Tribunals and CommissionsFull Bench(2022) 09 NGT CK 0005

Pramod vs State of Uttar Pradesh & Ors

National Green Tribunal · Decided on 6 September 2022

HON’BLE JUDGES
Adarsh Kumar Goel, CP · Sudhir Agarwal, JM · Prof. A. Senthil Vel, EM
RESULT
Dismissed
CASE NUMBER
Review Application No. 22 Of 2022 In Appeal No. 23 Of 2021 (I.A. No. 193 Of 2022)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

56 paragraphs · 1,900 words
1.

This application has been filed by the Project Proponent (PP), private respondent in the Appeal No. 23/2021 for review of order of this Tribunal dated 11.03.2022.

2.

By the said order, the Tribunal allowed the appeal against EC dated 17.09.2021 in favour of the PP on the ground that no requisite replenishment study was conducted before grant of EC. The Tribunal considered the response of the PP and SEIAA, UP on the subject. Even though the appellant had raised several grounds to challenge the EC, the appeal was allowed only on the ground of absence of replenishment study which was mandatory.

3.

Other grounds raised by the appellant are reflected in para 2 of the order which include validity of cluster certificate dated 16.09.2020. Pointwise response is set out in tabular form in the order as follows:

“5. The stand of the PP in a tabular form is as follows:-

“

Observations/            response sought     in     order     dated 21.10.2021

Response       of       Answering Respondent  as  it  was  on  the date    of    Hon’ble    Tribunal’s observations

1.

Chapter   5   of   the   Sand Mining     Guidelines,     2020 issued by MoEF&CC mandate that  River  bed  sand  mining be    permitted    only    after conducting  a  replenishment study  as  per  the  procedure prescribed     therein.         No replenishment     study     has been    conducted    on    River Yamuna         in         District Saharanpur till date.

1.

The  EC  has  been  issued  in favour  of  respondent  only  for 1 year with Specific Condition

–cluster   1   thereof   read   as under:-      “DSR      lacks      in replenishment     study     thus SEIAA decided to grant EC for a  period  of  one  year  only.  PP should  submit  replenishment study,  duly  approved  by  the competent      authority,      for extension  of  EC  beyond  one year”.

2.Further,          SEIAA          in compliance to Chief Secretary letter   dated   09.09.2021   in compliance    to    NGT    order dated     26.02.2021     in     OA 360/2015  has  already  passed resolution     that     “due     to uncertainty  and  to  avoid  any critical   condition   SEIAA   is granting    EC   only   for   one year.”

3.

Further, State of UP in M.A. No.    36/2021    86    M.A.    No. 37/2021  has  already  updated NGT  that  "study  is  underway and  will  be  completed  soon and  mining  will  be  allowed consistent    therewith"    copy annexed as Annexure G.

4.

The  project  proponent  has conducted          replenishment

study  as  per  the  T&C  of  EC and    submitted    to    SEIAA, District  Magistrate  and  DGM which is pending review.

2.

That      previously      also Environmental   Clearance   was issued  in  respect  of  the  same mining  site  at  village  Nuniyari District,      Saharanpur.      That environmental    clearance    was challenged  before  this  Hon’ble Tribunal       in       Appeal       No. 258/2018 (Sunil Kumar v. State of  UP  &  Ors.)  where  vide  order dated  29.03.2019,  the  Tribunal recorded  the  submission  of  the State   that  it  would  recall   the Environmental   clearance.   This aspect    has    been    completely ignored by UP SEIAA.

The  allegation  is  baseless  and not-related to Respondent.

1.

The  recalled  EC  belonged to   previous   lease   holder.   The recalled     EC     has     not     been transferred. The lease in favour of previous  lease  holder  was  also cancelled by DM Saharanpur.

2.

Thereafter,      lease      was published  afresh for e-auction  on by        District        Administration Saharanpur and Respondent was found   capable   fulfilling   all   the requirements   hence,   eventually granted   LoI   being   the   highest bidder.

3.

The       Respondent       has secured  fresh  EC  by  SEIAA,  UP as   per   the   provisions   of   EIA Notification-2006 (as amended).

3.

Cluster     Certificate     dt. 16.09.2020 is false since:

a.  It  says  that  no  lot  exists within 500 meters when in fact Lot  No.  37,  Village  Naniyari  is adjacent.

b. Certificate falsely states that no EC had earlier been issued for  this  Lot  when  in  fact  EC had earlier been issued.

1.

The  allegation   is  outrightly baseless  made  without  regard to  actual  site  position.  Further, appellant  herein  is  no  expert  in the  field  and  there  is  plausible field   and   there   is   plausible whatsoever      to      prefer      his imagination     based     on     his delusional thought process.

2.

It  is   innately   laughable   to even      imagine      that      maps prepared by appellant (as stated in para ‘E’ at pg. 15) should be relied   or   preferred   instead   of official     maps     prepared     by Government.

3.

The   cluster   certificate   has been  issued  as  per  the  format approved  by  SEIAA,  UP.  Which clearly  states  that  there  is  no lease  approved  in  terms  of  Lol and  neither  is  under  operation with   500   meter   periphery   of lease belonging to Respondent.

4.

The   Lot   No.   37   is   non- operation      and      is      under possession of State Government

which has not been allocated to

any lease holder.

5.

The     project     has     been appraised  by  SEIAA,  UP  under B1 Category.

6.

The  definition  of  cluster  is amply  clear  in  EIA  Notification- 2006         (and         subsequent amendments).

4.

No  permission  obtained  for extraction of ground water. The EC   itself   states   that   15,782 litres  of  water/day  is  required for  mining  operations.  (refer  to Sr. No. 27 of the EC)

The    allegation    is    completely baseless and mis-leading.

1.

The   Respondent   has   not commenced mining operation as on   the   date   of   filing   appeal. However,   certain   clarifications have    been    issued    by    the concerned authorities, thereafter and  those  would be  adhered  to fully.

2.

The  Respondent  secured  EC on   17.09.2021   and   the   lease deed has been duly executed in favour      of      the      answering respondent.

3.

The  Respondent  has  already obtained     all     the     requisite permissions (CTE & CTO)  under Air  &  Water  Acts  and  so  also assent of Central Ground Water Authority  (CGWA)  and  did  not start    mining.    The    necessary permission   are   annexed   with the instant reply.

4.

The     Respondent    further submits that since the project is under    the    notified    area    of ground  Water  extraction,  it  shall explore   alternate   valid   source   of water    demand    through    hiring tankers.      which      would      also generate     employment    of     local villagers     in     consultation     with concerned Gram Pradhan.

5.

No consent to operate obtained from  the  Uttar  Pradesh  Pollution Control Board

The    answering    respondent   has already   secured   all   the   required permissions    from    UPPCB    and CGWA   (Annexure-E,D   &   F)   and despite  that  it  did  not  commenced mining operation.

6.

River  Yamuna  flows  right through   the   centre   of   the mining  area.  It  is  submitted that while mining is permitted on the river bed but no mining area can  contain a  portion  of the River itself.

1.

It  is  submitted  that  the course   (drainage   pattern)   of river Yamuna has a fluctuating tendency   in   Behat   Tehsil   of Saharanpur due to its peculiar geo-morphological     conditions. the  river  keeps  shifting  season by  season  and  is  spread  into small,   big   channels   while   it flows.

2.

The  dry  river  bed  itself becomes  part  of  entire  action water    channel    in    monsoon season     when     replenishment occurs.

3.

The mining shall be done in   dry   river   bed   as   per   the provisions  of  approved  Mining Plan,    SSMG-2016    Guidelines, EMSM-2020     Guidelines     and General Condition Clause No. 6 & Specific Condition Clause No. 55.

7.

No due diligence conducted by U.P. SEIAA on the background of  project  proponent.  Mr.  Rajeev Bhatia,   Partner   of   the   Project proponent, is a habitual defaulter and    his    earlier    sand    mining operations    at    Village    Rehna, District    Saharanpur    conducted through his  brother were stopped pursuant  to  order  dt.  06.04.2021 passed  by  this  Hon’ble  Tribunal in O.A. No. 09/2020

1.

The  allegation  is  malicious, made  out  of  spite,  fabricated  and baseless and is  non-environmental subject.   Further,   apart   from   the infantile  nature  of  allegation  and deduction sought by appellant, it is trite  that  no  person  can  be  held responsible   for   an   action   of   his family member.

2.

Moreover,     the     character certificates   of   Respondents   were duly    scrutinized    and    validated during  evaluation   of   e-tender  by district administration.

4.

The Review Applicant filed an Appeal before the Hon’ble Supreme Court against the order of this Tribunal dated 11.03.2022 being Civil Appeal No. 4024 of 2022, M/s. Shanti Enterprises vs. State of Uttar Pradesh & Ors., which was disposed of on 11.07.2022 granting liberty to the Review Applicant to file a Review Application. As the order shows, contentions of the PP were that replenishment study had already been undertaken and that the Tribunal had extended time for such study in another case in O.A. No. 140 of 2021, Raj Kumar v. State of UP, by order dated 06.05.2022.

5.

We have heard learned Counsel for the Review Applicant as well as the Original Appellant.

6.

Only contention of the PP is that it got the replenishment study conducted on 01.12.2021 which has been filed with the SEIAA. Hon’ble Supreme Court has allowed mining activity even in absence of replenishment study by order of dated 10.11.2021 in Civil Appeal No. 3661-3662 of 2020, State of Bihar vs. Pawan Kumar and Others and order dated 11.11.2021 in SLP (C) No. 10587 of 2019, Bajri Lease LoI Holders Welfare Association vs. State of Rajasthan.

7.

As against the above, learned Counsel for the Appellant submitted that no ground for review has been made out. Replenishment study is mandatory as per Sustainable Sand Mining Guidelines, 2020 and orders of Hon’ble Supreme Court make exception in individual cases which does not obviate need for such study. Study got conducted by the appellant has to be duly appraised by the SEIAA which has not been done. Alternatively, the impugned EC is expiring on 17.09.2022 and at this stage mining cannot be allowed in view of lapse of period of EC. Further, other alternative submissions raised in the appeal may be now considered, particularly absence of appraisal as a cluster. The PP produced erroneous certificate that cluster was not involved. Our attention has been drawn to the EC granted by the MoEF&CC in respect of Lot no. 37 on 23.02.2012, giving coordinates for the said lease as follows:-

“Latitude- 30◦10' 59.5" to 30◦11' 19.6" N and Longitude-77◦ 29' 23.4" to 770 29' 26.8" E in topo sheet No. 53F/8.; Lot No. 37; Khasra no. 1/1/1”

8.

Map annexed to the said EC shows that Lot no. 38 which is subject matter of present proceedings was part of Lot no. 37 and formed a cluster with lot no. 38. It was submitted that in view of the said document, the cluster certificate dated 16.09.2020 relied upon by the Project Proponent (Annexure- A10 to the Appeal) cannot be accepted as correct. We find the argument substantiated from the record.

9.

Further, the appellant submitted that the lease area in present case is in river bed itself which is admitted in the response of PP itself at serial no. 6 in the tabular response quoted in the order referred to above.

10.

Considering the rival submissions, we find it difficult to accept the Review Application.

11.

Firstly, the EC is expiring on 17.09.2022. Secondly, the Cluster Certificate which has been relied upon by the PP is not correct in view of EC granted for Lot no. 37 and map annexed thereto showing that Lot no. 38, which is subject matter of the mining lease in question, forms a cluster which would require appraisal as such. Thirdly, the lease area is part of river bed which is not permissible. Even, with regard to the replenishment study, the study has been conducted by the PP itself which has not yet been appraised by SEIAA. Though later order of the Tribunal in another matter same cannot be ground for review on the principle of explanation to Order 47 Rule 1, even if the said plea is to be accepted, the impugned EC being also bad for absence of Environmental Impact Appraisal of Cluster and for lease area being in river bed, the review application cannot be accepted.

The Review Application is accordingly dismissed.

I.A. No. 193/2022 will stand disposed of accordingly.