High CourtsSingle Bench(2015) 02 MAD CK 0105

S. Sampath vs The Joint Registrar/Managing Director and Others

Madras High Court · Decided on 4 February 2015

HON’BLE JUDGES
K.K. Sasidharan, J.
RESULT
Partly Allowed
CASE NUMBER
Writ Petition No. 25884 of 2014

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

13 paragraphs · 850 words

K.K. Sasidharan, J.—This Writ Petition is directed against the order dated 8 August 2014, whereby and whereunder, the revisional authority upheld the order dated 30 September 2013 on the file of the 1st respondent, refusing to permit the petitioner to retire on account of the pendency of enquiry under Section 81 of the Cooperative Societies Act.

Summary of facts :-

2.

The petitioner was initially appointed in the erstwhile South Arcot District Cooperative Bank as Clerk and thereafter, he was absorbed in the service of the Villupuram District Central Cooperative Bank Ltd. with effect from 2 May 1997. The petitioner was promoted as Assistant Manager. The petitioner functioned as Field Manager, Villupuram Circle, from 4 June 2012 to 30 September 2013.

3.

The petitioner was given the task of supervision of 46 Primary Agricultural Cooperative Credit Societies in Villupuram Circle. The petitioner, on the basis of his inspection, submitted a report with respect to the functioning of a society by name Kandamanady Primary Agricultural Cooperative Society. The first respondent, pursuant to the said report, constituted a committee, in which the petitioner was also a member, to scrutinize the accounts of the society and to ascertain the exact amount of misappropriation. The petitioner, along with the other members of the committee, submitted a report on 2 February 2013. The first respondent made a request before the Deputy Registrar of Cooperative Societies to order an enquiry under Section 81 of the Cooperative Societies Act. The Deputy Registrar initiated proceedings pursuant to the said request. The petitioner was summoned to appear before the enquiry officer. The petitioner appeared before the Enquiry Officer and submitted his statement.

4.

While so, the petitioner attained the age of superannuation on 30 September 2013. However, he was not permitted to retire on account of the pendency of proceedings under Section 81 of the Act. The order refusing to permit him to retire from service was challenged before the second respondent by invoking Section 153 of the Tamil Nadu Cooperative Societies Act. The second respondent, confirmed the said order. Feeling aggrieved, the petitioner has come up with this Writ Petition.

5.

The first respondent has filed a counter affidavit wherein it was contended that the Deputy Registrar of Cooperative Societies by letter dated 23 September 2013, informed the Bank that Section 81 enquiry in respect of Kandamandy and Premadesam Primary Agricultural Cooperative Credit Society is pending and as such, it would not be possible to permit the petitioner to retire from service.

6.

Heard the learned counsel for the petitioner and the learned Standing Counsel for the respondents.

Discussion :-

7.

The petitioner functioned as Field Manager, Villupuram Circle, in his capacity as Assistant Manager of Villupuram District Central Cooperative Bank. The petitioner appears to have found certain acts of misappropriation committed by the officials of two cooperative societies and the same resulted in initiating proceedings under Section 81 of the Cooperative Societies Act by the Deputy Registrar of Cooperative Societies. There is nothing on record to show that there were allegations against the petitioner, warranting action to be taken against him. When the petitioner attained the age of superannuation, he was not permitted to retire, solely on the ground that enquiry under Section 81 of the Tamil Nadu Cooperative Societies Act is pending. Pendency of the statutory enquiry against the officers of two Cooperative Societies cannot be a reason to keep the petitioner in service notwithstanding his superannuation on 30 September 2013.

8.

The respondents were given sufficient time to produce materials to show that the petitioner was a party to the act of misconduct committed by the officials of the societies concerned. The respondents failed to produce even a single document before this Court to show that the petitioner was a privy to the transaction. The so called pendency of enquiry under Section 81 of the Cooperative Societies Act should not cause prejudice to an employee who was instrumental in submitting a report to the Cooperative Society, with regard to the acts of mismanagement committed by the officials of the societies in question. The revisional authority has made certain observations with respect to the merits of the case without any supporting material. The only reason for keeping the petitioner in service appears to be the pending proceedings under Section 81 of the Act.

9.

The respondents have miserably failed to produce materials before this Court to substantiate the reasons to retain the petitioner in service. Therefore, I am of the view that the petitioner is entitled to succeed.

10.

In the result, the impugned order is set aside. The first respondent is directed to pass a consequential order, permitting the petitioner to retire from service. He should be paid the retirement benefits. It is open to the respondents to take further action against the petitioner to recover the loss even after retirement, in case there is a finding that he was also responsible for causing loss to the society and a consequential order of quantification of such loss.

11.

The Writ Petition is allowed to the extent indicated above. No costs. Consequently, M.P. No.1/2014 is closed.