High CourtsSingle Bench(2020) 06 DEL CK 2496

RSCPL-RCC(JV) vs The Public Works Department Government Of Uttar Pradesh

Delhi High Court · Decided on 18 June 2020

HON’BLE JUDGES
C. Hari Shankar, J
RESULT
Allowed
CASE NUMBER
O.M.P.(MISC.)(COMM.) 131/2020 & I.As.4607-08/2020

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

4 paragraphs · 120 words
1.

This is a petition under Section 29A of the Arbitration & Conciliation Act, 1996, preferred by the petitioner M/s RSCPL-RCC (JV), seeking that the time granted for conclusion of the arbitral proceedings, pending before the learned Arbitral Tribunal consisting of Hon’ble Mr. Justice Badar Durrez Ahmed, Hon’ble Mr. Justice R.C. Chopra and Mr. A.K. Gupta, be extended by a period of three months till 2nd September, 2020.

2.

Mr. Suvir Sharma, learned Counsel for the respondent, has no objection.

3.

Accordingly, the time for conclusion of arbitral proceedings by the aforesaid learned Arbitral Tribunal is extended by a period of three months i.e. till 2nd September, 2020.

4.

The petition is allowed and disposed of in the aforesaid terms.