Tribunals and CommissionsDivision Bench(2023) 09 RERA CK 3584

Ms. Yogita Gola vs M/s Aerocity Dwarka Multi State CGHS Limited & Ors.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 22 September 2023

RESULT
Disposed Of
CASE NUMBER
137/2021
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

33 paragraphs · 1,724 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

A complaint was filed in FORM ‘M’ on 02.12.2021 by Ms. Yogita Gola (hereinafter referred as “Complainant”) stating that in the year 2019, she approached “M/s Aerocity Dwarka Multi State CGHS Limited” (hereinafter referred as “Respondents or Respondent Society”) for booking of an apartment in their project namely “Lok Awas, New Delhi” promoted by the Respondents in Dwarka, New Delhi.

2.

The Respondents vide Welcome Letter dated 30.03.2019 confirmed membership of the Complainant and welcomed her as new resident of proposed “Lok Awas, New Delhi” project.

3.

The Complainant paid Rs.17,38,600/- (Rupees Seventeen Lakh Thirty Eight Thousand Six Hundred only) to the Respondents for a 2 BHK flat of 1750 sq. ft. area.

4.

The Complainant has submitted that no progress has been made in the project by the Respondents till date, and, therefore, the Complainant want to withdraw from the project and seek refund of amount deposited with the Respondents along with interest.

5.

A preliminary hearing in the case was held on 15.02.2022 and the Authority issued a notice of the complaint on 25.03.2022 to the Respondents by speed post. Thereafter, various notices dated 01.04.2022, 06.04.2022, 23.02.2023, and 09.05.2023 was sent to the Respondents through speed post, dasti & through DCP, EOW for appearing before the Authority.

6.

The matter was heard in several hearings dated 12.04.2022, 05.07.2022, 14.09.2022, 16.11.2022, 14.02.2023, 18.04.2023 and 05.07.2023. Pursuant to service of notice, Advocate Nancy Gunwani appeared on behalf of Respondents on 14.02.2023 and filed Vakalatnama. The Respondents were granted time for filing reply. However, since no reply was filed consequent thereto on 05.07.2023, the defense of the Respondents was struck of and the case was proceeded ex parte due to the repeated absence of the Respondents on various dates. The case was reserved for orders on 05.07.2023.

7.

We have perused the documents available on records and heard the arguments of the Complainant.

Analysis and Consideration:

8.

A perusal of the documents available on record shows that the Respondents have issued six receipts dated 30.03.2019, two dated 29.04.2019, 03.09.2019, 05.10.2019, and 01.01.2020 acknowledging deposits of Rs.51,000/-, Rs.2,11,500/-, Rs.6,00,000/-, Rs.4,00,000/-, Rs.4,25,100/-, and Rs.51,000/-respectively. Hence, payment of Rs.17,38,600/- (Rupees Seventeen Lakh Thirty Eight Thousand Six Hundred only) by the Complainant to the Respondents is a recorded fact.

9.

The RE (RD) Act, 2016 has been enacted to induct professionalism and standardization in the real estate sector, paving way for catalyzing investments and accelerating growth of sector in long run. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. All disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered to determine under the Act. Moreover, section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.

10.

An exhaustive definition of "promoter" is provided in section 2 in the RE (RD) Act 2016. The sub-clause (iv) of clause (zk) of section 2 defines “promoter” as:

“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”

11.

The Respondent Society is a Multi-State Co-operative Society, which advertised membership, made members for their housing project and collected monies from them. The Respondents, thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.

12.

From the receipts, it is seen that the Respondents collected monies for purchase of land, which exercise was part of the housing project. The Welcome Letter issued to the Complainants by the Respondents clearly mention about the project “Lok Awas, New Delhi” promoted by the society. The aim and objective of the Respondent Society, thus, was to raise housing project and the Complainant invested money and became member of the Society to purchase a flat in the said housing project and not for purchase of land only. Therefore, the Respondents cannot shirk away from their obligation cast upon them by RE (RD) Act, 2016.

13.

The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoters and purchasers, enhance transparency of contractual conditions, set minimum standards of accountability and establish a fast-track dispute resolution mechanism.

14.

Under section 18 of RE (RD) Act, 2016, an allottee/house buyer can seek refund of amount invested/deposited with the promoter, along with interest and compensation, if the promoter fails to complete the project by the date specified in Agreement to Sale, and also under section 12 of RE (RD) Act, 2016, if he/she was misled by any information furnished by the promoter, with regard to the project, either through advertisement or otherwise.

15.

In the present complaint, the Complainant intend to withdraw from the project on the ground of delay and is seeking refund of the amount paid to the Respondents in respect of the unit under section 18(1) of the RE (RD) Act, 2016 which reads as under:

“Section 18. Return of amount and compensation:-

18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —

(a). in accordance with the terms of the agreement for sale or, asthe case may be, duly completed by the date specified therein; or

(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,

he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”

16.

As stated earlier, section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:

“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus:-

Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”

17.

The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainant but also misled her at the time of allotment itself by concealing information that they do not have any license or approval from the concerned authorities for construction of project and that no housing project can be developed on agricultural land proposed to be purchased by them. They also did not disclose the risks associated with the project to the society members including the Complainant. The promoters gave part information and cheated the members of public at large.

18.

From the facts produced before us, it is clear that the Respondents have collected deposits from the Complainant for the flat in their proposed project “Lok Awas, New Delhi” after 01.05.2017, the day RE(RD) Act, 2016 came into force, without registering the project with RERA, Delhi under section 3 of RE (RD) Act, 2016. Thus, if the Complainant wishes to withdraw from the project, the Respondents do not have any legal or moral authority to keep money deposited by the Complainant.

19.

The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount deposited alongwith interest to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).

20.

On perusal of the documents on record and submissions made by the Complainant, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016. As such, the Complainant is entitled to get the refund of the amount paid by her alongwith interest at prescribed rate @ 10.75% p.a. (i.e., MCLR plus 2%) as per provisions of sections 18 and 12 of RE (RD) Act, 2016 read with rule 15 of the National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016

21.

In the light of the aforesaid, we direct the Respondents, M/s Aerocity Dwarka Multi State CGHS Limited to refund the entire amount of Rs.17,38,600/-(Rupees Seventeen Lakh Thirty Eight Thousand Six Hundred only), to the Complainant, Ms. Yogita Gola, within 45 days of issuance of this order along with interest at the rate of 10.75% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.

22.

The case is disposed of accordingly.

23.

No order as to costs.