High CourtsSingle Bench(2020) 11 DEL CK 2742

Ms Bridge Building Construction Co Pvt Ltd vs Bharat Heavy Electricals Ltd

Delhi High Court · Decided on 23 November 2020

HON’BLE JUDGES
C. Hari Shankar, J
RESULT
Allowed
CASE NUMBER
O.M.P.(MISC.)(COMM.) 265/2020

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

8 paragraphs · 89 words

I.A. No.10824/2020 (Exemption)

1.

Exemption allowed, subject to all just exceptions.

2.

The applications stand disposed of.

O.M.P.(MISC.)(COMM.) No.265/2020

1.

This petition seeks extension of the time available with the learned sole Arbitrator to conclude the arbitral proceedings and pass award.

2.

Mr.Pallav Kumar, learned counsel appearing for the respondent, has no objection.

3.

Accordingly, the time available with the learned sole Arbitrator, to complete arbitral proceedings and render award, is extended by a period of nine months from today.

4.

The petition is allowed in the aforesaid terms.