High CourtsSingle Bench(2024) 05 MP CK 0091

Samrendra Singh And Others vs State Of Madhya Pradesh And Others

Madhya Pradesh High Court · Decided on 20 May 2024

HON’BLE JUDGES
Gurpal Singh Ahluwalia, J
CASE NUMBER
Writ Petition No. 13140 Of 2024

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

37 paragraphs · 1,678 words

Gurpal Singh Ahluwalia, J

It is submitted by Shri Mohan Sausarkar that the authorities have already sent a proposal for acquisition of land belonging to the petitioners.

It is the case of the petitioners that respondent no. 7 is illegally constructing road over petitioners' land bearing Khasra No. 266 ad-measuring 0.1900 hectare (part of) and Khasra No.273 ad-measuring 0.56 hectare (part of) situated at village Barti, Tahsil Rampur Baghelan, District Satna (MP).

It is the specific case of the petitioners that the said construction is being raised without acquiring the land belonging to the petitioners.

Even according to the counsel for the State, proposal has been sent for acquisition of the land, on which, road is being constructed.

Only dispute which is being raised by Shri Mohan Sausarkar is that road was already in existence for last 40 years but now it is being repaired.

Considered the submissions made by counsel for the State.

Without adjudicating the correctness of the statement made by counsel for the State that the road is in existence for last 40 years, the only question which is required to be answered by the State is as to whether the State can claim adverse possession against residents of the State or not.

Furthermore, right to hold the property is a constitutional right as enshrined under Article 300-A of the Constitution of India.

Supreme Court in the case of Kolkata Municipal Corporation and another vs. Bimal Kumar Shah and others, decided on 16.5.2024 in Civil Appeal No.6466 of 2024 has laid down seven principles which reads as under :-

“30. Following are the seven principles:

30.1. The Right to notice : (i) A prior notice informing the bearer of the right that the State intends to deprive them of the right to property is a right in itself; a linear extension of the right to know embedded in Article 19(1)(a). The Constitution does not contemplate acquisition by ambush. The notice to acquire must be clear, cogent and meaningful. Some of the statutes reflect this right.

(ii) Section 4 of the Land Acquisition Act, 1894, Section 3(1) of the Requisitioning and Acquisition of Immovable Property Act, 1952, Section 11 of the Right to Fair Compensation and Transparency in Land Acquisition,

Rehabilitation and Resettlement Act, 2013, and Section 3A of the National Highways Act, 1956 are examples of such statutory incorporation of the right to notice before initiation of the land acquisition proceedings.

(iii) In a large number of decisions, our constitutional courts have independently recognised the right to notice before any process of acquisition is commenced.

30.2. The Right to be heard: (i) Following the right to a meaningful and effective prior notice of acquisition, is the right of the property-bearer to communicate his objections and concerns to the authority acquiring the property. This right to be heard against the proposed acquisition must be meaningful and not a sham.

(ii) Section 5A of the Land Acquisition Act, 1894, Section 3(1) of the Requisitioning and Acquisition of Immovable Property Act, 1952, Section 15 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and Section 3C of the National Highways Act, 1956, are some statutory embodiments of this right.

(iii) Judicial opinions recognizing the importance of this right are far too many to reproduce. Suffice to say that that the enquiry in which a land holder would raise his objection is not a mere formality.

30.3. The Right to a reasoned decision: i) That the authorities have heard and considered the objections is evidenced only through a reasoned order. It is incumbent upon the authority to take an informed decision and communicate the same to the objector.

(ii) Section 6 of the Land Acquisition Act, 1894, Section 3(2) of the Requisitioning and Acquisition of Immovable Property Act, 1952, Section 19 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and Section 3D of the National Highways Act, 1956, are the statutory incorporations of this principle.

(iii) Highlighting the importance of the declaration of the decision to acquire, the Courts have held that the declaration is mandatory, failing which, the acquisition proceedings will cease to have effect.

30.4. The Duty to acquire only for public purpose: (i) That the acquisition must be for a public purpose is inherent and an important fetter on the discretion of the authorities to acquire. This requirement, which conditions the purpose of acquisition must stand to reason with the larger constitutional goals of a welfare state and distributive justice.

(ii) Sections 4 and 6 of the Land Acquisition Act, 1894, Sections 3(1) and 7(1) of the Requisitioning and Acquisition of Immovable Property Act, 1952, Sections 2(1), 11(1), 15 (1) (b) and 19(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and Section 3A(1) of the National Highways Act, 1956 depict the statutory incorporation of the public purpose requirement of compulsory acquisition.

(iii) The decision of compulsory acquisition of land is subject to judicial review and the Court will examine and determine whether the acquisition is related to public purpose. If the court arrives at a conclusion that that there is no public purpose involved in the acquisition, the entire process can be set-aside. This Court has time and again reiterated the importance of the underlying objective of acquisition of land by the State to be for a public purpose.

30.5. The Right of restitution or fair compensation: (i) A person's right to hold and enjoy property is an integral part to the constitutional right under Article 300A. Deprivation or extinguishment of that right is permissible only upon restitution, be it in the form of monetary compensation, rehabilitation or other similar means. Compensation has always been considered to be an integral part of the process of acquisition.

(ii) Section 11 of the Land Acquisition Act, 1894, Sections 8 and 9 of the Requisitioning and Acquisition of Immovable Property Act, 1952, Section 23 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and Sections 3G and 3H of the National Highways Act, 1956 are the statutory incorporations of the right to restitute a person whose land has been compulsorily acquired.

(iii) Our courts have not only considered that compensation is necessary, but have also held that a fair and reasonable compensation is the sine qua non for any acquisition process.

30.6. The Right to an efficient and expeditious process: (i) The acquisition process is traumatic for more than one reason. The administrative delays in identifying the land, conducting the enquiry and evaluating the objections, leading to a final declaration, consume time and energy. Further, passing of the award, payment of compensation and taking over the possession are equally time consuming. It is necessary for the administration to be efficient in concluding the process and within a reasonable time. This obligation must necessarily form part of Article 300A.

(ii) Sections 5A (1), 6, 11A, and 34 of the Land Acquisition Act, 1894, Sections 6 (1A) and 9 of the Requisitioning and Acquisition of Immovable Property Act, 1952, Sections 4(2), 7(4), 7(5), 11(5), 14, 15(1), 16 (1), 19(2), 25, 38(1), 60(4), 64 and 80 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 and Sections 3C(1), 3D(3) and 3E(1) of the National Highways Act, 1956, prescribe for statutory frameworks for the completion of individual steps in the process of acquisition of land within stipulated timelines.

(iii) On multiple occasions, upon failure to adhere to the timelines specified in law, the courts have set aside the acquisition proceedings.

30.7. The Right of conclusion: (i) Upon conclusion of process of acquisition and payment of compensation, the State takes possession of the property in normal circumstances. The culmination of an acquisition process is not in the payment of compensation, but also in taking over the actual physical possession of the land. If possession is not taken, acquisition is not complete. With the taking over of actual possession after the normal procedures of acquisition, the private holding is divested and the right, title and interest in the property, along-with possession is vested in the State. Without final vesting, the State's, or its beneficiary's right, title and interest in the property is inconclusive and causes lot of difficulties. The obligation to conclude and complete the process of acquisition is also part of Article 300A.

ii) Section 16 of the Land Acquisition Act, 1894, Sections 4 and 5 of the Requisitioning and Acquisition of Immovable Property Act, 1952, Sections 37 and 38 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, and Sections 3D and 3E of the National Highways Act, 1956, statutorily recognise this right of the acquirer.

iii) This step of taking over of possession has been a matter of great judicial scrutiny and this Court has endeavoured to construe the relevant provisions in a way which ensures non-arbitrariness in this action of the acquirer. For that matter, after taking over possession, the process of land acquisition concludes with the vesting of the land with the concerned authority. The culmination of an acquisition process by vesting has been a matter of great importance. On this aspect, the courts have given a large number of decisions as to the time, method and manner by which vesting takes place.

Since, the right to hold property is a constitutional right and the petitioners cannot be deprived of fruits of their rights unless and until they are legally dispossessed either by acquisition or by private negotiations.

At this stage, it is submitted by counsel for the State that he may be granted two days’ time to file return.

In view of aforementioned discussions, it is directed that the respondents shall immediately remove all their encroachments from the land in dispute within two days from today, failing which, they will be liable to pay daily rent @ Rs.15,000/- (Rupees Fifteen Thousand) till the encroachment is removed.

List this case on 22/05/2024 for further hearing.