(Per: Hon’ble Manoj Kumar Tiwari, ACJ)
Petitioner’s technical bid, submitted for the work of hill side cutting and muck disposal work (Phase II stage-I) and Construction of wall and cross drainage work (Phase-II stage-2) in Kathgodam to Ranibag section of National Highway No. 87, was declared to be non-responsive for the following reason:-
“As per Sec. IV, Cl 2.2 (C) and Form Tech-13(B) Bidder do not upload Existing Commitments certificate issued by Chartered Accountant.”
Petitioner contends that he submitted certificate issued by Executive Engineer of the Executing Agency and there was no requirement of submitting certificate duly signed by Chartered Accountant. He relies upon Clause 2.2 (C) Section IV of Standard Document for Procurement of Works (Government of Uttarakhand), which is extracted below:-
“C. Bidders who meet the above specified minimum qualifying criteria, will only be qualified, if their available bid capacity is more than the total tender value. The available bid capacity will be calculated as under: Assessed Available Bid Capacity=(A x N x 2 – B) A= Maximum value of civil Engineering works executed in any single year during the last five years (updated to the price level of the financial year 2024-25 @ 5% per year indicated taking into account the completed as well as works in progress). N= Number of years prescribed for completion of the works for which bids are invited (period of 6 months to be taken as (1/2) half-year and more than six months as one year). B= Value, at the current price level, of the existing commitments on on-going works to be completed during the period of completion of the works for which bids are invited).
Note- The Statements showing the value of existing commitments and ongoing works as well as the stipulated period of completion remaining for each of the works listed should be countersigned by the Engineer-in Charge, not below the rank of an Executive Engineer or equivalent.”
Learned counsel for the petitioner further submits that the defect, if any, in petitioner’s technical bid does not affect his bid capacity, therefore, his technical bid could not have been declared to be non-responsive only on the ground that Chartered Accountant’s certificate, in respect of existing commitments, was not uploaded.
Learned State Counsel, however, drew attention of this Court to proforma of Form Tech 13 (Information on Bid Capacity) enclosed at page 56 of the writ petition, which provides that while furnishing information regarding existing commitment or on-going works, a bidder is also required to submit certificate issued by Chartered Accountant with certificate of Executive Engineer. The information, which every bidder is required to submit, is mentioned in tabular form, which is reproduced below:-
“B) Existing Commitments and on-going Works:
Description of Work Place & State Contract No. Name and address of Employer Value of Contract (Rs.) Stipulated period of Completion Value of works remaining to be completed (Rs.) Anticipated date of Completion Note: Certificate issued by Chartered Accountant should be submitted along with work order and Certificate issued by Executive Engineer/Competent Authority on progress of work.”
This Court finds substance in the submission made by learned State Counsel. Since Form Tech 13 prescribes that Chartered Accountant’s certificate regarding existing commitments and on-going works has to be submitted by every bidder and petitioner did not submit Chartered Accountant’s certificate, therefore, rejection of petitioner’s technical bid on the ground that such certificate was not furnished, cannot be faulted.
The expression “existing commitment” used in Standard Bidding Document of Uttarakhand Rural Roads Development Agency was considered by coordinate Bench in WPMB No. 756 of 2026 vide judgment dated 10.01.2026. Relevant extract of the judgment in that writ petition is reproduced below:-
“14.Clause 1.3.3 of Section 3 of SBD makes it clear that a bidder is required to submit information regarding the ‘works for which bids have been submitted’ besides the works which are yet to be completed. This leaves no room for doubt that ever bidder is required to submit information not only regarding the ongoing works, but also for other works wherefor bids have been submitted by the bidder. Merely because there is no column in the table given in Clause 1.3.3 regarding works for which bids have been submitted, will not absolve petitioner from the liability to furnish information regarding other works for which he has submitted bids. Participation by petitioner in bidding process for some other road construction work amounts to ‘commitment’, as once he is declared successful in that tender process and contract is awarded to him, then he cannot back out of his obligation under such contract and failure on his part to execute that work, may make him liable to penal action. Thus, participation by petitioner in some other bidding process with same or other employer creates an ‘existing commitment’ and petitioner was under a duty to furnish information regarding such commitment to enable the employer (respondent no.1) to evaluate his bid capacity. Thus, the contention raised by learned Counsel for petitioner is bereft of merit and the same is, accordingly discarded.”
In the case of Central Coalfields Limited & another vs. SLL-SML (Joint Venture Consortium) & others, reported as (2016) 8 SCC 622 it was held that decision making process of the employer or owner of the project in accepting or rejecting the bid of a project tender should not be interfered with and interference is permissible only if the decision making process is mala fide or intended to favour someone. It was further held that the decision should not be interfered with unless it is so arbitrary or irrational that the court can say that the decision is one which no responsible authority acting reasonably and in accordance with relevant law could have reached.
In the case of Afcons Infrastructure Limited v. Nagpur Metro Rail Corporation Ltd., reported in (2016) 16 SCC 818, has held as under:-
“13.In other words, a mere disagreement with the decision-making process or the decision of the administrative authority is no reason for a constitutional court to interfere. The threshold of mala fides, intention to favour someone or arbitrariness, irrationality or perversity must be met before the constitutional court interferes with the decision-making process or the decision.”
In Afcons Infrastructure Limited (supra), it was further held that the owner or employer of a project, having authored the tender documents, is the best person to understand and appreciate its requirements and interpret its documents. Constitutional Courts must defer to his understanding and appreciation of the tender documents, unless there is mala fide or perversity in the understanding or appreciation or in the application of the terms of the tender conditions. It is possible that the owner or employer of a project may give an interpretation to the tender documents, which is not acceptable to the Constitutional Courts, but that by itself is not a reason for interfering with the interpretation given.
In Raunaq International Ltd vs I.V.R. Construction Ltd. And Ors reported as (1999) 1 SCC 492, Hon’ble Supreme Court held as under:-
“11.When a writ petition is filed in the High Court challenging the award of a contract by a public authority or the State, the court must be satisfied that there is some element of public interest involved in entertaining such a petition. If, for example, the dispute is purely between two tenderers, the court must be very careful to see if there is any element of public interest involved in the litigation. A mere difference in the prices offered by the two tenderers may or may not be decisive in deciding whether any public interest is involved in intervening in such a commercial transaction. It is important to bear in mind that by court intervention, the proposed project may be considerably delayed thus escalating the cost far more than any saving which the court would ultimately effect in public money by deciding the dispute in favour of one tenderer or the other tenderer. Therefore, unless the court is satisfied that there is a substantial amount of public interest, or the transaction is entered into mala fide, the court should not intervene under Article 226 in disputes between two rival tenderers.
12.…..
13.Hence before entertaining a writ petition and passing any interim orders in such petitions, the court must carefully weigh conflicting public interests. Only when it comes to a conclusion that there is an overwhelming public interest in entertaining the petition, the court should intervene.
14.Where there is an allegation of mala fides or an allegation that the contract has been entered into for collateral purposes and the court is satisfied on the material before it that the allegation needs further examination, the court would be entitled to entertain the petition. But even here, the court must weigh the consequences in balance before granting interim orders.
15.Where the decision-making process has been structured and the tender conditions set out the requirements, the court is entitled to examine whether these requirements have been considered. However, if any relaxation is granted for bona fide reasons, the tender conditions permit such relaxation and the decision is arrived at for legitimate reasons after a fair consideration of all offers, the court should hesitate to intervene.”
In the case of Air India Ltd. v. Cochin International Airport Ltd. and others, reported as (2000) 2 SCC 617, Hon’ble Supreme Court has held as under:-
“7.The law relating to award of a contract by the State, its corporations and bodies acting as instrumentalities and agencies of the Government has been settled by the decision of this Court in Ramana Dayaram Shetty v. International Airport Authority of India [(1979) 3 SCC 489] , Fertilizer Corpn. Kamgar Union (Regd.) v. Union of India [(1981) 1 SCC 568] , CCE v. Dunlop India Ltd. [(1985) 1 SCC 260 : 1985 SCC (Tax) 75] , Tata Cellular v. Union of India [(1994) 6 SCC 651] , Ramniklal N. Bhutta v. State of Maharashtra [(1997) 1 SCC 134] and Raunaq International Ltd. v. I.V.R. Construction Ltd. [(1999) 1 SCC 492] The award of a contract, whether it is by a private party or by a public body or the State, is essentially a commercial transaction. In arriving at a commercial decision considerations which are paramount are commercial considerations. The State can choose its own method to arrive at a decision. It can fix its own terms of invitation to tender and that is not open to judicial scrutiny. It can enter into negotiations before finally deciding to accept one of the offers made to it. Price need not always be the sole criterion for awarding a contract. It is free to grant any relaxation, for bona fide reasons, if the tender conditions permit such a relaxation. It may not accept the offer even though it happens to be the highest or the lowest. But the State, its corporations, instrumentalities and agencies are bound to adhere to the norms, standards and procedures laid down by them and cannot depart from them arbitrarily. Though that decision is not amenable to judicial review, the court can examine the decision-making process and interfere if it is found vitiated by mala fides, unreasonableness and arbitrariness. The State, its corporations, instrumentalities and agencies have the public duty to be fair to all concerned. Even when some defect is found in the decision-making process the court must exercise its discretionary power under Article 226 with great caution and should exercise it only in furtherance of public interest and not merely on the making out of a legal point. The court should always keep the larger public interest in mind in order to decide whether its intervention is called for or not. Only when it comes to a conclusion that overwhelming public interest requires interference, the court should intervene.”
Hon’ble Supreme Court in the case of M/s N.G. Projects Ltd. vs. Vinod Kumar Jain & others, reported as (2022) 6 SCC 127 has held that the constitutional Courts should refrain from interfering with tender process for infrastructure projects, as interference in such matters stalls projects of national importance and results in cost overrun. Paragraph nos. 21 to 23 of the said judgment are extracted below:-
“21.Since the construction of road is an infrastructure project and keeping in view the intent of the legislature that infrastructure projects should not be stayed, the High Court would have been well advised to hold its hand to stay the construction of the infrastructure project. Such provision should be kept in view even by the writ court while exercising its jurisdiction under Article 226 of the Constitution of India.
22.The satisfaction whether a bidder satisfies the tender condition is primarily upon the authority inviting the bids. Such authority is aware of expectations from the tenderers while evaluating the consequences of non-performance. In the tender in question, there were 15 bidders. Bids of 13 tenderers were found to be unresponsive i.e. not satisfying the tender conditions. The writ petitioner was one of them. It is not the case of the writ petitioner that action of the Technical Evaluation Committee was actuated by extraneous considerations or was mala fide. Therefore, on the same set of facts, different conclusions can be arrived at in a bona fide manner by the Technical Evaluation Committee. Since the view of the Technical Evaluation Committee was not to the liking of the writ petitioner, such decision does not warrant for interference in a grant of contract to a successful bidder.
23.In view of the above judgments of this Court, the writ court should refrain itself from imposing its decision over the decision of the employer as to whether or not to accept the bid of a tenderer. The Court does not have the expertise to examine the terms and conditions of the present day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands, rather the Court should examine as to whether the decision-making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a mala fide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the State and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived of the infrastructure for which the present day Governments are expected to work.”
Learned State Counsel points out that in recent times, due to influx of tourists to Nainital and Kainchi Dham, vehicular movement has increased manifold and because of the bottleneck created at Ranibagh due to landslide, huge problem of traffic jam is being faced everyday and people are stranded for several hours altogether. Thus, it is contended that the project in question, for which tender process was held, is not only necessary for easing the problem of traffic jam, but it is also a project of strategic importance.
As discussed above, petitioner failed to submit Chartered Account’s certificate, which every bidder was required to submit. Thus, we do not find any scope for interference in the matter. Accordingly, the writ petition fails and is dismissed. Interim order, if any, stands vacated.