High CourtsSingle Bench(2005) 08 JH CK 0083

R.L. Kochar vs Jharkhand State Electricity Board and Others Industrial Forge and Engineering Co. Ltd. Vs Appellate Authority for Industrial and Financial Reconstruction and Others

Jharkhand High Court · Decided on 25 August 2005 · Citation: (2005) 4 JCR 378a

HON’BLE JUDGES
S.J. Mukhopadhaya, J
RESULT
Dismissed
CASE NUMBER
WP (C) No. 3717 of 2003 with CWJC No. 2169 of 2001

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

4 paragraphs · 208 words

S.J. Mukhopadhaya, J.—Today when the above cases were taken up, Mr. Sanjeev Kr. Mishra, learned counsel appearing for the petitioners submitted that the Company has deposited a further sum of Rs. 5 lacs with the JSEB on 14th May, 2005. After depositing the amount, the matter has been taken up by the Chairman, JSEB to resolve the dispute. It is informed that the matter is pending with the Chairman of JSEB, wherein, prayer has been made to reduce the bill on the grounds, mentioned in the representation.

2.

Counsel for the petitioners further submitted that the petitioners intend to pursue the Chairman of JSEB to take a decision on their representation, on merit and the Company is expecting that a favourable decision may be taken by the JSEB. It is further informed that the petitioners also intend to file objection u/s 9 of the Public Demand Recovery Act before the Certificate Officer.

3.

Prayer has, accordingly, been made to allow the petitioners to withdraw the writ petitions to enable them to approach the Chairman, JSEB, for decision on their representation, on merit, and to prefer objection before the Certificate Officer and for interim relief. The petitioners are so permitted.