High CourtsDivision Bench(2018) 02 DEL CK 0204

Ravi Dutt Sharma And Anr. vs Govt. Of Nct Of Delhi & Ors

Delhi High Court · Decided on 6 February 2018

HON’BLE JUDGES
G.S.Sistani, J · Sangita Dhingra Sehgal, J
RESULT
Disposed Of
CASE NUMBER
Civil Writ Petition No. 7239 Of 2016

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

31 paragraphs · 547 words

G. S. Sistani, J

1.

By the present writ petition filed under Article 226 of the Constitution of India, the petitioners seek a declaration that the acquisition proceedings

with respect to the land of the petitioners i.e. agricultural land in village Karala in Rectangle No. 37/1 Khasra Nos. 6/1 (0-04), Khasra No. 38/1/2 (2-

16), 2/1 (0-7), Khasra No. 38 2/2 (4-9) 3 (4-9), 9/1 (3-16), 10 (4-12), Khasra No. 38/1 9/2 (1-0), 11/2 (4-9), 12/1 (3-16) (hereinafter referred to as

‘Subject Land’), has lapsed in view of Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation

and Resettlement Act, 2013 (hereinafter referred to as ‘2013 Act’), as neither the compensation has been paid nor the physical possession has

been taken.

2.

In this case, a notification under Section 4 of the Land Acquisition Act, 1894 was issued on 25.08.2005. A declaration under Section 6 of the said

Act was made on 10.07.2006 and thereafter an award was pronounced by the Land Acquisition Collector on 26.05.2008 with respect to 1905 Bighas

05 Biswa of land in Village Karala.

3.

Learned counsel for the petitioner submits that the case of the petitioner is fully covered by the decision rendered by the Apex Court in Pune

Municipal Corporation & Anr. V. Harak Chand Misiri Mal Solanki & Ors., reported in (2014) 3 SCC 183, as neither compensation has been paid nor

possession has been taken.

4.

Counter affidavit has been filed by the LAC as also by DSIIDC, the beneficiary department.

5.

According to the counter affidavit filed by LAC, the physical possession of the subject land has been taken and compensation has been tendered to

the owners of the land.

6.

Ms. Salwan, learned counsel appearing for DSIIDC has drawn the attention of the Court to paras 7 to 12 of the counter affidavit to show that

physical possession of the subject land has been taken and compensation has been tendered to the petitioners by cheque Nos. 733946 and 733947 both

dated 15.04.2009 for Rs.39,95,182/-each.

7.

Ms. Salwan submits that vide order dated 01.10.2008, the Government of NCT of Delhi decided to give Special Rehabilitation Package for the

people affected by land acqustion and enhanced compensation was given to the petitioners to rehabilitate themselves. She further submits that the

petitioners denied the benefit of Special Rehabilitation Package and received additional compensation vide cheque Nos. 929512 and 929513 both dated

13.12.2011 for Rs.34,86,146/- each.

8.

Ms. Salwan further submits that after taking possession of the subject land for public purpose of ‘Developing New Industrial Area’, the

DSIIDC in order to protect the land from encroachment, awarded the work of construction of boundary wall around the acquired land and executed

an agreement No. DSIIDC/CPM (CD-VIII)/Actts./2010-2011/01 dated 04.05.2011. Photographs showing the construction of boundary wall have also

been annexed along with the counter affidavit.

9.

Ms. Salwan further submits that as per the undertaking furnished by the petitioners at the time of receiving the payment of Special Rehabilitation

Package having given up their all rights make it abundantly clear that they are not in possession of the subject land.

10.

At this stage, Mr. Chandiwal, learned counsel for the petitioner wishes to withdraw the present petition.

11.

Accordingly, the present writ petition is dismissed as withdrawn.