High CourtsSingle Bench(2008) 11 J&K CK 0013

Nazir Ahmad Ganai vs State of J&K & Ors.

Jammu And Kashmir High Court · Decided on 5 November 2008 · Citation: (2009) 1 JKJ 87 : (2009) 1 SriLJ 26

HON’BLE JUDGES
Mansoor Ahmad Mir, J
CASE NUMBER
OWP No.591 Of 2008

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

20 paragraphs · 408 words
1.

Petitioner has questioned the Order No.751922 dated 10th of July, 2008 passed by respondent No.2 on the ground that it came to be passed

without jurisdiction and competence.

2.

Respondents have filed reply. It is specifically averred that the order in question came to be passed in compliance and in continuation to the

Government order No.379PW (R&B) of 2008 dated 20.06.2008 passed by respondent No. 1. Further, it is stated that it is the prerogative of the

Government to decide where the office is to be located. The said administrative and executive function cannot be questioned.

3.

It appears that Government in its wisdom issued order No.379PW(R&B) of 2008 dated 20.06.2008 with a view of accelerating the pace of

work and completing the prestigious Narbal Tangmarg Road Project on time in the public interest and ordered that subject project be handed over

to the Project Construction DivisionI, Srinagar by Gulmarg Project Organisation. It is apt to reproduce the said order herein:

With a view of accelerating the pace of work and completing the prestigious Narbal Tangmarg Road Project on time in the public interest, it is

ordered that the Narbal Tangmarg Road Project shall be handed over by the Executive Engineer, Gulmarg Project Organisation to Project

Construction DivisionI, Srinagar alongwith all relevant records, assets & liabilities. The supervision of this project will now be done by the Project

Construction DivisionI, Srinagar and SubDivision No. 1. The Project Construction Division No. 1, Srinagar shall exclusively look after this project

in addition to his own duties at present. The Headquarter of the SubDivision shall be shifted from its present place to Magam Tangmarg till the

completion of the Road Project with immediate effect. By order of Government of Jammu & Kashmir.

4.

In compliance to the said order, Chief Engineer in its wisdom passed the consequential order and fixed the location of the said office. The

petitioner has no right to question administrative action which came to be passed in public interest. Even otherwise petitioner has no right to

question the administrative order(s)/action(s) by the medium of writ petition. The interference of the court is also not warranted. However, it can

interfere if the order is outcome of malafide or came to be passed without jurisdiction and competence.

5.

In view of the above, no case for admission is made out. Accordingly, the writ petition is dismissed along with all connected CMPs. Interim

direction, if any, shall stand vacated.