Tribunals and CommissionsDivision Bench(2023) 01 NGT CK 0014

M/s Rajchem Global Technologies Private Limited vs Punjab Pollution Control Board & Others

National Green Tribunal · Decided on 12 January 2023

HON’BLE JUDGES
Sudhir Agarwal, JM · Prof. A. Senthil Vel, EM
RESULT
Allowed
CASE NUMBER
Appeal No. 46 Of 2022 (I.A. No. 337 Of 2022)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

101 paragraphs · 990 words
1.

Heard Mr. A.R. Takkar, assisted by Ms. Shriya Takkar & Ms. Unnati Anand, Advocates for Appellant.

2.

This appeal has been preferred under Section 16 read with Section 18 of National Green Tribunal Act, 2010 (hereinafter referr6ed to as ‘NGT Act, 2010’) assailing the order dated 17.07.2021 passed by Punjab Pollution Control Board (hereinafter referred to as ‘PPCB’) and appellate order dated 10.08.2022 passed by the appellate authority.

3.

The competent assessing authority has imposed environmental compensation of Rs. 1,14,62,500/- upon the appellant vide order dated 17.07.2021 and the same has been confirmed by appellate authority by impugned appellate order dated 10.08.2022.

4.

Leaned counsel for the appellant has assailed the aforesaid two orders on two grounds. Firstly, that the industry never came into production and therefore, there was no question of violation of any environmental law relating to consent to operate under the provisions of Water (Prevention and Control of Pollution) Act, 1974 (hereinafter referred to as ‘Water Act 1074’) and Air (Prevention and Control of Pollution) Act, 1981 (hereinafter referred to as Air Act 1981 and authorization under Hazardous Waste Management Rules, 2016 (hereinafter referred to as HWM Rules 2016 and therefore, imposition of environmental compensation is illegal.

5.

Secondly, it is contended that even while applying the formula for computing the aforesaid compensation, the respondent authorities have erred in law in as much as the compensation has been computed since the date when Consent To Establish (hereinafter referred to as ‘CTE’) was granted to appellant i.e., 09.01.2019. Admittedly the unit itself commenced process for its establishment on and after 09.01.2019, hence, the question of running any production in the unit from 09.01.2019 does not arise.

6.

So far as the first aspect is concerned, we find that during inspection the authorities found that the appellant had six storage tanks of capacity of 10,000 ltrs each out of which four tanks were half filled with acid, with composition of HCl and H2SO4 , ratio of 4:1 and 5:1. This has been found as per the sample collected from the storage tanks and the result of analysis, mentioned in the notice dated 28.06.06.2021, issued by Chairman, PPCB wherein results of report are reproduced as under:-

“

Sr. No.

Point   of   sample collection

Results   (Qualitative analysis)

Ratio

1

Acid   storage   tank (red)

H2SO4 & HCl

HCl 4:1 H2SO4

2

Acid   storage tank (Brown)

H2SO4 & HCl

HCl

5:1

H2SO4

”

7.

Secondly the authorities found that the consumption of electricity commenced in January, 2020 but in June 2022 and onwards consumption suddenly has risen. The chart of electricity consumption reads as under:

“

S.No.

Bill date

Units   consumed in (KWH)

Amount in Rs.

1.

20 January17 2020

628

15,770/-

2.

17 February 2020

592

15,630/-

3.

18 March 2020

798

15,721/-

4.

20 April 2020

542

9,840/-

5.

18 June 2020

3202

47,690/-

6.

15 July 2020

1744

72,010/-

7.

18 August 2020

1476

95,900/-

8.

18 September 2020

2396

30,060/-

9.

19 October 2020

2792

61,420/-

10.

17 November 2020

2404

91,570/-

11.

17 December 2020

2756

1,27,540/-

12.

18 January 2021

3064

1,61,340/-

13.

18 February 2021

2054

1,88,660/-

14.

15 March 2021

1088

45,080/-

15.

15 April 2021

832

59,230/-

16.

17 May 2021

2090

84,640/-

Total

28458

11,22,101/-

”

8.

The aforesaid facts shows that there was substantial quantity of acid present on the site. This acid is one of the raw materials required for production of FeCl, found stored by the appellant and that quantity was after consumption of material during alleged testing period which appellant admits that it ran the unit for testing production. Further, sudden rise of consumption of electricity from June 2020 and onwards could not be explained. In that view of matter, we find no merit in the submission that the unit has never run into production. Even test run of production would have required Consent To Operate (hereinafter referred to as ‘CTO’). Admittedly no CTO was obtained by appellant. Hence, the view taken by the authorities on this aspect cannot be said to be erroneous either on facts or law.

9.

Now coming to computation of environmental compensation, we find some substance in the submission that number of days for which amount of compensation has been computed is not correct in as much as compensation could not have been computed from the date CTE was issued but when there is material on record to show or atleast come to a reasonable conclusion based on record that production started from a particular day, computation of compensation must have correlation with such period and not earlier thereto. 10. Now taking from the chart of electricity consumption, we find prima facie that during June 2020 to May 2021, there was high quantity of consumption of electricity and therefore even test production of the unit as claimed by the appellant must have gone during this period but without obtaining any consent to operate under the Water Act 1974, and Air Act 1981 and authorisation under HWM Rules, 2016. 11. Taking the period of June 2020 to May 2021, it is about 365 days for which amount of environmental compensation comes to Rs. 42 lakhs and odd. We are of the view that if we appellant presently deposit Rs. 42 lakhs within two months, the respondent authority shall not proceed with recovery of further environmental compensation until further orders of this Tribunal. We order accordingly. 12. In  the  meantime,  we  issue  notice  to  respondents  who  may  file response to this appeal within two months by e-mail at [email protected] preferably in the form of searchable PDF/ OCR Support PDF and not in the form of Image PDF. 13. List  for  further  consideration  on  06.04.2023  after  exchange  of pleadings.

I.A. No. 337/2022

This application is seeking condonation of delay. Having considered the submissions, we find that the delay in filing this appeal deserves to be condoned.

The application is allowed. Delay in filing appeal is condoned.