High CourtsDivision Bench(2018) 08 CHH CK 0194

M/s Rajendra Construction vs State Of Chhattisgarh And Ors

Chhattisgarh High Court · Decided on 17 August 2018

RESULT
Disposed Of
CASE NUMBER
Writ Petition (C) No. 2324 Of 2018
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

14 paragraphs · 229 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ajay Kumar Tripathi, CJ

1.

Heard counsel for the parties.

2.

An unnecessary litigation has been generated because despite a request having gone to the Programmer Data Centre, Directorate, Urban

Administration and Development, Raipur, from the Municipal Corporation, Bilaspur, an inaction on their part or failure to give a suitable response for

almost a month and a half, the writ application has been filed.

3.

The Court is informed that the authorities are looking for a Court direction before they can roll-back the tender process for acceptance of the

technical bid and then only, the finance bid can be opened.

4.

If the Respondent-Municipal Corporation, Bilaspur is satisfied with the bona fide of the Petitioner and a request having gone to the Programmer of

the Data Centre, the matter should be expedited by a quick response.

5.

The questioned tender is Tender No. 24-6 which is System Tender No. 22752 dated 18.10.2017.

6.

The writ application is disposed off with a direction to Shri Toran Sharma, Programmer Data Centre, Directorate, Urban Administration and

Development, New Raipur that he will do the needful in terms of the request of the Municipal Corporation, Bilaspur as per their letter dated

05.07.2018, a copy of which is Annexure P/4. The said authority will do the needful within a period of one week from the date of production of a copy

of this order.