High CourtsSingle Bench(2014) 11 P&H CK 0141

Ranjit Singh vs State of Punjab and Others

Punjab And Haryana At Chandigarh · Decided on 19 November 2014 · Citation: (2014) 1 RCR(Rent) 971 : (2015) 1 SCT 705

HON’BLE JUDGES
Mahesh Grover, J
CASE NUMBER
C.W.P. No. 14874 of 1993 (O&M)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 650 words

Mahesh Grover, J.—The petitioner impugns the award of the Labour Court dated 20.7.1993. He pleaded that he had worked as a dak runner for 89 days w.e.f 1.7.82 to 24.6.1983 with notional breaks of one day after each term of 89 days, in the pay scale of 300-430. Subsequently the petitioner continued to discharge his duties as a Chowkidar on similar terms w.e.f 15.9.1983 till 28.2.1986. His services were eventually terminated on May, 1987. Respondents partially admitted the claim of the petitioner and gave out in their reply the period during which he worked. It is necessary to extract the details of the periods that the petitioner was made to work:-

2.

It was also admitted by the petitioner that he worked as Muzdoor on Muster Roll from 11/1986 to 6/1987 on daily wages. The Tribunal framed the following questions for determination:-

i) Whether the order of termination of services of the workman is justified & in order?

ii) Relief.

3.

A perusal of the award reveals that the reasoning adopted by it to dismiss the claim of the petitioner is totally perverse. No attempt has been made by the Tribunal to address the core issue as to whether the petitioner was a workman as defined in the Industrial Disputes Act. No finding was recorded by the Tribunal as to whether the petitioner had completed 240 days of employment in the year preceding his termination.

4.

As per the conceded case which has emerged from the pleadings of the parties before the Tribunal the petitioner had worked for a substantial number of years and lastly before his termination he had worked as a Muzdoor from 11/1986 to 6/1987.

5.

The plea of the respondents is that the petitioner was engaged against the scheme which has since been shut down. Therefore the services of the petitioners were terminated in accordance with principle of last come first go. Even this finding has not been recorded by the Tribunal. No evidence in this regard has been discussed. If this was the plea taken by the respondents then it was incumbent upon the Tribunal to atleast note whether the petitioner was indeed the last person or junior employee to warrant his termination. This Court, thus, has little hesitation to hold that the award of the Tribunal is totally arbitrary and unjust since there is material on record regarding the period of engagement of the petitioner which is undisputed. The Court would unhesitatingly accept the same. It is evident that the respondents have not offered any justification for termination and have not shown any material to indicate that provisions of Section 25F were ever complied with. Considering the length of engagement and the fact that provisions of Section 25F do not stand complied with, and similarly nothing is on record to justify the plea of discontinuance of scheme and petitioner being the last in the seniority to warrant his departure from service first, the petitioner''s termination would necessarily have to be termed illegal. This takes the Court to the next question as to what relief can be granted to the petitioner at this stage of the proceedings when petition has remained pending before this Court for last more than two decades. The reply filed by the respondents indicate that the scheme against which the petitioner was appointed stands concluded and terminated. There would thus be no question of reinstatement in these circumstances. The only alternate left with the Court is to explore the possibility of granting compensation to the petitioner considering the length of engagement of the petitioner which is more than continuous w.e.f 15.9.1983 till 28.2.1986 and the nature of employment, this Court would deem it appropriate to grant a consolidated sum of Rs. 2 lacs to the petitioner which will carry an interest at the rate of 7% per annum from the date of his termination till the date of realization.

Disposed of.