A complaint was filed in FORM ‘M’ on 02.08.2019 by Mr. Sachinanand Gupta (hereinafter referred as “Complainant”) stating that on 24.07.2015 he took the membership vide KHA051, in Colors Housing Society(hereinafter referred as “Respondents”) and booked a 2 BHK flat admeasuring 1050 sq. ft in their project namely “Krishna Heights II”.
A total sum of Rs 5,36,000/- (Five Lakh Thirty Six Thousand Only) through cheques in favour of the Respondents Colors Housing Society dated 21.07.2015, 12.08.2015 was paid by the Complainant.
Respondents had assured that the construction will begin in the year 2015 and there will be no delay in getting the approval for the land from DDA for construction of the housing society. For almost two years i.e., 2016-2018, the Complainant regularly visited the office of the Respondent i.e. Society and requested to apprise them about the construction of the flats but no proper information was received.
Since the year 2015, neither the land has been acquired nor has construction commenced. Thus, the Complainant approached this Authority seeking refund of Rs. 5,36,000/-along with 18% interest on account of playing fraud on the complaint under the garb of the ‘Land Pooling Policy’
A Preliminary hearing in the case was held on 06.09.2019 and a notice to the Respondents was issued on 03.10.2019.
Ms. Neha Pamnani, Advocate entered appearance on behalf of the Complainant. During the pendency of the matter at various stages the Respondents changed their counsels and finally the matter was argued by Mr. Nandan Jindal, Advocate on behalf of the Respondents.
The Respondents filed their reply on 21.10.2020. The rejoinder was filed by the Complainant by email on 02.12.2020. The final written submission was filed on behalf of the Complainant by email on 10.02.2021 and on behalf of the Respondents on 13.03.2021
Heard the submissions made by the Ld. Counsels for both the parties and perused the material available on record.
For the sake of convenience, the arguments and submissions made on behalf of both the parties are summarized as under:
A. Summary of submissions and arguments made by Complainant
All the averments made by the Respondents in their reply are denied by the Complainant. There is no transparency on the part of the Respondents. The competent authority i.e., Delhi Development Authority (“DDA”) never issued any notification to allow Companies/Societies/Developers and Respondents to advertise their scheme for seeking membership and booking of flats and charging money/initial deposits from the prospective members/buyers/Complainant under “Land Pooling Policy” of Delhi.
The Respondent Society did not hold any meeting with either Complainant or other members of the society. Respondents no. 2, 3 & 4 who are the office bearers of the Respondent Society did not even bother to call a general body meeting till date.
With regard to the applicability of Real Estate (Regulation & Development) Act, 2016 (hereinafter referred as “RERD Act, 2016”), following judgments are relied upon by the Complainant:
a. Hitendra Vishnu Thakur vs State of Maharastra, 1994 (4) SCC 602
b. Neelkamal Realtors Suburban Pvt. Ltd and anr. Vs. Union of India & ors, 2018(1) RCR (Civil) 298(DB).
c. M/s Pivotal Infrastructure Pvt. Ltd. Vs Prakash Chand Arohi, Haryana Real Estate Appellate Tribunal.
d. Mohammed Zain Khan Vs. Maharashtra Real Estate Regulatory Authority And Others.
B. Summary of submissions and arguments made by Respondents:
Complaint has been filed without any factual or legal ground, and hence not maintainable.
Respondent Society has been formed and established under a charitable initiative exclusively for the benefit and welfare of its valuable members. It was duly registered with the Registrar of Societies, Govt. of NCT of Delhi for which a registration certificate has been issued on 11.06.2014.
DDA (Delhi Development Authority) had announced Land Pooling Policy Regulation, 2014 applicable to urbanizable areas for urban extension.
The Respondents No. 1 duly entered into a Memorandum of Understanding on 26.09.2014 with M/s Vanshi Buildtech Pvt. Ltd. for giving land under Land Pooling Policy of DDA.
RERA Authority has no jurisdiction to entertain this complaint because the present complaint does not fall under Section 3 of the RERD Act, 2016 for multiple reasons (i) there is no sale of flats, which would be constructed only for the members of the Society and not for the sale in general public, (ii) Society does not fall under the definition of promoter, (iii) DDA is yet to allot Respondents developed plot of land in lieu of land submitted (iv) Complainant is not entitled for any compensation or interest as per Section 18 of the RERD Act, 2016 because the complaint is premature, he is not a buyer but a shareholder.
In support, of his arguments, Respondents relied upon para 298 of the case Neelkamal Realtors Suburban Pvt. Ltd and anr. Vs. Union of India & ors, 2018(1) RCR (Civil) 298 (DB) and Ireo Grace Realtech Pvt. Ltd. Vs. Abhishek Khanna and others 2021(1) RCR (Civil) 574.
An FIR has already been registered in the year 2017 against the Respondents Society and all office bearers and all accounts of the Respondents Society had been seized. The Respondents Society is ready to pay the actual amount in six equated installments to the Complainant with the condition that the Complainant will not claim any interest or compensation from the Respondents Society.
Analysis and Consideration:
It is a cardinal principle of law that a lis could be adjudicated only when the parties are not at issue or dispute. From the documents submitted in the present case it is clear that the Complainant took the membership in the Colors Housing Society, for getting a 2 + 1 BHK flat in the Project “Krishna Heights”. The Complainant paid a sum of Rs 5,36,000/- (Five Lakh Thirty Six Thousand Only) to the Respondents, which the Respondents are willing to return on the condition that the Complainant will neither claim any interest nor compensation from the Respondents.
The Respondents have neither denied the claim of membership or payments made by the Complainant. Their defence hinges upon three arguments (i) RERD Act, 2016 is not applicable in this case as there is no sale of flats, and flats are allotted to members only of the Society only (ii) Respondent Society is not covered under the RERD Act, 2016 as it does not fall under the definition of “Promoter” and (iii) The developed land is yet to be allotted by DDA under the ‘Land Pooling Policy’.
In the jurisprudence of law, there is a famous maxim ‘interest reipublicae ut sit finis litium’, which means that it is for the public good that there be an end to litigation. The RERD Act, 2016 has been enacted to ensure that in the interest of society as a whole, litigation must come to an end. The Preamble of this beneficial legislation, RERD Act, 2016 clearly resonate the legislative intent to protect the interest of consumers in real estate and establish an adjudicating mechanism for speedy redressal.
It is the first and foremost rule of interpretation that the words used in the Statue be given or interpreted in their natural and ordinary meaning. An exhaustive definition of “Promoter” is given under Section 2(zk) of RERD Act, 2016 and under Clause (iv) an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings are also defined as “promoter”. This conclusively proves that a Co-operative Housing Society which constructs apartments or buildings for its Members is covered under the ambit of RERD Act, 2016 and hence, the defence of the Respondents that it being a registered Society is not covered by the RERD Act, 2016 does not hold any merits. Further, Section 89 of the RERD Act, 2016 gives this Act overriding effect over anything inconsistent with the provisions of RERD Act, 2016. After carefully considering the provisions of the RERD Act, 2016 we are unable to agree with the contention of the Respondents that the RERD Act, 2016 is not applicable to co-operative housing societies and therefore they are not bound to register their project with RERA.
We find it unreasonable that only principal amount of Rs 5,36,000/- (Five Lakh Thirty Six Thousand Only) be refunded to the Complainant and that with the condition that he will not claim any compensation or interest thereon. The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the Promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Real Estate Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, along-with interest to the allottees (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., LL 2021 SC 641).
Thus, in the light of the aforesaid, we consider it appropriate to direct the Respondents Society to refund the entire amount of Rs 5,36,000/- to the Complainant within 45 days of issuance of this order along with interest at the rate of 9% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No orders as to costs