Tribunals and CommissionsSingle Bench(2023) 06 NCLAT CK 3173

Rajesh Kumar Tripathi vs Era Housing & Developers (P) Ltd. & Ors.

National Company Law Appellate Tribunal, New Delhi · Decided on 1 June 2023

HON’BLE JUDGES
Rakesh Kumar Jain, J
CASE NUMBER
Company Appeal (AT) (Insolvency) No. 357 of 2020 & I.A. No. 1925 of 2022
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

37 paragraphs · 3,839 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Per: Justice Rakesh Kumar Jain:

This appeal is directed against the order dated 03.12.2019, passed by the Adjudicating Authority (National Company Law Tribunal, Principal Bench, New Delhi), by which an application bearing CA 331 (PB)/2019 filed in CP (IB) No. 489 (PB)/2017 under Section 33 of the Insolvency and Bankruptcy Code, 2016 (in short ‘Code’) by the Resolution Professional (RP) seeking direction for liquidation of the Corporate Debtor ‘M/s Era Housing & Developers (India) Limited’ has been allowed and Sunil Kumar Gupta has been appointed as the Liquidator in terms of Section 34(1) of the Code.

2.

IFCI Limited, one of the Financial Creditor, filed an application under Section 7 of the Code bearing IB-489(PB)/2017 to initiate the Corporate Insolvency Resolution Process (in short ‘CIRP’) against the Corporate Debtor. The application was admitted by the Adjudicating Authority on 08.02.2018 and Vikram Kumar was appointed as the Interim Resolution Professional (IRP). In the first meeting of the Committee of Creditors (COC) held on 08.03.2013 the IRP was appointed as RP in the matter of the Corporate Debtor. The RP filed CA 331(PB)/2019 under Section 33 of the Code for initiation of liquidation process of the Corporate Debtor, inter alia, on the ground that despite best efforts, no resolution plan has been received and the CoC by way of 100% voting share resolved that the Corporate Debtor be liquidated in accordance with the provisions of Section 33(2) of the Code and the RP was further authorised to file an application before the Adjudicating Authority under Section 33(2) of the Code for seeking liquidation of the Corporate Debtor.

3.

The Adjudicating Authority found that “in the facts and in the absence of any approved resolution plan and for want of time bound statutory CIRP period; there is no other alternative left but to order in conformity with the unanimous decision of the CoC for liquidation of the Corporate Debtor under Section 33(1)(a) of the Code”. Since, the RP showed his inability to act as a liquidator, therefore, the Adjudicating Authority appointed Sunil Kumar Gupta as the Liquidator and issued further directions.

4.

The order dated 03.12.2019 has been challenged in this appeal by Rajesh Kumar Tripathi who is allegedly one of the allottees in the project, namely, Era Green World, Sector 8, Palwal, District Faridabad. He has filed this appeal making categorical averment in Para 7.2 of the facts that he is representing a group of allottees who have been allotted units in the project ‘Era Green World’ being developed by Adel Landmarks (Parent Company). The payments have been made by the allottees for their respective units to the Parent Company, however, the land was held by the subsidiaries i.e. Mehak Realtech Pvt. Ltd., Sachet Infrastructure Pvt. Ltd., Sameeksha Estates Pvt. Ltd., Magad Realtors Pvt. Ltd., Digamber Buildcon Pvt. Ltd. and Jamvant Estates Pvt. Ltd. (Subsidiary Companies) at Palwal in Sector 8 and 9 in terms of the licences no. 46 of 2009 and license no. 53 of 2009 issued in their favour by the town and country planning department, Govt. of Haryana.

5.

It is alleged that the impugned order passed by the Adjudicating Authority is contrary to the order passed by this Appellate Tribunal in CA (AT) (Ins) No. 377 of 2019 titled as ‘Edelweiss Asset Reconstruction Company Limited Vs. Sachet Infrastructure Pvt. Ltd.’

6.

It is pertinent to mention that Edelweiss Asset Reconstruction Company Ltd. filed CP No. (IB) 1083(PB) of 2018 against the parent company (Adel Landmarks) under Section 7 of the Code which was admitted by the Adjudicating Authority on 05.12.2018 and Udayraj Patwardhan was appointed as IRP.

7.

It is also pertinent to mention that Edelweiss Asset Reconstruction Ltd. also filed an application under Section 7 of the Code for initiation of CIRP against the subsidiary companies which was dismissed on 07.03.2019.

8.

Against the order of dismissal 07.03.2019, Edelweiss Asset Reconstruction Company Limited came up with nine appeals before this Tribunal, namely, CA (AT) (Ins) No. 377 of 2019, CA (AT) (Ins) No. 378 of 2019, CA (AT) (Ins) No. 379 of 2019, CA (AT) (Ins) No. 380 of 2019, CA (AT) (Ins) No. 381 of 2019, CA (AT) (Ins) No. 382 of 2019, CA (AT) (Ins) No. 383 of 2019, CA (AT) (Ins) No. 384 of 2019 and CA (AT) (Ins) No. 385 of 2019.

9.

It is pertinent to mention that while CIRP was going on against the principal borrower ‘Adel Landmarks’, Edelweiss Asset Reconstruction Company Limited, in whose favour Corporate Guarantee was given by other Corporate Guarantors for securing the loan disbursed to the Adel Landmarks (Principal Borrower), separate applications under Section 7 of the Code were filed by the Financial Creditors and on dismissal of the applications, aforesaid nine appeals were filed which were taken up together by this Tribunal and in its order dated 20.09.2019 held that “for the said reasons, we hold that group CIRP proceeding is required to be initiated against five Corporate Debtors, namely, Sachet Infrastructure Pvt. Ltd., Magad Realtors Pvt. Ltd., Mehak Realtech Pvt. Ltd., Sameeksha Estate Pvt. Ltd. and Jamvant Estates Pvt. Ltd. apart from the CIRP which has already been initiated against Adel Landmarks Limited (Principal Borrower). This Tribunal further made the following observations:-

“41.

In view of our findings and as the Adjudicating Authority has failed to appreciate the relevant fact that in the facts and circumstances, a group insolvency is to be initiated and in absence of simultaneous ‘Corporate Insolvency Resolution Process’ against five ‘Corporate Debtors’ namely— ‘Sachet Infrastructure Pvt. Ltd.’; ‘Magad Realtors Pvt. Ltd.’; ‘Mehak Realtech Pvt. Ltd.’; ‘Sameeksha Estate Pvt. Ltd.’ and ‘Jamvant Estates Pvt. Ltd.’, the township project of Town and Country Planning, Haryana, will not be complete, we set aside the impugned order dated 7th March, 2019 and remit the case to the Adjudicating Authority with following directions

42.

The Adjudicating Authority will admit the applications under Section 7 filed by ‘Edelweiss Asset Reconstruction Company Limited’ against ‘Sachet Infrastructure Pvt. Ltd.’; ‘Magad Realtors Pvt. Ltd.’; ‘Mehak Realtech Pvt. Ltd.’; ‘Sameeksha Estate Pvt. Ltd.’ and ‘Jamvant Estates Pvt. Ltd.’ and appoint the ‘Resolution Professional’ of ‘Adel Landmarks Limited’- (Developer) (‘Principal Borrower’) as common ‘Resolution Professional’ to ensure that the ‘Corporate Insolvency Resolution Process’ against ‘Adel Landmarks Limited’- (‘Corporate Debtor’) proceed jointly and ‘Information Memorandum’ is prepared in a manner that the ‘Residential Plotted Colony’ at village Palwal at Sectors 8 & 9 in terms of the License No. 46 of 2009 and License No. 53 of 2009, is completed in one go by initiating a consolidated ‘Resolution Plan(s)’ for total development.

43.

In so far the case of ‘Superlative Infrastructure Pvt. Ltd.’, ‘Bhisham Infrastructure Pvt. Ltd.’, ‘Neeleshwar Mines & Minerals (India) Pvt. Ltd.’ and ‘Manogayan Estates Pvt. Ltd.’ are concerned, their matter are remitted back to the Adjudicating Authority. The Appellant and the ‘Corporate Debtors’ may produce relevant Agreements to show that the ‘Adel Landmarks Limited’- (‘Principal Borrower’) against which the ‘Corporate Insolvency Resolution Process’ has been initiated is common Developer. In such case, one or other ‘Corporate Debtor’ if show the same, the Adjudicating Authority on hearing the parties will admit their applications so as to enable the other projects are also completed of which ‘Adel Landmarks Limited’- (‘Principal Borrower’) is the Developer.

44.

In the result, Company Appeal (AT) (Insolvency) Nos. 377, 379, 380, 381 & 385 of 2019 are allowed with directions as given above. Company Appeal (AT) (Insolvency) Nos. 378, 383, 382 and 384 of 2019 are remitted back to the Adjudicating Authority with observations and directions, as recorded above.”

10.

At the time of preliminary hearing of this appeal, this Tribunal passed the following order on 02.03.2020:-

“After perusing the impugned order, we find that based on the decision of the ‘Committee of Creditors’ and having regard to the fact that the ‘Corporate Insolvency Resolution Period’ has expired, the Adjudicating Authority accepted the application of the ‘Resolution Professional’ and directed that the ‘Corporate Debtor’ be sent for ‘Liquidation’. Learned counsel for the Appellant submits that the order is not sustainable in view of the order passed by this Appellate Tribunal on 20th September, 2019 in ‘Edelweiss Asset Reconstruction Company Limited vs. Sachet Infrastructure Pvt. Ltd. - ‘Company Appeal (AT) (Insolvency) No. 377 of 2019 & other connected appeals. The Appellant may satisfy us with regard to his locus standi to assail the decision of ‘Committee of Creditors’ being open to challenge. List the appeal on 24th March, 2020.”

11.

Thereafter, on 26.08.2020 liquidation proceedings were stayed. During the pendency of this appeal, which was filed, impleading Sunil Kumar Gupta as Liquidator of the Corporate Debtor as Respondent No. 1, Adel Landmarks Ltd. through its RP as Respondent No. 2, Vikram Kumar, RP as Respondent No. 3, Digamber Buildcon Pvt. Ltd. through its RP as Respondent No. 4, Rational Buildcon Pvt. Ltd. through its RP as Respondent No. 5, Golden Glow Estates Pvt.Ltd. through its RP as Respondent No. 6, Mansarovar Heritage Inn through its RP as Respondent No. 7, Pawandoot Estates Pvt. Ltd. through its RP as Respondent No. 8 and Angad Infrastructure Pvt. Ltd. through its RP as Respondent No. 9 were also impleaded as party. However, the Appellant suffered a statement on 16.09.2022 that he would press this appeal only against the Respondent No. 1 to 3 and an application filed vide diary no. 38660 dated 22.08.2022 was allowed with the following order:-

“Counsel for the Appellant has filed an application bearing diary no. 38660 dated 22.08.2022 by which the Appellant has sought to press this appeal only against Respondent No. 1 to 3 and deleting the rest of the Respondents i.e. 4 to 9. Counsel for the Appellant has submitted that no relief is being pressed against Respondent No. 4-9 and prayers made in the present appeal is confined only to Respondent No. 1 to 3. Counsel for Respondents No. 4 to 9 has not raised any objection about their deletion from the array of Respondents. The application is, thus, allowed. The registry is directed to assign a number of this application.”

12.

On the same day, in I.A. No. 1925 of 2022, notice was issued. The Order passed is as under:-

“This application is filed by Art Construction Pvt. Ltd. invoking Rule 11 of NCLAT Rules, 2016. Notice in the Application. Counsel for the Appellant has submitted that he has no objection if the application is allowed as prayed. However, Counsel for Respondent No. 1 and 2 have submitted that they would to like to file their reply to the application. Counsel for the Applicant is directed to provide a complete set of application to both Respondent No. 1 and 2 within two days. Reply to application, if any, be filed by the non-applicants/Respondent No. 1 and 2 on or before 30th September, 2022. List again on 12th October, 2022.”

13.

Thus, the present appeal is against Respondent No. 1 and 3 and there is an intervener ‘Art Construction Pvt. Ltd. and consequent upon the deletion of Respondent No. 4 to 9 from the array of the Respondent, the Appellant has also filed the amended memo of parties.

14.

Although, the Appellant has filed this appeal, but during the course of hearing, Counsel for the Appellant has restricted his prayer to prayer A and B regarding setting aside of the order of liquidation in view of the decision in CA (AT) (Ins) No. 377 of 2019 and stay of execution of the order in the meantime.

15.

Counsel for the Appellant has submitted that the present appeal has been filed by the Appellant who is an allottee of a project being developed by Adel Landmarks/Developer Company at Sector 8 Palwal, namely, Era Green World and the Appellant seeks for consolidation of the CoC of the Corporate Debtor alongwith the Parent Company and subsidiary/landowning companies and an order directing Group Insolvency of all the landowning subsidiary companies and mortgagor companies of Adel Landmarks and in this regard reliance has been primarily placed on an order passed by this Tribunal in the case of Edelweiss Asset Reconstruction Company Ltd. Vs. Sachet Infrastructure Pvt. Ltd., CA (AT) (Ins) No. 377 of 2019 and also a decision of this Tribunal in the case of Mrs. Mamatha Vs. AMB Infrabuild Pvt. Ltd. & Ors., CA (AT) (Ins) No. 155 of 2018 decided on 30.11.2018.

16.

On the other hand, Counsel appearing on behalf of the R2(RP) has submitted that vide an order dated 05.12.2018 passed in C.P. (IB) No. 1083(PB) of 2018 on an application filed under Section 7 of the Code by Edelweiss Asset Reconstruction Company Limited (EARC), the Adjudicating Authority initiated CIRP in respect of Adel Landmarks Limited and Mr. Udayraj Patwardhan was appointed as IRP who was later on confirmed as RP of Adel.

17.

It is further submitted that after the expression of interest (EOI) was floated by the RP of Adel, a resolution plan was received from one Prospective Resolution Applicant (PRA), namely, Art Construction Pvt. Ltd. dated 18.07.2020 in respect of Adel. The said resolution plan and modification submitted thereto read with addendum and clarification submitted and reply to the queries of the CoC, after prolonged deliberations with the CoCs of Adel, has been put for e-voting by the CoC and has been approved with 82.6605% votes on closure of e-voting on 06.12.2022 whereas Era has been ordered to undergo liquidation vide order dated 03.12.2019 passed by the Adjudicating Authority in CP No. (IB)489 (PB) of 2017and the said liquidation order has been passed as an independent entity without any linkages with regard to the insolvency proceedings of Adel or other group companies.

18.

Counsel for Respondent No. 2 has questioned the locus standi of the Appellant herein on the ground that he is not an aggrieved party to challenge the order of liquidation and thus could not maintain the appeal under Section 61 of the Code. It is contended that the Appellant is an allottee in a project namely ‘Adel Divine Court High Rise’ situated at Sector 76, Faridabad which is being developed by Adel. The Appellant has also filed his claim for an amount of Rs. 21,02,616.71/- with the RP of Adel, which has been admitted for Rs. 13,25,839.64/-. The claim was verified and collated by the RP and has not been challenged by the Appellant and has thus attained finality. It is further submitted that the Appellant is not a stakeholder of Era and is not an aggrieved person from the order of liquidation passed in respect of Era.

19.

It is further argued by the RP/R2 that the Appellant has though allegedly representing the group of allottees but he did not attach any list of group of allottees nor any kind of authorisation letter by the alleged group of allottees has been placed on record. It is argued that sample builder buyer agreement dated 16.05.2012 is stated to be have been entered into between one of the allottees Mr. Satish Tayal and Era Landmarks Limited pertaining to allotment by Adel in the project ‘Adel Divine Court’. It is argued that the Appellant is a Financial Creditor in class of Adel and a member of the CoC of Adel and not Era.

20.

Counsel for Respondent No. 2 has also submitted that the Appellate Tribunal, vide its order dated 20.09.2019 passed in CA (AT) (Ins) No. 377-385 of 2019, directed procedural consolidation of the CIRP of Adel with the following group/subsidiary companies, appointed Mr. Udayraj Patwardhan as the common Resolution Professional and thereafter vide its order dated 01.11.2019 directed initiation of the CIRP and appointment of Common Resolution Professional of the subsidiaries of Adel (i) Sachet Infrastructure Pvt. Ltd. (ii) Superlative Infrastructure Pvt. Ltd. (iii) Magad Realtors Pvt. Ltd.

(iv)

Mehak Realtech Pvt. Ltd. (v) Sameeksha Estate Pvt. Ltd.. It is also submitted that the Appellate Tribunal directed the Adjudicating Authority to pass orders, if collaboration agreements are entered into between Adel and other four subsidiary/group companies, pursuant to which the Adjudicating Authority vide its order dated 11.02.2020 directed initiation of CIRP and appointed common Resolution Professional of subsidiaries of Adel (i) Bhisham Infrastructure Pvt. Ltd. (ii) Manogayan Estate Pvt. Ltd. (iii) Superlative Infrastructure Pvt. Ltd. but the Appellate Tribunal while passing the said order did not deem it appropriate to pass any directions in respect of consolidation of the CIRPs of Era or Hi Point with Adel but ordered for procedural consolidation of the CIRP of Adel with the aforesaid eight subsidiary/group companies with common RP.

21.

It is further submitted that on the direction of the Appellate Tribunal and the Adjudicating Authority in respect of the consolidated companies, the RP issued EOI separately afresh for all the eight subsidiary companies with Adel and the resolution plan was received from one PRA, namely, Art Construction Pvt. Ltd. on 18.07.2020 in respect of Adel only. No resolution plan came to be received in respect of other eight subsidiary/group companies. In terms of the resolution plan proposed and submitted by Art Construction Pvt. Ltd. in CIRP of Adel and envisaged withdrawal of the CIRP of the above eight subsidiaries of Adel, namely, (i) Sachet Infrastructure Pvt. Ltd. (ii) Magad Realtors Pvt. Ltd. (iii) Mehak Realtors Pvt. Ltd. (iv) Sameeksha Estate Pvt. Ltd. (v) Jamvant Estates Pvt. Ltd. (vi) Bhisham Infrastructure Pvt. Ltd. (vii) Manogayan Estates Pvt. Ltd. (viii) Superlative Infrastructure Pvt. Ltd. and also other subsidiary i.e. (ix) Mansarover Heritage Inn Pvt. Ltd. ACPL submitted settlement proposal to EARC for withdrawal of CIRP of the aforesaid eight subsidiaries excluding Golden Glow under Section 12A of the Code. It is further submitted that resolution plan submitted by the ACPL put to e-voting by the CoC of Adel has been approved by the CoC on 06.12.2022. It is therefore submitted that Era as well as Hi Point are undergoing separate and independent liquidation proceedings and is not interdependent with Adel or any of its subsidiaries. In the end, it is argued that even otherwise the Code nowhere defines ‘consolidation’ of the CIRP of group insolvency nor provides any framework for it. Therefore, in the absence of any statutory framework for consolidation of CIRP, the prayer sought to be made by the Appellant is completely misconceived and beyond the purview of the Code.

22.

Counsel for the Intervenor has submitted that the project Era Greenworld of Parent Company located in Palwal at Sectors 8 & 9 is owned by multiple landowning companies i.e. Mehak Realteach Pvt. Ltd., Sachet Infrastructure Pvt. Ltd., Sameeksha Estate Pvt. Ltd., Magad Realtor Pvt. Ltd., Digambar Buildcon Pvt. Ltd. and Jamvant Estates Pvt. Ltd. (collectively referred to as subsidiary landowning companies). It is submitted that CIRP of the parent company and the subsidiary companies, namely, Sachet Infrastructure Pvt. Ltd., Magad Realtors Pvt. Ltd., Mehak Realtors Pvt. Ltd., Sameeksha Estate Pvt. Ltd., Jamvant Estates Pvt. Ltd., Bhisham Infrastructure Pvt. Ltd., Manogayan Estates Pvt. Ltd. and Superlative Infrastructure Pvt. Ltd. were consolidated. It is also submitted that the Intervenor/sole Resolution Applicant of the parent company provided resolutions vide 12A withdrawals for the landowning subsidiary companies which was duly allowed by the Adjudicating Authority. It is also submitted that the Successful Resolution of the Parent Company is only possible if the Corporate Debtor is resolved alongwith the subsidiary landowning companies. The Intervenor has thus argued that the Liquidator be directed to convene a CoC for consideration of the resolution plan for the Corporate Debtor which in turn will ultimately benefit all the stakeholders of the Corporate Debtor, the Parent Company and all the homebuyers involved in the project.

23.

We have heard Counsel for the parties and perused the record.

24.

The first question which has been raised by Respondent No. 2 is about the locus standi of the Appellant to maintain this appeal as an aggrieved person.

25.

There is no doubt that Section 61 of the Code provides for a right of appeal to any person who is aggrieved by an order of the Adjudicating Authority, therefore, the grievance of the person, who intends to file an appeal against the order of the Adjudicating Authority, is a sine qua non.

26.

The Appellant has filed this appeal and averred in para 7.2 that “Appellant is representing a group of allottees who were allotted units in the projects being developed by Adel Landmarks, namely, Era Green World. He has attached builder buyer agreement as annexure A2 which pertains to one Satish Tayal which is in respect of the project ‘Era Divine Court’, Sector 5 Palwal whereas the project in question in the present case is ‘Era Green World’, Sector 8 Palwal. There is no list of allottees attached with the memo of appeal or any kind of authorisation letter by the allottees in his favour. In para 7.14 of the memo of appeal, the Appellant has made a reference to the authorised representative as Mr. Inder Paul Singh Oberoi who was appointed by the CoC and confirmed by the Adjudicating Authority on 07.01.2019. Even otherwise, the Appellant is stated to be an allottee in a project, namely, ‘Adel Divine Court High Rise’ situated at Sector 76, Faridabad which is being developed by Adel. The Appellant has already filed his claim of Rs. 21,02,616.71/- with the RP of Adel which has been admitted for a sum of Rs. 13,25,839.64/-. The claim, as verified and collated by the RP, has not been challenged by the Appellant and has thus attained finality. Therefore, the Appellant is not a stakeholder of Era rather he is the Financial Creditor in class of Adel and is a member of the CoC of Adel and not Era. In such circumstances, the impugned order of liquidation having been passed in the matter of Era Housing & Developers Pvt. Ltd. is not a matter of concern of the Appellant and as such he is not a peson who is aggrieved of the order dated 03.12.2019.

27.

It is needless to mention that the appeal is a statutory right to remedy an injury caused by the impugned order, therefore, the legislature has categorically used the term ‘any aggrieved person’ and not simply ‘any person’. The very fact that the Appellant has nothing to do with the order of liquidation passed in respect of the Respondent No. 1 ‘Era Housing and Developers Pvt. Ltd.’ and he is not an allottee of Era rather he is an allottee of Adel in which he has already put up his claim as verified by the RP of Adel, therefore, in our considered opinion the present appeal is directly hit by lack of locus standi on the part of the Appellant.

28.

In such circumstances, it would be a futile exercise to go into other aspects of the matter which have been raised by the Appellant in the present appeal. Consequently, the present appeal is hereby dismissed on the ground that the Appellant does not have the locus standi to maintain the appeal because the Appellant do not fall within the definition of ‘any aggrieved person’. The appeal is thus found to be not maintainable and the same is hereby dismissed. No costs.