dated
……..
……..
……..
……..
……..
……..
New
ToR's
Granted vide letter dated 08/08/201
8 but EC
H-58, Village- Noo
r Nagar Raj Nagar
Extension, District- Ghaziabad, U.P.
,(Under Violation Notification dated 14 March2017) by
M/sShouryaShubha m Infrastructure Pvt. Ltd.
28/03/201
7
Application Not Received
117
Proposed
Expansion of Group Housing Project
Situated at Khasra No.- 527/4, 528,
549-554,556-559
Village- Ka]nawani,
Indirapuram, District- Ghazaibad,
U.P. prom
ted by M/s Niho Construction Ltd
Building Constructi on
04/05/202
1
……..
……..
……..
……..
……..
……..
Expansi on
Delisted due to non submission of reply
by PP/Absent
18
Proposed
Group Housing Project "Assotech Winder Court" at GH-04/A, Sector- 78,Noida, Di
strict-GautamBudh Nagar,U.P., dev
eloped by M/s Assotech Ltd.
Building Constructi on
EC (T OR)
Application
Received dated 13-
09-2017
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply
by PP/Absent
19
Revised Group Ho
using Project located at Khasra No.-
322 & 324, Village
-Noor Nagar, District- Ghaziabad, U.P., by M/sDiya Ang els Realtors Pvt. Ltd.
8(a)
Building Constructi on
01/09/201
9
19/02/201
9
Recommende d for E
C
7/3/2019
07/05/201
9
Information asked by PP Grant
04/08/20
19
New
EC Issued on 10/09/201
9
20
Commercial Complex "Galaxy Diamond Plaza"at Plot N
8(a)
Building Constructi on
EC (TOR)
Application
Received dated
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply
o.- C-1 A Sector-
04, Greater Noida,
District- GautamBudh Nagar,
U.P. AS
PER "SO804(E)"
dated 14.03.2017 by M/sAsteroid
SheltersHomes Pvt. Ltd.
10/09/201
7
by PP/ Absent
221
Environment Clearance for
Group Housing Project "Vrinda City located at
Plot No.GH- 2 Sevtor- PHI-4 Greater Noida,
Uttar Pradesh by
M/s Central and State Employees SahakariAwasSamiti
Limited under the
8(a)
Building Constructi on
21/03/202
0
04/06/202
0
19/08/202
0
Recommende d for EC
Recommende d
18/06/202
0
15/09/202
0
28/12/202
0
Refer
back to SEAC
Information asked by PP Grant
28/09/20
20
New
EC Issued on 15/01/202
1
provisionof Central Government,Gazette Notification
dated 14,March 2017-Violation case.
22
Environmental Clearance for (for Violation) Group Housing Project "Orchid Heights" apartments at Village Uttardhauna
District and Tehsil Lucknow,
Uttar
Building Constructi on
EC (TOR)
Application
Received dated 13/09/201
7
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply
by PP/ Absent
23
Environmental Clearance for (for Violation) Goel Heights Apartments,
Gro
up Housing under pahadi Sahkari A was Samiti Ltd. At Khasra no.- 761,762,763 (b)
Village- Anaura,
Building Constructi on
EC (TOR)
Application
Received dated 1
3/09/2017
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply
by PP/ Absent
Chinhat Faizabad Road,District- Lucknow, Uttar
Pradesh.
24
Environmental Clearance for (for Viola
tion) Group Housing Project "Green
Park" apartments
at VillageUttardhauna District and Tehsil Lucknow, Uttar Pradesh.
Building Constructi on
EC (TOR)
Application
Received dated 13/09/2017
……..
……..
……..
……..
……..
……..
New
Delisted due to non submission of reply
by PP/ Absent
25
Environmental Clearance for Expansi
on of "Swami VivekanandSubharti University"Project at
Khasra No.- Vill- Ghatt 941,947, 94950/1/2/3,951,9
52, 953/1/2, 954-
959,963, 964,
974/2,
Building Constructi on
EC (T OR)
Application
Received dated 13/09/201
7
……..
……..
……..
……..
……..
……..
Expan sion
Delisted due to non submission of reply
by PP/ Absent
977, 978, 980, 98
1, 982,984, 985,
960, 961, Vill-
Mallyana-
1625,1628, 1629,
1630-1633, 1635,
163
6, 1637,1638, 1650,
1651, 1653, 1654,
165
5/2, 1656,
1657, 1606, 1634,
1652, 1653 Vill
Panchali-522, 531
-537, 540, 545, 5
48, 549,550located at village-Ghatt, MaliyanaPanchali, Meerut Bypass Road, Meerut, Uttar Pr adesh (under violation Notificationdated 14
March 2017) by M/s Subharti K.K.B charitable Trust.
26
Proposed Group Ho
using Project "San
char Arcade SahkariAwasSamiti Ltd."at Khasra No.- 236& 237, Village-
Mo
rta, District- Ghazaibad, U.P
., M/s Sanchar Arcade SahkariAwasSamiti Ltd.,
8(a)
Building Constructi on
10/09/201
8
12/12/201
8
Recommende d for EC
28/12/201
8
Grant
New
EC Issued on 23/01/201
9
27
Proposed Residential Colony "AnsalBa
sera City" at Village- Buda,District-
Kanpur By Pass Road, District- Jhansi, U.P.
8(a)
Building Constructi on
13/07/201
9
08/08/201
9
Recommende d for EC
18/09/201
9
Grant
New
EC Issued on 16/07/202
0
28
Proposed
"Cement Grinding
Unit" Project at Village- Dhauhan, Pargana- Saktesgarh,
3(b)
Industry
21/09
/2019
26/09
/2021
Recommende d for E
C
8/11/2019
03/01/202
0
Information asked by PPGrant
19/11/20
19
EC Issued on 24/02/202
0
Tehsil- Chunar, District- Mirzapur, U
.P. M/s Uddyam Cement Pvt. Ltd.
29
Proposed
Project "Gomti River Front Channelization Project from Harding to Gomti Weir, District- Lucknow, U.P.
8(b)
Building Constructi on
26/11
/2018
20/12/201
8
11/07/201
9
20/11/201
9
28/02/202
0
Recommende d for EC
Information asked by PP
Information asked by PP Recommende d for EC
04/09/201
9
27/01/202
0
8/1/2019
09/03/201
9
01/07/201
9
01/08/201
9
20/12/201
9
09/05/202
0
Information asked by PP Information asked by PP Refer back to
SEAC Agreed with SEAC Agreed with SEAC Grant
24/0/201
9
04/0/201
9
-
EC issued on 21/08/202
0
30
Proposed Group
Housing "Grand Forte Apartments" at Plot NO.- 76, Sigma- IV, Greater Noida, District- Gautam Buddha Nagar
, U.P.,M/s
SatililaSahkari Awas Samti
8(a)
Building Constructi on
13/06/202
1
17/08/202
1
21/12/202
1
Information asked by PP Recommende d for EC
29/10/202
1
5/10/2021
31/12/202
1
Agreed with
SEAC Defer in view of SOP OM Stay byMadras HighCourt
New
Under Process
Table 7.3.1(b): Summary of Cases received during Window Period [from 14.03.2017 to 13.09.2017 and from 14.03.2018 to 13.04.2018]
SSector
Total
Applications received
EC
Granted
EC
Pending
BBuilding
Construction
29
14
15
IIndustry
01
01
00
TTotal
30
15
15
Observations:
It is submitted by SEIAA, UP that, during violation period total 30 no. of application were received. But, from the Annexure 26A and Table 7.3.1(a), it is noted that, for most of the projects dates of application for EC are beyond the window period. However, out of them 15 were granted EC and 15 no. were not granted EC. Out of 30 projects there are 29 construction projects and 01 is industry project. Details status of the projects follows:
Table 7.3.2 (a): Detailed status of the Projects under violation Category w.e.f. 01.04.2017 to 31.07.2021 for which EC has been granted (In context to Applications received during Window Period)
S. No.
Project Title
Sector
Date of
Applicatio n forEC
Category
of Violatio n whether
Expansi on/New
Action of Violation
Final
status/Dat e
of Grant of EC
Total no
of Days taken for
granting of EC
BG
released
(YEs/ No)
Current
status of the
project
Under
Section1 5 of EP),
Act
Bank
Guarante Imposed
Reme
diatio n Plan
Construction of Proposed Group Housing and Staff Quarters at UPSRTC Campus, Vikas Nagar, Kanpur, U.P.
8(a)
Building
Constructio n
22/03/201
8
New
Action under section 15 of E(
P) Act initiated vide
letter dated
02/07/
2018
1,25,00,0
00/-
Copy of bank guarantee submitted by PP
to SEIAA o n 26/07/2 018
Submitte d
EC Issued
on 14/09/208
176
N/A
Under constructio n
Proposed Group Housing Project "KW Srishti" at Khasra No.- 1125/1, 1125/2
&1125/3,Village- Noor Nagar, Pargana- Loni, Raj NagarExtension, District Ghaziabad, U.P.,M/s Dingle Buildcons Pvt. Ltd.
8(b)
Building
Constructio n
15/01/2019
Expansio n
Action under section 15 of E( P)
Act initiated vide
letter dated
5,02,000/
-
Copy of bank guarantee submitted by PP
to SEIAA on 05/03/2019
10,00,000
/-(additional Information; as provided by SPCB)
Submitte d
EC
Issued on 08/04/201
9
932
No
Completed
28/03/20
19
Affordable Housing Project
located at Plot No.-GH- 05, Sector - 10, Greater Noida, District GautamBudhaNagar,U.P.
,M/s Greater Noida Industrial Development
Authority
8(a)
Building
Constructio n
28/11/2019
New
Action under section 15 of E( P)
Act initiated vide
letter dated
09/11/20
20
90,00,000
/- PP vide letter dated
16/06/20
20 have re
quested for the exemption of bank Guarantee Letter sent to MoEF&CC
on 07/07/2020
for clarification regarding exemption of
bank guarantee
Copy of bank guarantee submitted by
PPto SEIAA
Submitte d
EC
Issued on 5/11/2020
363
No
Under constructio n
on 16/09/2020
Affordable Housing Project
located at Village-
GohodiB
acheda, Sector Mu II, Greater Noida, District- GautamBudhaNagar,U.P.
,M/s Greater Noida Industrial Development Authority
8(b)
Building
Constructio n
27/11/2019
New
Action
Under section 15 of E( P)Act initiated vide letter dated
09/11/20
20
1,10,48,0
00/-
Copy of bank guarantee submitted by PP
to SEIAA o n 19/10/2
020
Submitte d
EC
Issued on 15/12/202
0
384
No
Under constructio n
Affordable Housing Project
located at Plot No.-GH- 03A
, Omicron, Greater Noida,
District- GautamBudhaNagar,U.P.
,M/s Greater Noida
8(a)
Building
Constructio n
29/11/2019
New
Action
Under section
15 of E(P)
Act initiated vide letter dated
09/11/20
20
1,10,00,0
00/-
PP vide letter dated
16/06/20
20 have re
quested for the exemption of bank Guarantee
Submitte d
EC
Issued on 15/11/202
0
362
No
Under constructio n
Letter sent to MoEF&CC
on 07/07/2020
for clarification regarding exemption of
bank guarantee
Copy of bank guarantee submitted by PP to SEIAA
on 16/09/2020
Affordable Housing Project
located at Plot No.-GH- 02,
Omicron 1A, Greater Noida
, District GautamBudhaNagar,U.P. s Greater Noida Industrial Development
Authority
8(a)
Building
Constructio n
28/11/2019
New
Action
Under section
15 of E(P)
Act initiated vide letter dated
09/11/20
20
1,10,00,000
/-
vide letter dated
16/06/20
20 have re
quested for the exemption of bank Guarantee
Submitte d
EC
Issued on 25/11/202
0
363
No
Under constructio n
Letter sent to MoEF&CC
on 07/07/2020
for clarification regarding exemption of
bank guarantee Copy of bank guarantee submitted by PP
to SEIAA on 09/09/2020
1,03,20,0
00/(addition al Information; as provided by SPCB)
Affordable Housing Project
located at Plot No.-L &M, Sector- 12, Greater Noida,
8(a)
Building
Constructio n
27/11/2019
New
Action
Under section
15 of E(P)
Act initiated
50,00,000/-
vide letter dated
16/06/20
20 have re
Submitte d
EC
Issued on 05/11/202
0
364
No
Under constructio n
District- GautamBudhaNagar,U.P.
,M/s Greater Noida Industrial Development Authority
vide letter dated
09/11/20
20
quested for the exemption of bank Guarantee
Letter sent to MoEF&CC
on 07/07/2020
for clarification regarding exemption of
bank guarantee
Copy of bank guarantee submitted by PP to SEIAA
on 16/09/2020
Expansion of Logistic Park
(Warehouse) Project at Ga
ta No.-188 and 198, locate
8(a)
Building
Constructio n
26/09/2018
Expansio n
Action
Under section
15 of E(P)
Act initiated
22,50,000/-
Copy of bank guarantee submitted by PP to SEIAA
o
Submitte d
EC
Issued on 06/06/201
9
253
Yes
completed
d at Village- SikandrabadDehat, District- Bulandshahar, U.P.,(Under Violation Notification dated 14 March
2017) by M/s VRY Industrial Park LLP
vide letter dated
07/05/20
19
n 25/03/2019
5,00,000/
- (additional Information; as provided by SPCB)
Proposed Group Housing Project "VinayakApartment"
at Sector- 7 B, MajholaYojna- 4, Part-II, Delhi Road,
District- Moradabad, U.P.,
M/s Maya Nagar SahkariA
wasSamiti Ltd,
8(a)
Building
Constructio n
25/06/2019
New
Action
Under section
15 of E(P)
Act initiated vide letter dated 11/02/20
19
33,00,000/-
Copy of bank guarantee submitted by PP
to SEIAA on 05/02/2020
150000
(additional Information; as provided by SPCB)
Submitte d
EC
Issued on 04/02/202
0
244
No
Constructio n stopped
Revised Group Housing Project located at Khasra No.- 322 & 324, Village- Noor
Nagar, District- Ghaziabad
8(a)
Building
Constructio n
01/09/2019
New
Action
Under section
15 of E(P)
Act initiated
3,35,000/-
Copy of bank guarantee submitted by
PP to SEIAA
Submitted
EC
Issued on 01/09/201
9
241
No
Completed
, U.P., by M/s Diya Angels
Realtors Pvt. Ltd.
vide letter dated 08/07/20
19
on 08/07/2019
Environment Clearance for
Group Housing Project "Vrinda City located at Plot No GH- 2 Sevtor-
PHI-4 Gre
ater Noida, Uttar Pradeshby M/s Central and State Employees SahakariAwasSamiti Limited under the pro
vision of Central Government, Gazette Notification dated 14, March 2017-Violation case.
8(a)
Building
Constructio n
21/03/2020
New
Action
Under section
15 of E(P)
Act initiated vide letter dated 15/10/20
21
20,05,000/-
Copy of bank guarantee submitted by PP to SEIAA
on 18/06/2 020
Submitte d
EC
Issued on 15/01/202
1
300
No
Completed
Proposed Group Housing Project "Sanchar Arcade SahkariAwasSamiti Ltd." at Khasra No.- 236 & 237, Village- Morta, District- Ghazaibad, U.P., M/s Sanchar Arcade SahkariAwasSamiti Ltd.,
8(a)
Building
Constructio n
10/09/2018
New
Action
Under section
15 of E(P)
Act initiated vide letter
dated
24,44,000/-
Copy of bank guarantee submitted by PP to SEIAA
on 28/12/2018
Submitte d
EC
Issued on 23/01/201
9
135
21/09/20
19
Proposed Residential Colo
ny "AnsalBasera City" at V
illage- Buda, District-
Kan
pur By Pass Road, District-
Jhansi, U.P.
8(a)
Building
Constructio n
13/07/2019
New
Action
Under section
15 of E(P)
Act initiated vide letter dated 09/07/20
20
5,00,000/-
Copy of bank guarantee submitted by PP
to SEIAA o n 03/07/2 020
Submitte d
EC
Issued on 06/07/202
0
369
Proposed "Cement Grinding Unit" Project at Village-
Dhauhan, Pargana- Saktesgarh, Tehsil- Chunar, District- Mirzapur, U.P. M/s Uddyam Cement Pvt. Ltd.
3(b)
Industry
21/09/2019
Action
Under section
15 of E(P)
Act initiated vide letter dated 12/02/20
20
4,86,000/-
Copy of bank guaran tee submitted by PP to SEIAA
on 07/11/2019
Submitte d
EC
Issued on 07/11/201
9
Proposed Project "Gomti River Front Channelization Project from Harding to Gomti Weir, District-Lucknow, U.P.
8(b)
Building
Constructio n
26/11/2018
-
Action
Under section
15 of E(P)
Act
Letter dated 07/08/
2020 sent to MoEF&
EC
Issued on 21/08/202
0
625
initiated vide letter dated 09/08/20
20
CC for exemption of
bank guarantee being a govt. project
Table 7.3.2(b): Summary of EC Granted under violation Category w.e.f. 01.04.2017 to 31.07.2021 (In context to Applications received during Window Period)
S.
No.
Table
7.3.2(b):
Summary of EC Granted under violation Category w.e.f. 01.04.201 7 to 31.07.202 1 (In context to Applicatio ns received during Window Period)
No.
of
Projects
Category
of
violatin
whether Expasion /New in Number
Action of Violation in Number
Time Taken to Grant E
C
( from date of Application for EC)
Construction status
Under
Section15 of E(P) Act
Damage
Assessment Quantified
Remedia
tion Plan
within
1 year
betwe
en 1to2 years
bet
ween 2 to 3 years
bet
ween 3 to 4 years
betwe
en 4 to 5 y ears
Completed
Under
construction
Work
Stopped
No
infomation
Yes
No
Yes
No
Yes
No
1.
Building Construction
14
Expansion: 0 2
02
-
02
-
02
-
01
-
01
-
-
02
-
-
-
Observation:
It is reported that, ECs have been issued to 15 projects and actions under Section 15 of the Environment (Protection) Act, 1986 have been taken against all these 15 projects. Most of these ECs have been issued within a period of 01 year from the date of application. Out of the 15 aforesaid cases; damage assessments have been made in respect of 14 cases . However, this exercise of damage assessment has not been undertaken for the remaining 1 project belonging to the government sector. Same observations have been made in context of preparation of Remediation Action Plan. In some cases, it has been found that, two types of Bank Guarantees have been imposed. In such cases, one information has been provided by SEIAA itself and another information has been provided by SPCB. Clarification in these regard has not been provided. Project completion status as provided by SEIAA in respect of these 15 projects are as follows:
Completed – 04 Projects
Under construction – 06 Projects
Work stopped - 01 Project
No information - 04 projects
Table 7.3.3(a): Ground status of Projects to Whom ECs were not granted (Under violation Category w.e.f. 01.04.2017 to 31.07.2021)
S.
N.
Project Title
Sector
Date of Application for EC
Category of Violation whether Expansion
/New
Action of Violation
Final status/Date of Grant
of EC
Total no of
days
BG
released
(Yes/No)
Current status of
the project
Under Section 15 of E(P), Act
Bank Guarantee Imposed
Remediati on
Plan
1.
Proposed Group Housing Project at Plot No.- 139, Block- H, Scheme- 1, Fazalganj, Kanpur, U.P.,M/s Tapasya
Projects Ltd.
Building Constructi on
EC (TOR)
Application Received dated 12/04/2018
New
--
--
--
ToR's Granted vide letter dated 09/03/2019 but EC Application Not Received
--
N/A
Completed
2.
Residential Complex "Gulmohar Residency" at Khasra No.-527/1, 519, Village- Kanawani, District- Ghaziabad, U.P.,M/s SVP
Builders (I) Ltd.
Building Constructi on
21-06-2019
New
--
5,20,000/
-
(additional Informatio n; as provided by SPCB)
--
Delisted due to non submission of reply by PP/Absent
--
No
Completed
3.
Proposed Group Housing Project "Platinum Premier" at Khasra No.- 304, 294, 295 & 296 of
Village- Pehladgarhi&Khasr a No.-194 of Village- Makanpur Sector- 9, Vaishali Ext., District- Ghaziabad, U.P.
Building Constructi on
EC (TOR)
Application Received dated 13/04/2018
New
---
--
--
Delisted due to submission f reply by Absent
--
N/A
Completed
4.
Environmental Clearance for the Ansal Town Project located at Village - Jatoli, Meerut Byepass, Roorkee Road, Meerut, U.P. - 201308 (Under Violation Notification dated 14th March, 2017) by M/s Ansal Housing & Construction Ltd.
Building Constructi on
EC (TOR)
Application Received dated 13/09/2017
New
--
500000/-
(additional Informatio n; as provided by SPCB)
---
Delisted due to non submission of reply by PP/Absent
--
No
Completed
5.
Proposed Affordable Housing at Sector- 22 D, Village- Ballukhera, YEIDA,Yamuna Expressway Industrial Development Authority, District- GautamBudh Nagar, U.P.
Building Constructi on
EC (TOR)
Application Received dated 28/07/2017
New
--
---
---
Delisted due to non submission of reply by PP/Absent
--
N/A
Under construction
6.
Combined Residential and Non- Residential Campus for 32 Battalion PAC, at Kanpur Road, District- Lucknow, U.P., M/s Provincial
Armed Constabulary
Building Constructi on
EC (TOR)
Application Received dated 19/08/2017
New
--
---
---
Delisted due to non submission of reply by PP/Absent
--
No
Completed
7.
Proposed Group Housing Project "Chimera" located at
Building Constructi on
EC (TOR)
Application Received
New
--
---
---
ToR's Granted vide letter dated 08/08/2018 but EC
--
No
Completed
Khasra No.- 1134, NH-58, Village- Noor Nagar Raj Nagar Extension, District- Ghaziabad, U.P. (Under Violation Notification dated 14 March 2017) by M/s Shourya Shubham Infra-structure Pvt.
dated 28/03/2017
Application Not Received
8.
Proposed Expansion of Group Housing Project situated at Khasra No.- 527/4, 528, 549-554,556-
559 Village- Kanawani, Indirapuram, District- Ghazaibad,
U.P. promoted by M/s Niho Construction Ltd.
Building Constructi on
04-05-2021
Expansion
--
---
---
Delisted due to non submission of reply by PP/Absent
--
N/A
Under construction
9.
Proposed Group Housing Project "Assotech Winder Court" at GH-04/A, Sector- 78, Noida, District- GautamBudh Nagar, U.P., developed by M/s Assotech Ltd
Building Constructi on
EC (TOR)
Application Received dated 13-09-
2017
New
--
10,00,000
/- (additional Informatio n; as provided by SPCB)
---
Delisted due to non submission of reply by PP/Absent
--
No
78%
Constructio n done. 28% Under construction Total Tower proposed- 05,
Constructio n done-4 tower (744 flats)
Under construction
-01 tower
(208 flats) At present 330 flats Occupied
10.
Commercial Complex "Galaxy Diamond Plaza" at Plot No.- C-1 A, Sector-04, Greater Noida, District- Gautam Budh Nagar, U.P. AS PER
"SO 804(E)" dated 14.03.2017 by M/s
Asteroid Shelters Homes Pvt. Ltd.
Building Constructi on
EC (TOR)
Application Received dated 10/09/2017
New
---
1000000/
-
(additional Informatio n; as provided by SPCB)
---
Delisted due to non submission of reply by PP/Absent
---
No
Under construction
11.
Environmental Clearance for (for Violation) Group Housing Project "Orchid Heights" apartments at Village Uttardhauna District and Tehsil Lucknow, Uttar Pradesh.
Building Constructi on
EC (TOR)
Application Received dated 13/09/2017
New
---
--
--
Delisted due to non- submission of reply by PP/Absent
--
NA
Completed
12.
Environmental Clearance for (for Violation) Goel Heights Apartments, Group Housing under pahadi Sahkari Awas Samiti Ltd. At Khasra no.-
761,762,763 (b)
Village- Anaura, Chinhat Faizabad Road, District- Lucknow, Uttar Pradesh.
Building Constructi on
EC (TOR)
Application Received dated 13/09/2017
New
---
3000000
(additional Informatio n; as provided by SPCB)
---
Delisted due to non submission of reply by PP/Absent
--
Yes
Completed
13.
Environmental Clearance for (for Violation) Group Housing Project "Green Park" apartments at Village Uttardhauna District and Tehsil Lucknow, Uttar Pradesh
Building Constructi on
EC (TOR)
Application Received dated 13/09/2017
New
---
1000000
(additional Informatio n; as provided by SPCB)
---
Delisted due to non submission of reply by PP/Absent
--
Yes
Completed
14.
Environmental Clearance for Expansion of "Swami Vivekanand Subharti University" Project at Khasra No.- Vill-Ghatt 941
,947, 949, 950/1/2/3,951,
952, 953/1/2, 954-
959, 963, 964,
974/2, 977, 978,
980, 981, 982, 984,
985, 960, 961, Vill-
Mallyana- 1625,
1628, 1629, 1630-
1633, 1635, 1636,
1637, 1638, 1650,
1651, 1653, 1654,
1655/2, 1656,
1657, 1606, 1634,
1652, 1653 Vill-
Panchali- 522, 531-
537, 540, 545, 548,
549, 550 located at village- Ghatt, Maliyana Panchali, Meerut Bypass Road, Meerut, Uttar Pradesh (under violation Notification dated 14 March
2017) by M/s Subharti K.K.B charitable Trust.
Building Constructi on
EC (TOR)
Application Received dated 13/09/2017
Expansion
---
---
---
Delisted due to non submission of reply by PP/Absent
--
No
Not started
15.
Proposed of Group Housing "Grand Forte Apartments" at Plot NO.- 76, Sigma- IV, Greater Noida, District- Gautam Buddha Nagar, U.P.,M/s Satilila Sahkari Awas Samti
8(a)
Building Constructi on
13-06-2021
New
---
4,86,000/
-
Copy of bank guarantee submitted by PP to SEIAA on 05/01/20
22
--
Under Process
---
Table 7.3.3(b): Summary of Projects to Whom EC has not been Granted under violation Category (w.e.f. 01.04.2017 to 31.07.2021) (In context to Applications received during Window Period)
Project Sector (e.g.Industry, Mining, Building Construction
No. of Projects
Category
Of violation whether Expansion/New (Nos.)
Action against Violation
Construction status
Under Section 15 of E(P) Act
Damage Assessment Quantified
Remediation Plan
Completed
Under construction
Not started
No information
Yes
No
Yes
No
Yes
No
Building Construction
15
Expansion: 02
00
02
00
02
00
02
-
01
01
-
New:13
00
13
07
06
00
13
09
03
-
01
Total
15
15
00
15
07
08
00
15
09
04
01
01
Observations:
Observations are as follows:
· Out of 30 project proposals, ECs have not been granted to 15 projects.
· Out of these 15 projects to whom ECs are yet to be issued:
o 09 nos. of projects have been completed
o 04 are under construction.
o 01 project is yet to be started
o No information has been made available regarding remaining
o 01 project.
o Action Under Section 15 of E(P) Act has not been taken even for a single project
o Damage assessment has been carried out only for 07 projects and remediation action plan has not been formulated for any of the projects.
7.4 Detailed status of violation cases which were received after the window period
SEIAA, UP, submitted that only one project has been received after window period (Annexure 26 D). Details are as follows:
S. N.
Project Title
Se cto r
Dat e of App lica tio n for
EC
Da te of Gr ant of EC
Categ ory of Violat ion w hethe r
Exp
ansio n/ New
Under S ection 1 5 of E(P ), Act
Bank Gu arantee Imposed
Remediation Patlan
Final Stus
Remark
8(b
) Bui ldi ng Co nst ructi o n
Expans
Action under sect
ion 15 of E(P) Act
initiated vide letter dated 07/08/202
0
The application was submitted to
EAC on 01/03/ 2018 which was transferred to SEIAA, UP as
per notification dated 08/03/2018
1
Proposed Project "Gomti River Front Channelizati on Project from Harding to Gomti Weir, Di strictLucknow, U.P
6-
11-
201
8
21-08-
20
20
ion
Letter sent to MoEF&CC
for
exemption
Submitted
EC Issued
But, from the Annexure 26A and Table 7.3.1(a), it is noted that, for most of the projects, date of application for EC are beyond the window period.
7.5 Details of projects for which post-facto ECs are granted, including the ECs for expansion projects which were in violation of existing EC:
UPPCB informed that, these information are included in Annexure-14A. Same is represented in Table 7.3.2(a).
7.6 Consideration of Disciplinary / Legal Action by other Enforcement Agencies
As per information provided by SEIAA, it is submitted that before grant of EC, they have informed that action under section 15 of the E(P) Act have been taken and UPPCB has also initiated disciplinary / legal action in such cases against the project proponent.
7.7 Details of the Agency which is monitoring the remediation action plans
The reply of SEIAA, UP is reproduced here-below:
The mechanism for compliance monitoring has been well defined in the office order issued vide file no. J-11013/10/2009-IA.I dated 30/09/2009 wherein it has been mentioned that:-
“The Monitoring Cell in IA Division is the nodal point for monitoring and compliance of the stipulated conditions imposed on the industrial units/infrastructural projects including CRZ, while granting Environmental Clearance (EC). A copy of the EC is endorsed to the concerned Regional Office of the MoEF&CC for monitoring the compliance of the stipulated conditions, besides to the concerned State Pollution Control Board (SPCB) and Central Pollution Control Board (CPCB).”
For the aforesaid purpose after the grant of EC letter issued to the concerned project proponent for the very project, the copy of the same is endorsed with enclosure for information and necessary action to:
Advisor, IA Division, Ministry of Environment, Forests & Climate Change, Govt. of India, Indira Paryavaran Bhawan, Jor Bagh Road, Aliganj, New Delhi.
Additional Director, Regional Office, Ministry of Environment & Forests, (Central Region), Kendriya Bhawan, 5th Floor, Sector-H, Aliganj, Lucknow.
District Magistrate, (Concerned District).
The Member Secretary, U.P. Pollution Control Board, TC-12V, ParyavaranBhawan, VibhutiKhand, Gomti Nagar, Lucknow.
And more specifically, SEIAA/SEAC, appraises the violation category cases as per the EIA Notification dated 14/09/2006 (as amended thereof) read along with notification dated 14/03/2017 and 08/03/2018. The SEIAA/SEAC, stipulates the implementation of Environmental Management Plan, comprising remediation plan and natural and community resource augmentation plan corresponding to the ecological damage assessed and economic benefit derived due to violation as a condition of environmental clearance. The condition implies as given below:
“The project proponent is asked to submit bank guarantee of Rs.(the sum levied) equivalent to the amount of remediation plan and natural and community resource augmentation plan within 15 days to the SPCB.
It is observed by the Committee that the reply of SEIAA doesn’t make it clear that the SPCB or the Regional Office have verified the progress of implementation of Remediation Action Plan or the Natural and Community Resource Augmentation Plan.
7.8 Types of Projects and Time Taken by SEIAA to Grant Environmental Clearances
The data provided by SEIAA was processed to assess types of projects coming up in the State and time taken for grant of Environmental Clearance to these projects. Data are presented in the following Tables No. 3.8.1 to 3.8.4:
Table 7.8.1: Project category-wise dealt with regard to granting of Environmental Clearances (Period 01.01.2017 – 25.12.2021)
Sl. No.
Project Sector
No. of Projects
1.
Building Construction
494
2.
Cement
21
3.
Highway
3
4.
Industry
104
5.
Mining
1483
Total
2105
Table 7.8.2: Status of Granting of Environmental Clearances
Sl. No.
Status of Processing of the Application
No. of Projects
1.
Absent
1
2.
Closed
149
3.
Delisted
241
4.
EC issued
1486
5.
EC revoked
1
6.
Exemption Letter
1
7.
Information SEAC
82
8.
TOR issued
5
9.
Under process
139
Total
2105
Table 7.8.3 (a): Time Taken by SEIAA to take decision on EC Applications (Period 01.01.2017 – 25.12.2021)
Sl. No.
Nos of days taken
for making
decision
No. of EC
Appln.
Sl. No.
Nos of days
taken for making
decision
No. of EC
Appln.
1.
0-30
129
21
601-630
4
2.
31-60
278
22
631-660
2
3.
61-90
230
23
661-690
3
4.
91-120
251
24
691-720
4
5.
121-150
135
25
721-750
1
6.
151-180
86
26
751-780
1
7.
181-210
50
27
781-810
1
8.
211-240
75
28
811-840
1
9.
241-270
72
29
841-870
0
10.
271-300
45
30
871-900
1
11.
29
31
2
301-330
901-930
12.
331-360
30
32
931-960
2
13.
361-390
21
33
961-990
0
14.
391-420
9
34
991-1020
0
15.
421-450
20
35
1021-1050
2
16.
451-480
5
36
1051-1080
0
17
481-510
4
37
1081-1110
1
18.
511-540
3
38
1111-1140
0
19.
541-570
0
39
1
20
571-600
6
1141-1170
Total Nos. of Projects - 1504
Table 7.8.3(b): Time Taken by SEIAA to Grant Environmental Clearance (Period 01.01.2017 – 25.12.2021)
Sl. No.
Nos of days taken to Grant EC
No. of EC
Granted
Sl. No.
Nos of days taken to Grant EC
No. of EC
Granted
1.
0-30
127
20.
571-600
6
2.
31-60
272
21.
601-630
4
3.
61-90
227
22.
631-660
2
4.
91-120
249
23.
661-690
1
5.
121-150
134
24.
691-720
4
6.
151-180
86
25.
721-750
1
7.
181-210
49
26.
751-780
0
8.
211-240
75
27.
781-810
1
9.
241-270
72
28.
811-840
1
10.
271-300
45
29.
841-870
0
11.
301-330
29
30.
871-900
1
12.
331-360
30
31.
901-930
2
13.
361-390
21
32.
931-960
2
14.
391-420
9
33.
961-990
0
15.
421-450
20
34.
991-1020
0
16.
451-480
5
35.
1021-1050
2
17.
481-510
4
36.
1051-1080
0
18.
511-540
3
37.
1081-1110
1
19.
541-570
1
38.
1111-1140
0
Total:1486
Observations are as follows:
i. For the Period of 01.01.2017 – 25.12.2021, a total of 2105 project applications were received &dealt with by SEIAA, UP for issue of EC. Out of them, EC have been issued to 1486 projects. Ground status of remaining 601 projects as on date is not intimated.
ii. During aforesaid period, mining projects predominated in the State. This was followed by building construction projects.
iii. In 745 cases, the ECs were granted within reasonable time (105 days) period.
iv. In 86 cases, the time taken to grant ECs varied from 1yr to more than 4 years. Possibility of initiation of the construction activities in such cases without obtaining EC, cannot be ruled out.
v. Delay in granting EC: Decisions have been taken by SEIAA within reasonable time for majority of the projects, but justification for the cases where inordinate delay has taken place, is not in order.
7.9 Brief Details of the NGT Matter under reference - information about the Project namely M/s Saviour Park Apartment, Mohan Nagar Ghaziabad.
In context of project under reference following observations have been made:
o PP got the approval for the site plan from Ghaziabad Development Authority on 21.06.2011.
o PP has obtained the CTE from UPPCB vide letter no. F08023/C-1/NOC/G-752/2012/6 dated 26.07.2012, before obtaining the Environmental Clearance.
o Environmental Clearance was received for project under reference vide dated 04.03.2013.
o As per record, the project was inspected by MoEF&CC, IRO, Lucknow on 30.05.2019 to review the status of stipulated EC conditions granted by SEIAA, U.P. on 04.03.2013. Subsequently, a letter of non-compliances was sent to PPs vide letter no. VII/Env/SCL-UP/510/2019/422 dated 13.08.2019. The certified compliance report indicating various noncompliance with detailed monitoring report was also sent to PPs with a copy to SEIAA, UP vide letter no. VII/Env/SCL-UP/510/2019/423 dated 13.08.2019. However, no response has been received by IRO, Lucknow against the above mentioned letter. Further, no compliance report has been received in the MoEF&CC, IRO, Lucknow since 2019 onwards.
o Additionally, PPs have obtained the Expansion EC from SEIAA, U.P. vide letter no. 788/Parya/SEAC/6057-5683/2019 dated 04.03.2021.
o PP had obtained the CTO vide dated 17/09/2020 from UPPCB which is valid till 31.07.2025.
Following violations have been reported by the five Member Committee in this matter.
· Project Proponent is supplying water to Township through bore wells but has not obtained any approval from CGWA.
· Rain Water Harvesting pits were found clogged and filled with mud and stagnant water.
· The STP operated by M/s Savfab Buildtech Pvt. Ltd in apartment is not functioning properly. Sample obtained from STP outlet is not complying with the prescribed standards.
· During the site visit, entire basement area of the project was found affected with seepage and large number of cracks were visible in many pillars upon which structural stability of all the towers resides.
· However, Joint committee also observed that, various measures with respect to EC conditions have not been taken by the PP. Compliance of EC conditions was not ensured in ’letter & spirit’.
· It was observed from the records submitted by PPs and records of project as available with UP RERA that construction of Phase II towers / flats had been started before grant of EC for Phase II.
In the matter under reference following additional information have been received from SEIAA, UP:
When was the violation noticed in the above case? Is there any gap in the appraisal process adopted by SEIAA or SPCB?
SEIAA submitted that violation has not been established as the matter is still sub-judice in Hon’ble NGT. There is no gap in the appraisal process adopted by SEIAA/SEAC.
It would be worthwhile to mention that the aforementioned project has already been categorized as a violation case by the Joint Inspection Team.
Was CTE/CTO issued in this case? Was the violation not noticed at the time of grant of CTE and CTO?
Following points are intimated by SEIAA:
Unit has obtained CTE for existing project (Total Built up area 1,55,000 sqm) vide letter dated 26/07/2012.
RO, Ghaziabad, UPPCB reported that unit has obtained CTO for existing project (Total 850 flats against 980 flats, built up area 1,55,000 sqm) vide letter dated 17/09/2020. During inspection for CTO on 26/07/2020, a total of 850 flats were observed as constructed, which is less than as permitted in CTE. No violation was noticed during inspection.
It is observed by the Committee that reply of SEIAA is not satisfactory. Further, UPPCB didn’t take cognizance of operation of tube-wells in the society without permission from CGWA. Many other non-compliances such as poor performance of STP have been observed by the Joint Inspection Committee, were not recorded by UPPCB during its routine inspections.
Chapter 8
Overall observations of the Committee
8.1 Overall observations of the Committee
· It is observed that applications in respect of a total of 2105 Projects have been received during 01.01.2017 to 25.12.2021. Further details in this matter are as follows:
o Applications processed: 2105
o ECs granted: 1486
o Present Ground status of remaining 619 projects are not known.
o Possibility of their continuation or completion of such projects cannot be ruled out.
· During aforesaid period, mining projects predominated in the State. This was followed by building construction projects.
o In some cases, the ECs are granted within reasonable time period.
o In many cases, the time taken to grant ECs varied from 1 yr to more than 4 years. Possibility of initiation of the construction activities in such cases without obtaining
EC, cannot be ruled out.
o Delay in granting EC: Decisions have been taken by SEIAA within reasonable time for majority of the projects, but justification for the cases where exorbitantly higher time have been taken is not in order. SEIAA, UP has mentioned about the Parivesh Portal and procedure in this regard.
· It is intimated by SEIAA, UP that, during window period, a total of 30 nos. of application were received. Out of these 30 projects, there are 29 construction projects and 01 is industry project. Although, these cases are received during Window Period but from the Annexure 26A and Table 7.3.1(a), it is noted that, for most of the projects, the dates of application for EC are beyond the window period. Further, out of 30 applications, ECs have been granted to 15 projects ECs to remaining 15 nos. of projects could not be granted due to various reasons.
· Further details in respect of those 15 projects to whom ECs have been granted, are as follows:
o Actions under section 15 of the E(P) Act, 1986 have been initiated for all these 15 Projects.
o Time-lines for grant of ECs were as follows:
§ Within 01 year – 10 Projects
§ 1 to 2 years – 4 Projects
§ 2-3 years – 1 Project
o Completion of Damage Assessment – 14 Projects only. It could not be undertaken for remaining 01 Project as it
belonged to the category of Government Project. Same observation was found in context to Remediation Plan.
o In some cases it is found that, two types of Bank Guarantees have been imposed. In such cases, one information has been provided by SEIAA itself and another information has been provided by SPCB. Clarification in these regard have not been provided.
o Out of these 15 projects:
§ 04 projects have already been completed
§ 06 are under construction
§ 01 project is stopped
§ No information is provided in respect of 04 projects
§ Further details in respect of those 15 nos. of projects to whom ECs are yet to be issued, are as follows:
o 09 nos. of projects have been completed
o 04 are under construction.
o 01 project is yet to be started
o No information regarding remaining 01 project.
o Action Under Section 15 of E(P) Act have not been taken for a single project
o Damage assessment has been made only for 07 projects and Remediation Action Plan is not at all formulated for any of the project.
§ Lack of coordination amongst various Agencies concerned for issuing Permissions, Clearance, Consents etc. have been noticed as mentioned in the foregoing paras. Concerned Agencies are not following the Notifications issued from time to time which is leading to violations in many cases. Further, compliance verification and monitoring could not be performed from time to time.
o The Committee feels that SEIAA could have paid greater attention as regards the following:
o Processing of EC applications including reasons having quoted for delay.
o Actions under Section 15 of the E(P) Act, 1986 against violation projects
· It is observed by the Committee that this action of monitoring of action plan undertaken recently by SEIAA through UPPCB could have been undertaken long back in these “Violation Category “ i.e. immediately after submission of such plans by the violator PPs.
· Violation of stipulated procedure has taken place during the process of grant of Expansion EC in the matter of M/s Saviour Park Apartment. Possibility of similar violation in other cases can’t overruled.
· It emerged from the replies furnished by SEIAA UP that there was:
o Lack of adherence to the Stepwise flowchart and time-lines for issue of Environment Clearance by SEIAA and lack of institutional mechanism for coordination with SPCB, Municipal Bodies, Town Planning and other enforcement agencies / designated bodies involved in sanctioning building construction projects at local level.
o Absence of well laid down procedure regarding examination of EC and sanction of plan by the Town Planning Department. It is not clear whether the approval process for Building Construction by the Town Planning Department / Municipal Bodies also includes examining whether EC has been granted and whether there is any requirement of CTE / CTO before sanctioning or issuing of Occupancy certificate by concerned Agencies/ Authorities?
o Lack of clarity regarding requirement of necessary Clearances/ NOCs/ Licenses etc. required for processing application for EC.
o Lack of clarity regarding methodology to be following for building projects or imposition of Environmental Compensation for building projects.
Besides, no specific information has been received from SEIAA, UP.
o Information with respect to Application format o Procedure adopted for processing of application
o Reasons for blatant violations taking place and how can the situation be remedied?
8.2 Identification of Issues leading to Blatant Violation
After careful examination of the information received from SEIAA, Uttar Pradesh issues leading to violation have been identified as follows:
i. Wilful violation of the provisions of EIA Notification, 2006 by the Project Proponents
ii. Suppression of the information by the Project Proponents.
iii. Processing of applications received for getting EC is not upto mark. This is including scrutinization of necessary NOCs / Licenses / Clearances from other concerned departments
iv. Time-lines prescribed for processing the EC applications are not followed.
v. Lack of coordination among the various Agencies concerned for issuing Permissions, Clearance, Consents etc.
vi. Lack of surveillance in the State especially by UPPCB, T&C Planning Department and Local Bodies.
Chapter 9
Recommendations
9.1 Recommendations
9.1.1 For Project Proponent
Project Proponents may be made aware of the concerned Environmental Regulations and Environmental Norms. Periodic workshops may be organized with the related Associations, Organizations and key Institutions so as to apprise them about the extant provisions of Acts, Rules, OMs, Procedures and the Dos and the Don’ts as far as Environmental Clearances and adherence to Environmental Safeguards are concerned.
9.1.2 For SEIAA, UP
It was observed that Member Secretary of UPPCB is also the Member Secretary, SEIAA, UP. However, this does not appear to have translated into better synergy and convergence. It is, therefore, suggested that institution mechanism for sharing information between SEIAA and UPPCB may be established to ensure efficient and effective monitoring and implementation of environmental safeguards.
It is found that, during window period for most of the projects dates of application for EC are beyond the window period. SEIAA, UP may provide clarification in this regard.
It was observed that out of the 15 projects received during Window Period for which ECs were not granted, constructions of 09 nos of projects have been completed, and 04 are under construction. Action needs to be taken in these cases by SEIAA, UP and UPPCB.
Action u/s 15 of the E(P) Act, 1986 against all the projects falling under violation category may be initiated by SEIAA, Uttar Pradesh.
It is observed that applications in respect of a total of 2105 Projects have been received during 01.01.2017 to 25.12.2021. All the 2105 Applications have been processed and ECs are granted to 1486 projects. Inspection of remaining 619 projects may be conducted to assess their current status. Action against defaulter projects needs to be initiated as per the provisions of EIA Notification, 2006, as amended and E(P) Act, 1986. Further, Environmental Compensation also needs to be imposed as per orders issued by Hon’ble Supreme Court and Hon’ble National Green Tribunal.
SEIAA, Uttar Pradesh needs to follow the Rules/Provisions of ‘Environment Impact Assessment Notification, 2006 including its amendments’ in ‘letter & spirit’ for considerations of the applications received for obtaining EC. Timelines for grant of EC need to be adhered to.
SEIAA, Uttar Pradesh may work in close coordination with State Government agencies including Uttar Pradesh Pollution Control Board, Town & Country Planning Department, Municipal Corporations, Ground Water Board, City Development Authority and other organization like CPCB (Regional Directorate) and IITs. This will facilitate transparency in the matter and effective enforcement of Legal Framework.
SEIAA may consider utilising the features of PARIVESH and also independently use the available IT Tools to assess the situation on the ground based on the latitude and longitude mentioned in the application submitted on the PARIVESH portal to ensure that construction of the Project/Activities for which EC has been asked for has not started so as to avoid grant of EC in a routine manner to “Violation Category” of Projects.
Taking a cue from the analysis of the Violation cases, it may be seen that delay in deciding upon the application for grant of ToR and processing for grant of EC may lead to a situation where the Project Proponent may be emboldened to start the Project which may result in compromising with the environmental safeguards which need to be observed. It may be worthwhile to explore the possibility of devising a method whereby PARIVESH Portal, through its own IT tool seamlessly flags the cases where there are delays beyond the specified time of 45 days post the recommendations of SEAC as mentioned in the EIA Notification,2006, as amended and generates alerts not only for SEIAA but also for the Ministry so that such cases are dealt with on priority and corrective/remedial actions are undertaken by SEIAA/EAC in the best interest of protection of the environment.
SEIAA, UP may also take support of Technology viz. Parivesh for tracking of the process of issuing EC.
ECs issued by SEIAA may be given wider publicity by posting it on the relevant Portals/Websites so as to bring in transparency and keep the stakeholders informed.
9.1.3 For SPCB
· Stake-holder consultation in the State along with the State Environment Depts., may be conducted to avoid wilful violation of the provisions of EIA Notification, 2006 by the Project Proponents.
9.1.4 For all Agencies
· Coordination amongst concerned State level Agencies may be established. These Agencies include SEIAA, UPPCB, Town & Country Planning Department and Local Bodies so far as Construction Projects are concerned and similarly amongst the key stakeholders for other Projects/Activities. There is a need for exchange of knowledge and understanding the issues of enforcement.
· Surveillance activities in the State especially by UPPCB, T&C Planning Department, Public Health Engineering Department and Local Bodies may be improved for effective monitoring of EC conditions without causing undue interference in the execution of Projects /Activities by the Project Proponent.
· Monitoring and assessment of compliance of Environmental Regulations including EC conditions and Remediation Action Plans may be conducted on regular basis by the Integrated Regional Offices. Random inspection by Integrated Task Force comprising of the Officers from these departments may be conducted for surveillance in the State and execution of illegal / unauthorized projects in the State.
9.2 Additional recommendations are as follows:
· SEIAA may co-opt Member from Town and Country Planning, Local Bodies and other concerned agencies for processing of EC applications as per need.
· EC must be issued in transparent fashion and area wise database be uploaded for the information of all concerned.”
Finding about functional audit of SEIAA
On due consideration, we see no reason not to accept the report based on verified data by credible committee. We accept the report. We find it disappointing to note the failures found on the part of SEIAA, U.P to act as per mandate of law. If the statutory regulators fail in their duties, it is difficult to understand how the Rule of Law will be protected. Let remedial measures be taken as recommended. The MoEF&CC may oversee further steps so as to ensure compliance of the recommendations within three months.
Further Directions about audits of other SEIAAs and regulators
In light of experience of above functional audit report, there is every reason to apprehend unsatisfactory functioning other SEIAAs and other regulators in other States/UTs, to the detriment of environmental rule of law which the country can ill afford. Such functional audits in respect of SEIAAs is thus called for which may be undertaken within one year by preparing a time bound action plan by the MoEF&CC. The MoEF&CC may create a dedicated cell in the Ministry for such functional audit which should not stop with the first such audit but should be a regular feature, to be undertaken periodically. All such audit reports may be placed in public domain and remedial action overseen in the light of such reports. Similar functional audits may be undertaken in respect of functioning of other statutory regulators under the MoEF&CC, including CZMAs in a like manner. Though the report of functional audit has identified violations, it has failed to suggest specific remedial action against the incumbents manning the SEIAA, which aspect may now be looked into by the MoEF&CC. Further, SEIAA should be run by the technically qualified and experienced members rather based on only administrative experience. They must have their own surveillance backup to monitor the compliances till it reaches to CTO stage instead of depending on PCB who are unable to monitor compliances, in absence of effective mechanism. This is resulting in failure of environmental rule of law to that extent, defeating the object of laying down EC conditions. Thus, necessary steps are required to be taken by MoEF&CC.
The Application is disposed of.
A copy of this order be forwarded to the MoEF&CC, all SEIAAs and Coastal Zone Management Authorities by email for compliance.
