High CourtsSingle Bench(2021) 10 SHI CK 0082

Renuka Ji Dam And Others vs Jiwan Singh And Others

High Court Of Himachal Pradesh · Decided on 29 October 2021

HON’BLE JUDGES
Tarlok Singh Chauhan, J
RESULT
Dismissed
CASE NUMBER
Regular First Appeal Nos.313, 314, 315, 316, 317, 318, 319, 320, 321, 322, 323, 324 Of 2018, 69, 70, 71, 72, 73, 74, 75 Of 2021

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

6 paragraphs · 167 words

Tarlok Singh Chauhan, J

1.

The learned counsel for the parties are ad idem that the issue in question is squarely covered by the judgment rendered by a Co-ordinate Bench of this Court in RFA No. 370 of 2014, titled 'The Renuka Dam Project and another vs. Sh. Surender Singh and others, alongwith connected matters, decided on 02.11.2018. The directions and observations contained in the aforesaid judgment shall apply mutatis mutandis to all these appeals.

2.

Accordingly, appeal Nos. 313 to 324 of 2018 filed by the appellants-Renuka Ji Dam Project, are dismissed.

3.

As far as appeal Nos. 69 to 75 of 2021 filed by the claimants/petitioners are concerned, they are allowed by holding the claimants/petitioners entitled for compensation of Rs.5,00,000/- per bigha of land on the basis of the judgment cited supra.

4.

It goes without saying  that the benefit of this judgment shall be extended even to the proforma respondents in case they are entitled to compensation.

5.

All pending applications stand disposed of.