High CourtsSingle Bench(2026) 11 DEL CK 3848

Nesteasy Facility Private Limited vs Union Of India & Ors.

Delhi High Court · Decided on 19 November 2026

HON’BLE JUDGES
Amit Mahajan, J
RESULT
Dismissed
CASE NUMBER
W.P.(C) 13279/2026 & CM APPL. 61678/2026, CM APPL. 61679/2026, CM APPL. 79099/2026
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

23 paragraphs · 1,311 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

AMIT MAHAJAN, J. (Oral)

1.

By way of the present petition, the petitioner seeks the following prayers:

“I. Issue Writ Petition under Article 226 of the Constitution of India seeking issuance of appropriate writes), including certiorari and mandamus, against the arbitrary and un-notified reopening 1 revival 1 continuation of reverse auction no. GEM/2026/R/712794 after its displayed and concluded closure on 10.082026; for quashing the consequential reverse-auction result dated 13.08.2026; and for restoration of the price-discovery result recorded upon the first closure;

II. direct Respondent Nos. 2 and 4 to forthwith preserve and place before this Hon'ble Court the complete electronic and administrative record of the subject Bid/RA, and records of all communications to the five qualified sellers for re-opening ofRA on 12.08.2026;

III. consequentially direct Respondent No. 2 & 4 to treat the displayed closure dated 10.08.2026 at 18:51 hours, showing the Petitioner as L1 at Rs. 42,68,673.76/- (Rupees Forty-Two Lakh Sixty-Eight Thousand Six Hundred Seventy-Three and Seventy-Six Paisa), as the operative price-discovery result for lawful consideration of award;

IV. pass any other or further order that this Hon'ble Court may deem just and proper in the facts and circumstances of the case.”

2.

Briefly stated, Respondent No. 2 published Bid dated 02.09.2025 for pest and animal control maintenance services for two years at Lady Hardinge Medical College and Smt. Sucheta Kriplani Hospital (Respondent No. 4), with an estimated value of Rs. 1,07,45,132/-. The petitioner submitted its bid on 11.09.2025 and was declared technically qualified along with four other bidders.

3.

On 07.08.2026, Reverse Auction (‘RA’) No. GEM/2026/R/712794 was created, with bidding scheduled from 08.08.2026 to 10.08.2026 and a reference price of Rs. 45,36,546/-.

4.

It is the petitioner’s case that on 10.08.2026, following successive automatic extensions, the auction displayed zero time remaining at 18:51 hours and declared the petitioner as L1 at Rs. 42,68,673.76/-. Thereafter, the same RA was reopened for further bidding on 12.08.2026. The petitioner is stated to have immediately objected to the reopening and lodged a complaint with the GeM Helpdesk (Ticket No. 13472680). The petitioner participated in the reopened auction under protest on 12.08.2026 and 13.08.2026, which again concluded with the petitioner being declared L1, this time at Rs. 29,42,274.12/-.

5.

The petitioner is essentially aggrieved by the reopening of the RA after the portal had displayed its closure and declared the petitioner as L1 at Rs. 42,68,673.76/-. It is contended that the petitioner participated in the subsequent auction only under protest to protect its commercial interests and repeatedly represented that it remained willing to execute the contract at the original L1 price. It is submitted that the reopening was affected without prior notice, any RA-specific order or disclosure of the authority and reasons justifying such action.

6.

The petitioner further contends that the Helpdesk responses referring to an intermittent login-service issue and the Buyer's power to extend an ongoing RA do not explain the reopening of an auction which had already displayed zero time remaining. It is further submitted that the subsequent extension of the RA was arbitrary and the petitioner ought to have been awarded the tender at the original bid of Rs. 42,68,673.76/-.

7.

The learned counsel for Respondent No.2 submits that the extension of the impugned RA was necessitated on account of intermittent issues reported in the login services on 10.08.2026 and 11.08.2026. He submits that in order to ensure that all eligible bidders were afforded a fair and equal opportunity to participate, Respondent No.2, as a prudent administrative measure extended all bids and RAs scheduled to end during the affected period, the results of which had not yet been opened/declared by the buyer, including the impugned RA. He submits that the petitioner after having participated in the extended RA process cannot, at this stage, pray to be awarded the tender at a higher amount.

8.

The petitioner essentially seeks restoration of the original RA result dated 10.08.2026, wherein it was declared L1 at Rs. 42,68,673.76/-.

9.

At the outset, it is pertinent to note that Respondent No.2 being the administrator and facilitator of the procurement process, retains the authority to take necessary measures to ensure the integrity and fairness of the bidding process, including extending or rescheduling impacted bids/RAs in circumstances where technical or systematic issues may have affected the ability of eligible bidders to participate on equal terms.

10.

It has been submitted before this Court by Respondent No. 2 that the impugned RA was extended on account of intermittent disruptions in the login services of the GeM portal on 10.08.2026 and 11.08.2026. It is further explained that, in order to ensure that all eligible bidders were afforded an equal opportunity to participate, all impacted bids and RAs scheduled to end during the affected period, in respect of which the financial results had not yet been declared by the Buyer, were extended. The subject RA was accordingly included in the said category. Respondent No. 2 has also clarified that the expression 'not yet opened' in its communications referred to the declaration of financial results by the Buyer and not the conclusion of the bidding process.

11.

It is pertinent to note that the petitioner, despite having initially objected to the extension, did not refrain from participating in the extended RA. Rather, with knowledge that the RA had been extended, the petitioner actively participated in the subsequent bidding process on 12.08.2026 and 13.08.2026 and made multiple revised offers, ultimately reducing its bid from Rs. 42,68,673.76/- to Rs. 29,42,274.12/-. The petitioner was once again declared L1 upon conclusion of the extended auction.

12.

In these circumstances, the petitioner, having consciously participated in the extended RA and submitted multiple revised offers, cannot be permitted to selectively challenge the very process in which it voluntarily participated, merely because the subsequent bidding resulted in a lower price than its original offer. The petitioner itself chose to quote the revised price at which it was willing to undertake the contract and, having emerged L1 on that basis, cannot now seek to disregard the subsequent price-discovery process and revert to its earlier offer.

13.

The fact that the petitioner had raised an objection or participated under protest does not alter the fact that it actively engaged in the extended auction, submitted revised bids and sought to secure the contract through that process. It is also undisputed that the petitioner did not challenge the extension of the RA at that stage.

14.

It is also pertinent to note that the subject procurement concerns the utilisation of public funds. The reverse auction mechanism is intended to facilitate competitive price discovery and secure the most economical offer for the public authority. In the present case, it is not disputed that the other technically qualified bidders were willing to quote prices lower than the petitioner's original L1 offer of Rs. 42,68,673.76/-, and that multiple bids below the said amount were submitted after the RA was extended. The petitioner itself ultimately reduced its offer to Rs. 29,42,274.12/-. In such circumstances, directing the respondents to restore the original bid result would be contrary to public interest.

15.

Respondent No.2, in their counter affidavit, have clearly explained that the extension of the RA was necessitated on account of certain intermittent technical disruptions in the login services of the GeM portal during the relevant period. It has been specifically stated that the extension was undertaken to ensure that all eligible bidders were afforded an equal and fair opportunity to participate in the price-discovery process. In such circumstances, no mala fide or arbitrariness can be attributed to the respondents in extending the RA, particularly when the decision was taken in the larger interest of the public exchequer.

16.

In view of the above, this Court finds no reason to exercise its extraordinary discretionary jurisdiction under Article 226 of the Constitution of India.

17.

The present petition is accordingly dismissed.

18.

Pending applications also stand disposed of.