Judgment
S.J.VAZIFDAR, CHIEF JUSTICE
The petitioners seek a writ of mandamus directing respondent Nos.1 to 3 the official respondents, to consider their technical bid, to open their financial
bid and to consider them for the allotment of the work. The petitioners also seek an order restraining the official respondents from finalizing a contract
with respondent No.4 i.e. private respondent.
Respondent Nos.1 to 3 i.e. the official respondents invited e-tenders from various transporters and transport unions for transporting food grains
from Mandi/storage points for the year 2018-19.
The petitioners and the private respondents, among others, submitted their bids. The petitioners’ bid was rejected. The reason for the rejection
was communicated only on 22.03.2018 i.e. after this writ petition was filed. The petitioners’ technical bid was rejected on the ground that it did not
meet the requirements of Clause 4(ix) of the terms and conditions which admittedly formed a part of the Notice Inviting Tenders (NIT). Clause 4(ix)
reads as under:-“ix) Statement of Assets with valuation certificate from valuator along with documentary proof of immovable property other than
residential house, which may not be less than 10% of the cost of contract value.â€
The value of the contract is about Rs. 1.83 crores, 10% whereof is Rs.18.30 lacks. The Naib Tehsildar issued a certificate dated 02.02.2018 valuing
the property for the purpose of clause 4(ix) relied upon by the petitioner at about Rs.52 lacs. Absent anything else this met the requirement of clause
4(ix). The official respondents, however, rejected the technical bid on the ground that the Punjab National Bank held a lien in respect of the property
to the extent of Rs.1.85 lacs. The property, therefore, was unencumbered to the extent of over Rs.50 lacs. The question is whether this met the
requirement of clause 4(ix). We think it did.
Clause 4(ix) does not create a security in favour of the official respondents. It is not even the respondents’ case that a lien or charge or a
mortgage was created in respect of the said land. The official respondents in any event, therefore, could not proceed to recover any claim that they
may have had against the petitioner by proceeding against the said property except as unsecured creditors. Had the requirement been to furnish
unencumbered security it may have been a different matter altogether.
There is nothing to indicate that clause 4(ix) was to enable the official respondents to recover future dues, if any, against the petitioners. Had that
been the intention the NIT would have provided for the creation of a security in respect of the property. The clause is also consistent with the official
respondents i.e. the parties inviting tenders, being satisfied as to the financial capacity and ability of the bidder. The rejection of the bid, therefore,
merely on the ground that the Punjab National Bank held a lien to the extent of Rs.1.80 lacs is not valid.
The private respondent contends that irrespective of the circumstances the petition ought to be dismissed as a contract has already been entered
into between the official respondents and themselves.
In the facts and circumstances of this case, this ought not to deprive the petitioners an opportunity of being considered in the tender process. The
official respondents issued a work order dated 09.03.2018 in favour of the 4th respondent. An agreement was entered between them on 17.03.2018.
The work was to commence only on 01.04.2018 i.e. after the interim order. Prior thereto on 20.03.2018 we passed an interim order inter-alia to the
effect that any steps taken hereafter would be subject to further orders in the writ petition. As we noted earlier the impugned order was served upon
the petitioners only on 22.03.2018. There is nothing to indicate that between 17.03.2018 and 20.03.2018 the private respondents altered their position to
such an extent as to the warrant the dismissal of the writ petition although the petitioners have otherwise succeeded.
The fact that the petitioners had earlier filed a civil suit before Civil Judge (Junior Division), Hisar and that an interim order dated 09.03.2018 was
passed therein is irrelevant. The interim order merely required the official respondents to proceed in the matter in accordance with the terms and
conditions of the NIT. Pursuant thereto the official respondents proceeded with the tender process which has now been impugned in this petition. The
suit itself has been withdrawn. The issues on-merits were never dealt with by the Court.
In the circumstances, the petition is allowed. The petitioners’ technical bid shall be considered in accordance with the terms and conditions of
the NIT. If the technical bid is valid, the petitioners’ financial bid shall also be considered along with other bids. It is clarified that the technical bid
cannot be rejected on the ground that clause 4(ix) was not complied with.
It is also clarified that we have not directed the official respondents to issue the work order in favour of the petitioners or to any other party. That is
for the official respondents to decide. The official respondents are not bound to accept any bid. They are also at liberty to invite fresh bids, if
necessary and justified.