Tribunals and CommissionsDivision Bench(2019) 07 NCLT CK 0787

Rajesh Jhunjhunwala RP for Siddharth Tubes Ltd. vs Madhya Pradesh State Industrial Development Corporation Ltd. & Ors.

National Company Law Tribunal · Decided on 24 July 2019

HON’BLE JUDGES
Harihar Prakash Chaturvedi, Member Judicial · Manorama Kumari, Member Judicial
CASE NUMBER
IA 431 /2019 in C.P. (I.B) No. 67/NCLT/AHM/2018

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 233 words

ORDER

The RP is represented through learned counsel.

The instant IA 431/2019 is filed under section 12 of the IB Code for extension of time for the further period of 90 days beyond 180 days for the completion of the CIRP as provided under section 12 of the Code.

It is informed that statutory period of 180 days has been expired on 23.07.2019 and the instant application was filed on 22.07.2019.

Heard the arguments of learned Counsel for the Applicant.

On a perusal of the record, it is found that COC in its Meeting dated 19.07.2019 has passed a resolution seeking extension of time for further period of 90 days and has duly authorised the RP for the same. The above stated fact is reflected in the Minutes of the Meeting held on 19.07.2019 at Agenda Item No. 7, wherein, the COC has decided for extension of CIRP period for further 90 days beyond 180 days. The COC has voted in favour of the extension of time by 100% voting.

Considering the aforesaid reasons as mentioned in the application we being Adjudicating Authority are of the view that sufficient reasons are shown for seeking extension of the period of the CIRP in respect of Corporate Debtor. Hence, prayer for extension of the CIRP period of 90 days beyond 180 days is hereby granted.

Accordingly, the IA 431/2019 is allowed and stands disposed of.