High CourtsDivision Bench(2024) 03 TP CK 0024

Priyanka Chowdhury vs Subham Banik

Tripura High Court · Decided on 28 March 2024

HON’BLE JUDGES
Arindam Lodh, J · S.D. Purkayastha, J
RESULT
Allowed
CASE NUMBER
First Appea 07 Of 2023 & Interlocutory Application No. 1 Of 2023 In First Appeal No. 7 Of 2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

6 paragraphs · 176 words

Heard Mr. S. Lodh, learned counsel appearing for the applicant. Also heard Mr. Pujan Biswas and Ms. S. Debbarma, learned counsel appearing for the respondent.

This is an application filed under Section 5 of Limitation Act for condoning the delay of 57 days in preferring the connected appeal against the judgment and order dated 14.07.2023 passed by the Ld. Judge, Family Court, West Tripura, Agartala, in Civil Misc. 81 of 2022 arising out of T.S.(Div) No.211 of 2022.

Mr. Lodh, learned counsel has submitted that the delay caused in preferring the appeal was unintentional and the reasons for the same have been explained in the instant application.

Mr. Biswas, learned counsel has not raised any objection to the prayer for condonation of delay.

Considering the above submissions of the learned counsel appearing for the parties and after going through the reasons for causing delay, we deem it fit to allow the instant application.