High CourtsSingle Bench(2009) 07 DEL CK 0486

Raripur Rotocast-Ravi and Co. vs Union of India (UOI) and Another

Delhi High Court · Decided on 29 July 2009

HON’BLE JUDGES
Sanjiv Khanna, J
CASE NUMBER
Writ Petition (C) 1354 of 1995

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

26 paragraphs · 1,605 words

Sanjiv Khanna, J.—The petitioner M/s Raipur Rotocast-Ravi and Company is a joint venture partnership firm, which was awarded contract for conversion of meter gauge railway lines into broad gauge railway lines from Jodhpur to Jaisalmer and loading of rails, sleeper points, cutting, drilling, pairing and dispatching to the work site at Bhagat-ki-Kothi/Banar vide letter dated 18th May, 1994. The said works were required to be completed within six months. It is the contention of the petitioner that after initial formalities were completed, the petitioner contacted the respondent officers and commenced the work on the site on 20th May, 1994 by mobilization of resources, which involved bringing to the site highly specialized equipment for unloading of rails, their cutting, drilling, pairing and dispatching. The petitioners claim that between 20th May, 1994 to 4th June, 1994 they had executed work to the tune of Rs. 25,00,000/-.

2.

On 4th June, 1994, the respondent verbally informed the petitioner to suspend the work, which the petitioner did under protest. The petitioner wrote letters dated 6th June, 1994, 20th June, 1994 and 23rd June, 1994 to the respondents protesting against the closure/suspension of work.

3.

The respondents by their letter dated 28th July, 1994 terminated the contract of the petitioner under Clause 61 of the General Conditions of Contract to invite fresh tenders for the same work.

4.

The petitioner filed W.P. (C) No. 3215/1994 against the said termination. While the writ petition was pending, fresh tenders were opened and the petitioner, who had participated in the fresh tenders under protest, was awarded the same contract. On the basis of statement made by the respondents, on 26th August, 1994 the following order was passed in the said writ petition.

CW 3215 & CM 6013/94

Mr. Birbal states that after the fresh tenders were opened and processed the petitioner was still found to be the lowest tenderer. He says, on instructions:

1.

That the work will be awarded to the petitioner.

2.

As far as the work already done by the petitioner under the earlier tender is concerned his bill will be processed expeditiously as per rule and payment made to him within six weeks from today.

3.

Whatever further amount, if any, is due to the petitioner under the earlier contract that shall also be processed and paid within three months as a committee will have to be constituted for the purpose.

In this view of the matter, Mr. Jaitley does not press this petition. Dismissed as withdrawn.

Interim order made earlier shall stand vacated.

Copy of the order be given to counsel for both the parties.

5.

In terms of the said order, the petitioner made a representation in form of a claim petition dated 28th September, 1994. The said claim petition has been rejected by Chief Engineer vide letter dated 15th December, 1994. The said letter reads as under:

Dear Sirs,

The claims submitted by you under Clause 61(2) of the General condition of contract in connection with above noted contract have been examined carefully. It has been decided that nothing is due to you. Payment as due for the work done has already been made to you.

6.

The aforesaid order rejecting the claim petition is cryptic and a non- speaking order. It does not deal with the contentions of the petitioner/claim raised by the petitioner and why and for what reason the same is not acceptable. It may be appropriate here to refer to Clause 61 of the General Conditions of Contract, which applies in case of determination of contract by the Railways. The said Clause reads as under:

DETERMINATIION OF CONTRACT

61.

(1) Right of Railway to determine contract.- The Railway shall be entitled to determine and terminate the contract at any time should, in the Railways opinion, the cessation of work becomes necessary owing to paucity of funds or from any other cause whatever, in which case the value of approved materials at site and of work done to date by the Contractor will be paid for in full at the rates specified in the contract. Notice in writing from the Railway of such determination and the reason therefore shall be conclusive evidence thereof.

(2) Payment on determination of contract.-

Should the contract be determined under sub-clause (1) of this clause and the Contractor claims payment for expenditure incurred by him in the expectation of completing the whole of the works, the Railway shall admit and consider such claims as are deemed reasonable and are supported by vouchers to the satisfaction of the Engineer. The contractor shall have no claim to any payment of compensation or otherwise how so ever on account of any profit or advantage which he might have derived from the execution of the work in full but which he did not derive in consequence of determination of the contract. The Railways decision on the necessity and propriety of such expenditure shall be final and conclusive.

7.

Under Clause 61(1), Railways have the right to determine and terminate a contract owing to paucity of funds or for any other cause and thereupon the contractor is entitled to payment of value of the approved material at site and the work done. Under Clause 61(2), the contractor upon termination of contract can make a claim for payment of expenditure incurred by him in expectation of the whole work and the Railways are required to consider the claims. Only such claims, which are deemed to be reasonable and supported by vouchers to the satisfaction of the Engineer, are required to be paid. No claim for compensation or damages or loss of profit or advantage can be entertained. Clause 61(2) further states that the decision of the Railways, i.e., the Engineer on the necessity and propriety of expenditure is final and conclusive. Clause 61 falls under the category of excepted matters and the decision of the Engineer and the satisfaction of the Engineer under Clause 61(2) cannot be made subject matter of arbitration in view of Clause 63 of the General Conditions of Contract. In other words, as far as Railways are concerned, there is finality attached to the said determination and satisfaction of the Engineer.

8.

Keeping in view the nature of he said clause, the finality attached to it and the language used in the said clause stipulating that the Railways shall admit and consider claims, which are reasonable and supported by vouchers, a speaking and a reasoned order is required and necessary. The petitioner along with the claim petition had submitted vouchers and had tried to justify the claim. The petitioner also relies upon parawise reply submitted to the Committee for Settlement of Disputes. It is alleged that the reply contains admissions both on admissibility as well as quantification in some cases and admissibility in other cases, while some claims are disputed. Learned Counsel for the respondents, on the other hand, has drawn my attention to confidential report attached to the counter affidavit as per which a committee had recommended rejection of all claims. The said confidential report/recommendation of the committee was not circulated and informed to the petitioner. It is also the contention of the petitioner that Clause 36 of the General Conditions of Contract and Clause 21(5) of the Special Conditions of Contract and Instructions to Tender of contract were not relied upon by the respondent Railways and the petitioner was never confronted and asked to meet objections based upon the two clauses. It is submitted that Clause 61(2) has to be read harmoniously along with Clause 36 of the General Conditions of Contract and Clause 21(5) of the Special Tender Conditions and Instructions to Tenders. It may be also noticed that the confidential report of the committee attached with the counter affidavit is only a recommendation. Ultimately, it is satisfaction of the Engineer, i.e., the Chief Engineer in the present case, which matters as per Clause 61(2) of the General Conditions of Contract. The order dated 15th December, 1994 passed by the Chief Engineer does not mention any reason or ground for rejection of the claim under Clause 61(2) of the General Conditions of Contract. The petitioner was not confronted and asked to reply to the report of the Committee. It is not possible for the Court to decipher what weighed with the Chief Engineer to reject the claims. It is thus difficult to sustain the said order. Order dated 15th December, 1994 is accordingly quashed and set aside and the matter is remanded back to the Chief Engineer (Construction) for fresh decision.

9.

In view of the reorganization in the Railways, the matter will have to be decided by the concerned Chief Engineer of North West Railway, Jodhpur as stated by the counsel for the respondents. Fresh decision will be made expeditiously and preferably within a period of five months from today.

10.

The petitioner will appear before the Chief Engineer, North West Railway, Jodhpur on 10th August, 2009 at 2 p.m., when further date will be fixed .

11.

It is clarified that this Court has not expressed any opinion on the merits of the claim made by the petitioner and whether the claims fall within Clause 61(2) of the General Conditions of Contract or whether the claims are barred in view of Clause 36 of the General Conditions of Contract or Clause 21(5) of the Special Tender Conditions or Instructions to Tenders. In case the petitioner is aggrieved by the decision, they will be entitled to challenge the same in accordance with law.

12.

The writ petition is disposed of. In the facts and circumstances of the case, there will be no order as to costs.