Judgment
The present appeal has been filed by the Appellant under Section 37 of the Arbitration and Conciliation Act, 19961, directed against the order passed by the learned Arbitral Tribunal under Section 17 of the Act whereby the learned Tribunal has restrained the Appellant from invoking and encashing the Performance Bank Guarantee furnished by the Respondent.
The learned Tribunal has, at the same time, directed the Respondent to keep the Performance Bank Guarantee alive during the pendency of the arbitral proceedings.
The dispute arises out of an EPC (Engineering, Procurement, and Construction) Agreement dated 21.08.2018 executed between the parties for construction and maintenance of a 4-lane NH-56 bypass forming part of the Varanasi Ring Road.
A Provisional Certificate was issued with effect from 21.10.2021 followed by a Completion Certificate with effect from 24.01.2022. Thereafter, recognition of the pavement was introduced.
However, dispute arose after the concerned highway, though provisionally certified on 21.10.2021 and subsequently granted a Completion Certificate with effect from 24.01.2022, allegedly began showing excessive rutting and pavement deterioration from around March 2022.
According to the Appellant, the deterioration was attributable to the deficiency in construction and maintenance undertaken by Respondent.
The controversy intensified when the Appellant issued the Final Notice dated 28.03.2025 seeking approximately Rs.102.49 crores towards the cost of rehabilitation and consequential damages following which the Respondent invoked arbitration challenging its liability for the pavement failure and deficiency.
The Respondent disputed the aforesaid attribution. According to Respondent the deviation was principally on account of excessive overloading.
The Respondent also questioned the adequacy of the contractual specification as, according to him, the same was inadequate, which led to deterioration of the pavement and other deficiencies and sought to attribute the pavement failure to practice beyond its contractual responsibility.
The disputes were referred to arbitration.
During the pendency of the arbitration proceedings, the Appellant sought to move the entire Performance Bank Guarantee furnished by the Respondent under the Agreement.
Being aggrieved, the Respondent approached the learned Tribunal under Section 17 of the Act.
By the impugned order, learned Tribunal restrained the Appellant from invoking any specific Performance Bank Guarantee and directed the Respondent to keep the guarantee alive during the pendency of the arbitral proceedings.
The Appellant has challenged this order of the Arbitral Tribunal whereby they were restrained from invoking the Performance Bank Guarantee.
Learned Counsel appearing for the Appellant submits that the Performance Bank Guarantee is unconditional and irrevocable and is payable on the Appellant’s first written demand, without demur and without requiring proof of any breach under the underlying contract.
Reliance is also being placed on Clauses 7.3.1 and 26.1.4 of the subject agreement which according to the Appellant expressly contemplate appropriation of the Performance security upon default by the contractor not withstanding the pendency of the arbitral proceedings.
It is further submitted that the Respondent failed to undertake the requisite strengthening and overlay works.
Consequently, the Appellant was constrained to engaged a new agency under agreement dated 24.10.2025 to execute the work at the Respondent’s risk and cost.
It is contented that the learned Arbitral Tribunal failed to take into account the continuing expenditure being incurred by the Appellant towards the rehabilitation of the highway as its obligation to ensure safe and uninterrupted traffic.
Per contra, learned counsel for the Respondent, submits that invocation of the PBG was itself unjustified since, under Clause 7.3.1 of the EPCA, occurrence of a “Contractor’s Default” is a prerequisite to invocation, whereas no such default under Clause 23.1 has been established and the contractual conditions permitting risk and cost remedial works under Clauses 14.7 and 17.4 are also stated not to have been satisfied.
It is submitted that the pavement deterioration was not attributable to defective construction or maintenance but arose principally from persistent excessive overloading and allegedly deficient traffic and pavement specifications prescribed under the EPCA.
It is further contended that the Respondent had constructed the Project Highway in accordance with the approved designs, and quality requirements, which is evidenced by the issuance of the Provisional and Completion Certificates.
Learned Counsel for the Respondent also alleges that the strengthening and overlay works proposed by the Appellant materially exceed the pavement thickness prescribed under the original EPCA and therefore amount, in substance, to an upgradation/change of scope rather than rectification of any Contractor’s Default.
It further relies upon the fact that the Appellant initially sought extension of the PBG in September 2025 and thereafter invoked it on 08.10.2025, only shortly before expiry of the Defect Liability Period, contending that the invocation was coercive and inconsistent with the earlier stated basis for seeking extension.
Lastly, it is submitted that no prejudice is caused to the Appellant because the Performance Bank Guarantee has been extended and is required to remain alive during the arbitration, whereas immediate encashment, while the Appellant’s counterclaim on the very same liability remains pending adjudication, would cause irretrievable prejudice and unnecessary multiplicity of proceedings.
I have heard both sides and perused the record.
The only short issue which arises for consideration is whether the Tribunal was justified in restraining encashment of the unconditional and irrevocable Performance Bank Guarantee.
The law on the aspect of encashment of unconditional PBG is settled.
The division bench of this court in Black Gold Resources Private Limitada v. International Coal Ventures Pvt. Ltd.2, recognised the exceptions that are; i) egregious fraud of which the bank has notice and which vitiates the foundation of the guarantee, and (ii) special equities where encashment would result in irretrievable harm or injustice.
In view of this Court, even assuming every allegation made by the Respondent regarding deficient specifications etc. these merely establish a substantive dispute concerning responsibility for pavement failure.
According to this Court, the learned Arbitral Tribunal erred in warranting restraint on invocation of the Performance Bank Guarantee, as the guarantee was unconditional and irrevocable and constituted an independent contract between the issuing bank and the Appellant beneficiary.
The disputes raised by the Respondent regarding the cause of pavement deterioration, are matters for adjudication in the pending arbitration.
Such contractual disputes, even if substantial, do not by themselves furnish a legal basis to interdict an unconditional bank guarantee.
It is undisputed that the nature of the Performance Bank Guarantee was unconditional.
The mere fact that the invocation of the Performance Bank Guarantee may cause a financial burden upon the Respondent or that the Respondent may ultimately succeed in the arbitration, cannot constitute irreparable harm in the legal sense required to justify interdiction of an unconditional bank guarantee.
Indeed, the very purpose of performance security is to secure the beneficiary against the financial consequences of a Contractor’s default. The possibility of financial prejudice to the contractor upon invocation is, therefore, the inherent consequence of the security and cannot, in the absence of circumstances of an exceptional nature, be elevated into a ground for issuing its invocation.
The fact that the Appellant continues to incur expenditure towards rehabilitation of the highway also assumes significance.
While the Court is not required to determine, at this stage, whether the Respondent is ultimately liable for such expenditure, the existence of continuing expenditure and the Appellant’s obligation to maintain the highway do not detract from its Contractor’s right to invoke the Performance Bank Guarantee in accordance with its terms.
Consequently, the impugned order in so far as it restrained the Appellant from invoking any specific Bank Guarantee and is accordingly set aside.
The appeal is allowed in the aforesaid terms.
It is clarified that nothing contained in this order has expression of opinion on the merits of the claims or counter-claims arising out of the underlying agreement.
All such issues are left open for determination by the learned Arbitrator in accordance with law.