High CourtsSINGLE BENCH(2017) 04 KAR CK 0050

M/S GVR INFRA PROJECTS LIMITED vs UNION OF INDIA MINISTRY OF ROAD TRANSPORT & HIGHWAYS,

Karnataka High Court · Decided on 12 April 2017

HON’BLE JUDGES
A S Bopanna
RESULT
Dismissed
CASE NUMBER
1819 of 2017 (GM-RES)

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

426 paragraphs · 4,641 words
1.

The petitioner is before this Court claiming to be

aggrieved by the letter dated 04.01.2017 (Annexure-A)

issued by the respondent No.3 terminating the

agreement entered into between the parties. The

petitioner is seeking that enquiry be initiated into the

gross acts of omission and commission on the part of

respondents No.1 to 3 in playing fraud upon the

petitioner.

2.

The petitioner having participated in the tender

process for the work of strengthening from KM 216.00

(Gulagalale) to KM 237.00 (Maranahalli) and

providing rigid pavement from KM 250.620 (Kempuhole)

to KM 263.00 (Addahole) (Shiradi Ghat) of NH-48,

Bengaluru-Mangaluru Section, being successful had

entered into an agreement dated 06.11.2015 with the

respondents No.1 to 3 called as ''Engineering,

Procurement and Construction'' (''EPC'' for short). The

project cost was fixed at Rs.90,27,83,520/-. The

petitioner in that regard has referred to the different

Articles contained in the agreement including the term

to appoint a consulting firm and the manner of

commencement of the work as per the appointed date.

The petitioner contends that as per the requirement

they had submitted the Performance Bank Guarantee,

but the respondents had failed in their obligation to

provide 90% ''right of way'' of the project to carry out the

work. According to the petitioner, the work could have

been commenced only after the right of way was

provided so as to enable the petitioner to undertake the

work. The petitioner contends that the work of

Bituminous road (strengthening) for 21 kms and rigid

pavement/concrete of 12.25 kms had been carried out

and 50 Nos. of structures were also constructed. The

traffic continued to ply on the project Highway wherein

the petitioner was to undertake the work. The

respondent No.3 was required to close the project

highway for vehicular traffic and handover the same to

the petitioner in terms of Article 8.1 and Schedule-A to

the EPC agreement. The concrete road/rigid pavement

could have been carried out only if the road was

completely blocked as the work also involved the

construction of Culverts, Earthwork, Dry lean Concrete,

Pavement quality concrete.

3.

The petitioner further reiterates about the right

of way not being provided and that the respondent No.3

had verbally informed the petitioner to not carry out the

work in the stretch from KM 216.000 to KM 237.000 as

there is likely to be variation/ change in the scope of

work which was recorded in the meeting dated

04.12.2015. It is further contended that due to the

heavy rainfall in the region the work cannot also be

carried out between May to October. Hence the

possibility of carrying on with the work is only between

November to April. Despite not handing over the right of

way the respondents forced the petitioner to procure

construction material and equipment upto the extent of

50% of the entire project. It is contended that due to

the action of the respondents they were forced to invoke

Article 26 of the agreement for dispute resolution and

sought for appointment of the Conciliator. Despite all

this the respondents illegally issued the notice of

termination on 02.12.2016 without complying the

natural justice. The petitioner in that view filed a

petition under Section 9 of the Arbitration and

Conciliation Act for interim measure and injunction

against invoking the bank guarantee was obtained.

Petitioner contends that the four laning of KM 189.700

at Hassan to KM 237.000 at Maranahally of NH 48 was

awarded to respondent No.4 without informing the

petitioner and it came to their knowledge only

subsequently. Due to such action of the respondents,

the petitioner has approached this Court.

4.

Respondent No.3 has filed a detailed objection

statement. At the outset it is contended that the parties

are governed by an arbitration clause contained in the

agreement and as such the instant petition is not liable

to be entertained. It is contended that the petitioner

has already approached the City Civil Judge, Bengaluru

in a petition under Section 9 of the Arbitration and

Conciliation Act seeking to restrain the respondent No.3

from encashing the demand drafts. Even prior to the

order the same had been encashed. The petitioner

instead of availing an appropriate remedy for dispute

resolution has filed the instant writ petition only to

avoid the natural consequences that would flow on

termination. In that regard the petitioner is seeking to

overcome Section 2 and Articles 2.1.19 and 2.1.19.3 of

the EPC agreement insofar as the contract as entrusted

to the petitioner. It is pointed out that the tenders

called by the respondent No.4 is for the stretch

commencing from KM 189.700 to KM 237.00. The

entire stretch was sought to be rigid pavemented and

required a four-line Highway and it cannot be

considered as a substitution of the contract entrusted to

the petitioner and is in addition to that work entrusted

to the petitioner. The petitioner has failed to adhere to

the work entrusted to them and is only putting forth

excuses to overcome the non-performance and breach.

Insofar as the contract awarded to the petitioner from

KM 216.000 to KM 237.000 and from KM 250.620 to

KM 263.000, the allegations as made by the petitioner

relating to appointment of consulting Engineer and the

report submitted are all disputed and the further

contention that the right of way was not handed over is

also disputed.

5.

It is contended by respondent No.3 that the

performance guarantee was delivered by the petitioner

on 25.11.2015 and it is only at the delivery of the

performance guarantee the respondent was required to

handover possession. The possession is claimed to have

been handed over on 23.12.2015 and the

acknowledgement has also been reduced into writing.

The use of the road from Nelamangala to Mangaluru is

referred to with the details of the route through which it

passes. The steps taken to provide a road by keeping in

view the problem of maintenance in the Western Ghats

is referred to in detail. In that light, the work that was

required to be performed keeping in view that the

complete closure will not be possible due to various

villages located in the transit way is highlighted. Hence,

it is contended that the contract does not cast any

obligation to close or stop the flow of traffic. The

petitioner-company was aware of the challenges. As

indicated in Article 2.5, these aspects were also taken

note prior to bidding and it was done after visiting the

project site. With the knowledge of all these aspects the

petitioner had offered to ensure collection of 60% of the

material by the end of December 2015 after which the

respondent No.3 had indicated that the road would be

closed. Despite the same, the petitioner did not ensure

collection of the material. In that light the respondent

No.3 on making further reference to the specific Articles

contained in the agreement has disputed the claim of

the petitioner about the petitioner having been ready to

perform their part and the respondent not having made

appropriate arrangement for closure of the road as

alleged. With regard to the issues raised by the

petitioner relating to the bill not having been paid, it is

contended that the RA Bill No.1 itself would indicate

that it was prepared on 04.01.2017 and submitted on

05.01.2017 subsequent to the termination. Thus the

respondent No.3 contends that there are serious

disputed questions which arise for adjudication and in

that light, they seek dismissal of the petition.

6.

Respondent No.4 have filed their separate

objection statement limiting it only insofar as the nature

of the work being performed by them and the contention

relating to the work is reiterated in the same manner as

has been put forth by respondent No.3 whereby it is

contended that there is no overlap of the work being

performed by them and the petitioner. The said

respondent also seeks for dismissal of the petition.

7.

Heard Sri. Udaya Holla, learned senior counsel

on behalf of Sri. Venkat Satyanarayana, learned counsel

for the petitioner, Sri. Krishna Dixit, Sri. S.V.Giridhar,

Ms. Shilpa Shah, learned counsel for the respective

respondents and perused the petition papers.

8.

As evident from the records and the rival

contentions, the contract entered into between the

parties is terminated by the communication dated

04.01.2017. It is impugned in this petition at

Annexure-A. The contract between the parties is the

EPC agreement dated 06.11.2015 entered into for

undertaking the work of strengthening from KM

216.000 to KM 237.000 and providing rigid pavement

from KM 250.620 to 263.000 (Shiradi Ghat) of NH 48

Bangalore- Mangalore Section in the State of Karnataka.

The termination of the contract has been made since

the respondent No.3 based on the report of the

Authority Engineer and the Superintending Engineer

concluded that the petitioner has not been able to

complete the work as provided under the contract. If in

that light a dispute has arisen between the parties, the

mechanism for resolution thereof is provided under

Article 26 of the EPC agreement as it is to be resolved by

arbitration.

9.

The learned counsel for the respondent No.3 at

the outset would therefore contend that the dispute

resolution mechanism as provided under the EPC

agreement is the appropriate remedy to be availed if the

petitioner is aggrieved by the termination of the contract

and as such the instant petition is not maintainable. It

is pointed out that the petitioner in that regard, for the

purpose of interim measure having filed a petition under

Section 9 of the Arbitration and Conciliation Act in A.A.

No. 08/2017 cannot now invoke the writ remedy. Hence

the petition is liable to be dismissed in limine, is the

contention.

10.

Learned senior counsel for the petitioner in

order to counter the said contention and to contend that

the writ petition will be maintainable has relied on the

decision in the case of Uttar Pradesh State Bridge

Construction Corporation Limited, Lucknow -vs-

Bangalore Development Authority and Others

[2005 (5) Kar. L.J. 112 (DB)] wherein the Hon''ble

Division Bench of this Court has held that the writ

petition against the State and its instrumentality arising

out of contractual obligation is maintainable and

judicial review is permissible both at the pre-contract

stage and post-contract stage since the action of the

State should be fair, just, reasonable and devoid of

arbitrariness which are the basic requirements of

Article 14 of the Constitution. In the said case the

termination of the contract which had been made by

BDA was upheld by this Court on taking note of the

procedure that was followed.

11.

The decision in the case of Zonal Manager,

Central Bank of India -vs- Devi Ispat Limited and

Others [(2010) 11 SCC 186] is relied, wherein the

Hon''ble Supreme Court has held that even in

contractual matters, mandamus can be issued against

the authorities discharging the ''State'' functions. That

was a case where despite the repayment of the entire

loan the documents were not returned by the bank. In

that situation, it was held that it is not the DRT alone

which should look into such matter but a writ can also

be issued. The learned senior counsel has also relied on

the decision in the case of Union of India and Others

-vs- Tantia Constructions Private Limited [(2011) 5

SCC 697] wherein, in respect of a contractual matter

which contained an arbitration clause, it is held that an

alternative remedy is not an absolute bar to the

invocation of the writ jurisdiction of the High Court or

the Supreme Court and a writ petition without

exhausting that remedy will be maintainable.

12.

Learned counsel for the respondent No.3 in

order to rebut the same and to contend that in the

present facts the exercise of jurisdiction by this Court is

not called for, has relied on a later decision of the

Hon''ble Supreme Court in the case of Joshi

Technologies International Inc. -vs- Union of India

[(2015) 7 SCC 728] wherein the Hon''ble Court with

reference to its earlier decisions has summarised the

position as hereunder,

"69. The position thus summarised in the aforesaid principles has to be understood in the context of discussion that preceded which we have pointed out above. As per this, no doubt, there is no absolute bar to the maintainability of the writ petition even in contractual matters or where there are disputed questions of fact or even when monetary claim is raised. At the same time, discretion lies with the High Court which under certain circumstances, it can refuse to exercise. It also follows that under the following circumstances, "normally", the Court would not exercise such a discretion:

69.1. The Court may not examine the issue unless the action has some public law character attached to it.

69.2. Whenever a particular mode of settlement of dispute is provided in the contract, the High Court would refuse to exercise its discretion under Article 226 of the Constitution and relegate the party to the said made of settlement, particularly when settlement of disputes is to be resorted to through the means of arbitration.

69.3. If there are very serious disputed questions of fact which are of complex nature and require oral evidence for their determination.

69.4. Money claims per se particularly arising out of contractual obligations are normally not to be entertained except in exceptional circumstances.

70.

Further legal position which emerges from various judgments of this Court dealing with different situations/aspects relating to the contracts entered into by the State/public Authority with private parties, can be summarized as under:

70.1. At the stage of entering into a contract, the State acts purely in its executive capacity and is bound by the obligations of fairness.

70.2. State in its executive capacity, even in the contractual field, is under obligation to act fairly and cannot practice some discriminations.

70.3. Even in cases where question is of choice or consideration of competing claims before entering into the field of contract, facts have to be investigated and found before the question of a violation of Article 14 could arise. If those facts are disputed and require assessment of evidence the correctness of which can only be tested satisfactorily by taking detailed evidence, Involving examination and cross- examination of witnesses, the case could not be conveniently or satisfactorily decided in proceedings under Article 226 of the Constitution. In such cases the court can direct the aggrieved party to resort to alternate remedy of civil suit etc.

70.4. Writ jurisdiction of High Court under Article 226 of the Constitution was not intended to facilitate avoidance of obligation voluntarily incurred.

70.5. Writ petition was not maintainable to avoid contractual obligation. Occurrence of commercial difficulty, inconvenience or hardship in performance of the conditions agreed to in the contract can provide no justification in not complying with the terms of contract which the parties had accepted with open eyes. It cannot ever be that a licensee can work out the license if he finds it profitable to do so: and he can challenge the conditions under which he agreed to take the license, if he finds it commercially inexpedient to conduct his business.

70.6. Ordinarily, where a breach of contract is complained of, the party complaining of such breach may sue for specific performance of the contract, if contract is capable of being specifically performed. Otherwise, the party may sue for damages.

70.7. Writ can be issued where there is executive action unsupported by law or even in respect of a corporation there is denial of equality before law or equal protection of law or if it can be shown that action of the public authorities was without giving any hearing and violation of principles of natural justice after holding that action could not have been taken without observing principles of natural justice.

70.8. If the contract between private party and the State/instrumentality and/or agency of State is under the realm of a private law and there is no element of public law, the normal course for the aggrieved party, is to invoke the remedies provided under ordinary civil law rather than approaching the High Court under Article 226 of the Constitutional of India and invoking its extraordinary jurisdiction.

70.9. The distinction between public law and private law element in the contract with State is getting blurred. However, it has not been totally obliterated and where the matter falls purely in private field of contract. This Court has maintained the position that writ petition is not maintainable. The dichotomy between public law and private law, rights and remedies would depend on the factual matrix of each case and the distinction between public law remedies and private law, field cannot be demarcated with precision. In fact, each case has to be examined, on its facts whether the contractual relations between the parties bear insignia of public element. Once on the facts of a particular case it is found that nature of the activity or controversy involves public law element, then the matter can be examined by the High Court in writ petitions under Article 226 of the Constitution of India to see whether action of the State and/or instrumentality or agency of the State is fair, just and equitable or that relevant factors are taken into consideration and irrelevant factors have not gone into the decision making process or that the decision is not arbitrary.

70.10. Mere reasonable or legitimate expectation of a citizen, in such a situation, may not by itself be a distinct enforceable right, but failure to consider and give due weight to it may render the decision arbitrary, and this is how the requirements of due consideration of a legitimate expectation forms part of the principle of non-arbitrariness.

70.11. The scope of judicial review in respect of disputes falling within the domain of contractual obligations may be more limited and in doubtful cases the parties may be relegated to adjudication of their rights by resort to remedies provided for adjudication of purely contractual disputes.

71.

Keeping in mind the aforesaid principles and after considering the arguments of respective parties, we are of the view that on the facts of the present case, it is not a fit case where the High Court should have exercised discretionary jurisdiction under Article 226 of the Constitution. First, the matter is in the realm of pure contract. It is not a case where any statutory contract is awarded."

13.

In the above background, the legal position is

clear that there is no bar for a writ Court to entertain a

writ petition in contractual matters even if the

alternative remedy is provided in the contract, but it is

only in the exceptional circumstances carved out, the

writ is to be entertained and not as a matter of routine.

Normally, if there are factual disputes involved relating

to performance or non- performance of the contract, the

parties are to be relegated to the appropriate remedy. In

that back ground, if the facts in the instant case is

noticed, it is not that even as per the case of the

petitioner the work has been completed. On the other

hand, the contention is that the work could not be

undertaken as there was breach on the part of the

respondent No.3 in not providing the right of way by

blocking the road and enabling them to undertake the

work and the allegation is also that there is overlap of

the work as entrusted to the petitioner and being

undertaken by the respondent No.4. Hence it is in the

nature of a justification being put forth for the work not

being progressed and the blame of committing the

breach is being shifted on the other party to the

contract.

14.

On those aspects relating to the contract, the

learned senior counsel for the petitioner has made

reference to Article 10.3.1 with regard to the time frame

within which the work is to be performed from the

appointed day i.e., the date on which the petitioner has

delivered the performance security and on which day

90% of the ''right of way'' is to be provided. In that

context, the Site as described in Article 8.1 and

Schedule-A is referred and in that regard, it is

contended that though the vehicles were to be blocked

the same had not been done which prevented the

petitioner from undertaking the work. The learned

senior counsel has referred to the documents produced

along with the additional statement of facts with regard

to the portion of the work performed in Sakleshpur

Town as depicted in Annexure-AA, which is a part of the

contract and the petitioner having procured the

materials and machinery as per the requirement, the

work could not be done in the remaining portion as the

''right of way'' was not provided.

15.

Learned counsel for respondent No.3 on these

aspects would seriously dispute the position and would

refer to Article 23.1 wherein the procedure for

termination is provided and despite the notice being

issued to cure the defects and the cure period having

lapsed, there was no progress and in that light the

termination has been made. Reference is made to the

definition of ''Right of Way'' as contained in Article 28 of

the EPC agreement relating to the constructive

possession of the site and in that context, reference is

made to Article 6.1.1 where the disclaimer is provided

due to which the petitioner being aware of the terrain

and all working conditions had agreed to undertake the

work which is further contained in the Instruction to

bidders in Clause 2.5.1. The letter dated 16.12.2015

(Annexure-R2) whereunder the petitioner was requested

to depute the authorised person to take over the project

site is relied. The letter dated 19.03.2016 addressed to

the petitioner will also indicate that the site was

inspected on 26.12.2015 and instruction was issued to

start the work immediately but the work had not

progressed which was also referred therein. To point

out that the complete closure of the road was not a

condition agreed upon and on the contrary the

petitioner had agreed to maintain the road to keep it in

road worthiness for the plying traffic as contained in

Article 10.4 relating to maintenance during construction

period is also referred. In this regard, reference is also

made to Article 16 relating to the traffic regulation to be

made by the Contractor. The newspaper reports relating

to road closure are all reports of the earlier contract

period and not relating to the present one. Even

otherwise the stoppage of traffic would have arisen only

if the petitioner had stored the construction material

and the equipments to the extent of 60% as agreed in

the contract, which the petitioner had failed to fulfil.

16.

Insofar as the overlapping of work as

contended by the petitioner, due to which they claim

that they could not perform the work, a comparative

reference is made to the work assigned to the petitioner

which is described in page 70 of the petition papers

which states the work as Strengthening from KM

216.000 to 237.000 and providing Rigid Pavement from

250.

620 to 263.000 (Shiradi Ghat) of NH-48, whereas

the work undertaken by respondent No.4 is referred to

in Section 1 of the Agreement as available in page 457

of the petition papers and is described as Package-I-

Four Laning of Hassan (Existing Km 189+700, Design

Ch 184+912) to Maranahally (Existing km 237+000,

Design Ch 230+060) section of NH-75 (Old NH No 48).

Though the petitioner has relied on the communication

dated 17.12.2016 (Annexure-Q) to contend that there

was change in scope of work, the learned counsel for

respondent No.3 has referred to the contents to point

out that it was not a decision taken. The schedule as

per which the work should have been completed is

stated in paragraph-30 of the objection statement which

is on the basis as contained in Schedule-J of the EPC

agreement. The bill dated 04.01.2017 as at Annexure-R

is pointed out to contend that if the same is taken into

consideration only about 10% of the work was done as

on the date of termination. The letter dated 05.05.2016

of the petitioner is referred to point out that the reasons

put forth therein is not what is sought to be contended

herein, but it was the difficulty faced by the petitioner at

their end which had delayed the work. The notice dated

30.06.2016 (Annexure-R3) calling upon to cure the

defects will point out that all the details had been

indicated and thereafter the termination was made.

17.

In the background of the contentions urged, it

will indicate that there are several disputed factual

aspects relating to the site in the context of ''right of way''

not being available since the traffic had not been closed

and as to whether it was necessary at all in view of the

terms agreed in the contract. The materials having been

collected in that background also raises disputed

questions and the contention that only 10% of the work

having been completed at the time of termination of the

contract and the reasons there for, are issues which

require adjudication to come to a conclusion as to who

had committed the breach. The scope of work is also

being disputed in the context of the work being

undertaken by respondent No.4. Therefore in that

context, even though the decisions cited above indicate

about the writ petition in contractual matters that too

when alternative remedy is available being maintainable

as a proposition of law, the question is whether it is to

be entertained in a situation when it raises several

disputed questions of fact which will require resolution

in an appropriate manner.

18.

This Court while examining such disputed

contentions in W.P.Nos.11091-92/2016 disposed on

20.03.2017 had taken note of a decision of the

Hon''ble Supreme Court in the case of State of

Kerala and Others -vs- M.K.Jose [(2015) 9 SCC 433]

wherein it is observed, what precisely was the quantum

of work done and whether there had been a breach by

the owner or the contractor are required to be gone into

by the appropriate legal forum. It is held therein that a

writ Court should ordinarily not entertain a writ

petition, if there is a breach of contract involving

disputed questions of fact. In the instant facts as

already noticed above, there are several factual disputes

which require determination based on evidence. As

noticed, Article 26 of the EPC agreement provides for a

detailed dispute resolution mechanism. The petitioner

being aware of the legal remedy has already resorted to

the same for the purpose of interim measure by filing

the petition under Section 9 of the Arbitration and

Conciliation Act in A.A.No.08/2017. Hence it would be

open for the petitioner to avail that remedy which is

provided to them under law, due to which I do not deem

it appropriate to decide the disputed questions between

the parties in the narrow scope available in a writ

petition, when prima facie it is seen that the respondent

No.3 has terminated the agreement by following the

procedure contemplated under the agreement. Whether

the reason for which it was terminated is justified or

not, if not, what relief is to be provided to the petitioner

are matters to be decided in the appropriate legal forum

as otherwise in a writ proceedings, it is not expected to

grant specific performance of the contract or quantify

the damages, if the breach is proved. The observations

herein being only for the purpose of consideration of

this writ petition, the contentions on merits are to be

left open which shall be considered by the appropriate

forum based on the evidence available before it, without

being prejudiced by any of the observations.

In that view the petition is dismissed, leaving it

open to the petitioner to avail the appropriate remedies

open to them in accordance with law. No costs.