AI Structured Summary
Not yet generated for this judgment
Judgment
N.S. Ravi, Member.
This is a revision against the order passed by Divisional Commissioner Jhansi on 2222000 in Revision No. 47/992000 arising out of an interim order passed by S.D.O. Tal Behat in a declaratory Suit No. 74/9899 on 251099. By the impugned order the learned Commissioner has held that the title suit Bearing No. 5/992000, Har Dass and others v. Randhir Singh and others, under Section 229B be decided first and then proceedings under Section 176 be taken up. The revisionist has come to this Board against this order. It appears from the papers that regarding the same plots of land two suits were pending before S.D.O. Tal Behat. One under Section 229B of the U.P.Z.A. and L.R. Act and another under Section 176 of the U.P.Z.A. and L.R. Act. An application under Section 10 C.P.C. was moved before the trial Court on 251099 requesting that first the declaratory suit be decided and then the partition suit. On this application the learned trial Court passed the impugned order dated 251099 directing that both case be heard simultaneously on same dates. Against this order revision was filed before the learned Commissioner which was disposed of by the impugned order.
The revisionist before the Board agitates that no notice was issued by the revisional Court and the order is exparte , illegal and arbitrary as well as without jurisdiction. I see no irregularity in the impugned order passed by Divisional Commissioner which simply a direction to the trial Court first to decide the claims of the contesting parties and then proceed for partition.
Revision is devoid of any merit and misconceived which is dismissed. The trial Court is directed to abide by the directions issued by the Divisional Commissioner to decide the suit expeditiously within six months.
Revision dismissed.