High CourtsDivision Bench(2011) 11 BOM CK 0118

M/s. Sardessai Engineering Works, Naguesh Prasad, Madant, Cortalim, Goa and Shri Prakash B. Sardessai, Naguesh Prasad, Madant, Cortalim, Goa vs The Consumer Grievance Redressal Forum (CGRF), Electricity Department, Government of Goa

Bombay High Court · Decided on 17 November 2011

HON’BLE JUDGES
U.V. Bakre, J · A.P. Lavande, J
CASE NUMBER
Writ Petition No. 641 of 2011

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

7 paragraphs · 322 words

A.P. Lavande, J.—Heard Mr. Menezes, learned Counsel for the petitioners and Mr. Kantak, learned Advocate General for respondent No.2. Respondent No.1 being formal party, notice to respondent No.1 is dispensed with.

2.

Rule. By consent heard forthwith.

3.

By this petition, the petitioners challenge the order dated 26 th August, 2011 passed by respondent No.1, by which respondent No.1 has declined to entertain the application filed by the petitioners herein, seeking redressal of the grievance under various provisions of the Electricity Act, 2003. By order dated 11th December, 2009, passed by this Court in Writ Petition No. 536 of 2009, the petitioners were directed to pay a sum of Rs.8,00,000/-to respondent No.2 within a period of six weeks from the date of the order and in case the payment is not made as directed, respondent No.2 was permitted to proceed, in accordance with law, against the petitioners.

4.

Perusal of the impugned order discloses that respondent No.1 has refused to entertain the application on the ground that the petitioners have not paid the amount of Rs.8,00,000/-as directed by this Court in terms of order dated 11th December, 2009. A bare perusal of the order dated 11th December, 2009, passed by this Court in Writ Petition No. 536 of 2009, discloses that the payment of amount of Rs.8,00,000/-was not condition precedent for entertaining the application filed by the petitioners and as such, the impugned order is patently unsustainable in law and, as such, is liable to be set aside.

5.

For the reason stated above, the impugned order dated 26th August, 2011 passed by respondent No.1 is quashed and set aside. Respondent No.1 is directed to decide the complaint/representation No.2/11 expeditiously and in any case, within a period of two months from today, in accordance with law.

Needless to mention that respondent No.2 is at liberty to take appropriate steps for recovery of the amount/dues payable by the petitioners.

Petition stands disposed of.