Tribunals and CommissionsDivision Bench(2022) 07 RERA CK 0790

Raghavi Abhilesh Bembey & Ors. vs M/s C.J. Infrastructure Pvt. Ltd. & Ors.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 26 July 2022

CASE NUMBER
16/2019, 17/2019, 24/2019, 38/2019
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

20 paragraphs · 545 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Dr. Abhilesh Kumar Bembey, Complainant appeared on behalf of the Complainant in case no. 16/2019, Mrs. Shyamala Abhilesh Bembey, Complainant appeared in person in case no. 17/2019, Adv. Riya Seth appeared on behalf of the Complainant in cases no. 24/2019 and 38/2019. Shri Shiv Ambardar, AR also appeared in case no. 38/2019.

2.

Adv. Praveen Kapoor appeared on behalf of the Respondents No. 1 'CJ Infrastructure Pvt. Ltd' and Adv. Ajeet Kumar appeared on behalf of Respondent No. 4, Shri Jagdish Dhingra

3.

None present on behalf of the DDA.

4.

The Authority recalls that after hearing the arguments on 01.04.2022 the case was reserved for orders. Thereafter on perusal of records it was seen that the Complainants had made following as Respondents, however, the notice was issued only to 1st Respondent M/s C J Infrastructure Pvt. Ltd.

i.

M/s C J Infrastructure Pvt. Ltd.

ii.

M/s Bhandari Infrastructure

iii.

Shri Jaideep Bhandari

iv.

Shri Jagdish Dhingra

v.

Shri Ramesh Wadhwa

vi.

Shri Ajay Bhandari

5.

The perusal has further shown that though, the Complainants had made all payments to M/s CJ Infrastructure Pvt. Ltd., the receipts were issued on behalf of the Bhandari Infrastructure listed as second Respondent by the Complainants.

6.

Since, M/s Bhandari Infrastructure and others were not given notices by the Authority before reserving the case for orders, in the interest of natural justice, the Authority opined that fresh notice be issued to all Respondents and case be listed once again for hearing.

7.

At the time of hearing today, the Complainants once again clarified and reconfirmed that they made all payments to M/s C J Infrastructure Pvt. Ltd. and not to any other entity.

8.

Ld. Counsel for the Respondents no. 1 submitted that M/s Bhandari Infrastructure is the group under which M/s C J Infrastructure Pvt. Ltd. is a company registered as per Companies Act of 2013.

9.

He further confirmed that the Complainants had made payments to M/s C J Infrastructure Pvt. Ltd. and M/s Bhandari Infrastructure had role in the project. He further submitted that the building plans for the subject project were sanctioned in the name of M/s C J Infrastructure Pvt. Ltd. and they only gave/will give possession of booked space to the allottees by way of Registered deed.

10.

Ld. Counsel for Respondent No-4 stated that his client had no role in construction of the project and he dealt with both the parties in his capacity as Real Estate Agent.

11.

In view of the above, we decide that in order to adjudicate the matter, there is no need to hear Respondents M/s Bhandari Infrastructure, Shri Jaideep Bhandari, Mr. Jagdish Dhingra and Shri Ramesh Wadhwa except M/s CJ Infrastructure Pvt. Ltd. and DDA.

12.

The Authority also notes that DDA was impleaded as a party in the case on the request of Complainants and they have already made final written submissions. We feel there is no need to examine them further.

13.

Since, we have heard all parties at length over last few months and as all parties have concluded their arguments and as we are of opinion that deposition of all other Respondents except Respondents M/s C J Infrastructure Pvt. Ltd. is not necessary for adjudication of this case.

14.

We reserve the case for final orders.