AI Structured Summary
Not yet generated for this judgment
Judgment
Heard Mr. Y.V. Giri, learned senior counsel for the
petitioner and learned counsel appearing on behalf of the State-
respondents.
The grievance of the petitioner, in this application
under Article 227 of the Constitution of India, is that the learned
court below while admitting and issuing the notice to the
respondents in Misc. (Arbitration) Case No. 123 of 2017 filed by
the petitioner under Section 9 of the Arbitration & Conciliation Act,
1996 has failed to consider the relief as prayed for grant of interim
protection to the petitioner and pass appropriate order thereupon.
Learned senior counsel for the petitioner, after
elaborating the facts of the case in detail, has submitted that though
the learned court below has noticed the prayer of the petitioner for
grant of interim relief but has omitted to pass any order in that
regard which clearly amounts to failure to exercise jurisdiction in
the facts and circumstances. It has been contended that the
dispossession of the petitioner from the work site including the
materials thereupon will result in irreparable loss and injury to the
petitioner. It has also been pointed out that no notice for
cancellation of the contract as envisaged by clause 14 of the
contract (Annexure-1) has been received by the petitioner and in
fact the said contract has not been cancelled to the knowledge of the
petitioner but subsequent contract (Annexure-16) has been executed
by the respondents on 11.07.2017.
Learned counsel for the State-respondents while
resisting the assertions made on behalf of the petitioner has
submitted that the petitioner has already been dispossessed from the
work site and there is now no scope for grant of interim relief, as
prayed. It has been emphasized that the notice for cancellation of
the contract has already been issued to the petitioner and the
cancellation order has also been passed. Learned counsel has also
made submissions that the petitioner has not approached this Court
with clean hands and the facts of the case itself show that
substantial delay has already taken place in completion of the
important work in question for the reasons directly attributable to
the conduct of the petitioner.
After considering the submissions on behalf of the
parties and the materials on record, this Court in the facts and
circumstances and in view of the nature of the order being passed
refrains from going into the merits of the rival assertions. However,
from the order dated 10.07.2017 (Annexure-15) passed by the
learned court below in Misc. (Arbitration) Case No. 123 of 2017, it
is manifest that the prayer for grant of interim relief was indeed
made by the petitioner but has not been considered by the learned
court below. There is no reason assigned in the impugned order for
non-consideration of the said relief. It is, therefore, beyond cavil
that the learned court below has failed to exercise the jurisdiction.
Accordingly, this application is disposed of with
direction to the learned court below to pass appropriate order in
accordance with law on the prayer of the petitioner for grant of
interim relief as made before it. Learned counsel for the parties has
submitted that the learned court below be directed to hear the matter
on 26.07.2017, and have jointly submitted that both the parties
would be present on that date for hearing the matter on the issue of
grant of interim relief. Keeping in view the nature of the dispute
between the parties and the facts and circumstances of the case, the
learned court below is directed to take up the Misc. (Arbitration)
Case No. 123 of 2017 (M/s Vasishta Construction Pvt. Ltd. Vs. The
State of Bihar & Others) on 26.07.2017 for considering the prayer
for grant of interim relief as prayed by the petitioner and pass
appropriate order in accordance with law.
Further this Court restrains the respondents from
dispossessing the petitioner, if not already been dispossessed, from
the work site and the materials thereupon till 26.07.2017.
It is clarified that this Court has not gone into the merits
of the case of either of the parties and this order shall not prejudice
the case of the parties either in any manner and the same shall be
decided on its own merits in accordance with law.
Accordingly, this application is disposed of with the
above directions and observations.
