High CourtsSingle Bench(2023) 06 SHI CK 0009

M/S/ C&C Constructions Ltd vs Chief Engineer-Cum-Project Director (HPRIDC)

High Court Of Himachal Pradesh · Decided on 12 June 2023

HON’BLE JUDGES
Jyotsna Rewal Dua, J
RESULT
Disposed Of
CASE NUMBER
Arbitration Case No. 365, 366 Of 2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

5 paragraphs · 208 words

Jyotsna Rewal Dua , J

1.

Provisions of Section 29A(4) of the Arbitration and Conciliation Act have been invoked second time by the petitioner for extending the period of making the Arbitral award.

2.

Vide order dated 10.01.2023, passed in Arbitration Case No. 89/2022, time to complete Arbitral proceedings in the matter was extended up to 31.03.2023. The order pertains to arbitration in the matter of M/s C&C Constructions Ltd. Vs HPRIDC in respect of the disputes arising out of a contract for executing the Balance work of widening and strengthening of Theog-Kothkai- Kharapathar Road Section from Km 0+000 to Km 48+000 (48 Km) in October, 2013.

Learned Senior Counsel for the petitioner has placed on record proceedings of 38th Meeting (Internal Virtual Meeting) of learned Arbitral Tribunal held on 2nd March 2023 and on that basis submitted that the learned Arbitral Tribunal has tentatively fixed 25.06.2023 as the date for announcement of the Arbitral award. Learned Senior Counsel for the respondent has no objection for extending the period of making the Arbitral award.

In view of submissions made by learned Senior Counsel for the parties, time to complete the Arbitral proceedings is extended till 30.06.2023. The petition to stand disposed of alongwith pending miscellaneous application(s), if any.