. Heard Mr. M. V. Rai, learned Counsel for the Petitioner, Mr. V. B. Bhise, learned Counsel for the Respondent Nos.5 to 7 and Mr.. S. C. Joshi, learned AGP for the Respondent Nos.1 to 4.
By the present Petition, challenge is to the order dated 14/7/2021 passed by the Divisional Commissioner (Revenue), Amravati Division, Amravati in Revision Application No. 129/B.N.D.-54/Akoli Jahagir/Akola/ 2018, whereby the Revision Application filed by the present Respondents was allowed and set aside the order dated 4/6/2018 passed by the Additional Collector, Akola.
The Petitioner, who approached before this Court, is the original Applicant in the Revenue Proceeding. He has filed the application before the Tahsildar under Section 143 of the Maharashtra Land Revenue Code stating that he is not having the approach way to his agricultural field, and therefore, he may be provided the alternate way to approach to his agricultural field. The said proceedings were contested by the present Respondents and it was held by the Authorities that Petitioner would have an alternative approach way to the Gat No. 134 from the border (dhura) of Gat Nos.132, 133 and 137 from Akoli Jahagir to Goulkhed Road.
It is stated that before the Tahsildar, report of the Circle Officer (Mandal Adhikari), Akot was called. In his report it is stated that there was already existing way through boundary of Gat Nos. 132, 137 and 133 and same can be used by the Petitioner to approach his agricultural field Gat No. 134. Accordingly, Tahsildar allowed his application. The order of Tahsildar was challenged by the Respondents before the Respondent No. 3/Sub Divisional Officer. He has remanded back the matter to the Tahsildar.
The Tahsildar, after remanding the matter back, conducted the spot inspection and held by his order dated 21/2/2017 that Petitioner has only way to approach to his field from the boundaries of the agricultural field of Respondents. The order of Tahsildar was confirmed by the Sub Divisional Officer by his order dated 24/11/2017. So also the learned Collector confirmed the order of Tahsildar. However, the Divisional Commissioner reversed all the orders and allowed the Revision filed by the Respondents.
It is the contention of the Respondents that the report of Talathi dated 23/8/2016 was considered by the Divisional Commissioner. It is specifically stated in the report that, to the Eastern side of Gat Nos. 132, 133 and 134, there is Stream/Nullah at Mouza Narsingpurand thereafter there is a Government barren land. According to him, from that barren land, way is available to the Petitioner to approach to his field. In his report, he has also suggested that if one cement bridge is constructed over that Nullah, the entire dispute between the parties can be resolved, however, this proposal was not accepted by the present Petitioner.
In the present Petition, during pendency of the present Petition it is pointed out by the Respondent that owner of field Gat No.133, who was facing same issue, constructed a bridge of bricks and cement and same can be constructed by the Petitioner. The Respondent fairly stated that he is ready to bear half charges of construction of bridge, but the Petitioner was not ready for construction of bridge. According to him, construction of bridge over the Nullah is not permanent solution. He insisted to have approach road from the boundaries of the field of Respondents.
In my considered opinion, Divisional Commissioner needs to reconsider all the issues afresh. If only through Nullah the approach way is available to the Petitioner, then whether in rainy season Petitioner can use the said road. If not, then which will be option available with the Petitioner, whether it is permissible to construct a cement bridge over the Nullah to provide permanent approach way to the Petitioner to reach to his field.
In view of this, impugned order passed by the Divisional Commissioner dated 14/7/2021 is hereby quashed and set aside. The matter is remanded back to the Divisional Commissioner, Amravati to decide afresh on the basis of subsequent events which were taken place in the matter.
The Divisional Commissioner, while deciding the Revision Application, shall also take into consideration the proposal of the Respondent Nos.5 to 7, whereby they have stated that if the Petitioner is ready to construct the bridge to approach to his field like the owner of Gat No. 133, they are ready to bear half charges for construction of the said road.
In the light of above observation, following order is passed.
ORDER
Writ Petition is allowed.
The proceeding bearing Revision Application No. 129/B.N.D.-54/Akoli Jahagir/Akola/ 2018 is restored to the file of Divisional Commissioner, Amravati.
The Divisional Commissioner is directed to take into consideration the observations recorded by this Court along with other issues raised by the parties before this Court and decide the Revision accordingly.
Writ Petition stands disposed of in above terms. No order as to costs.