Judgment
A complaint was filed in FORM 'M' on 18.07.2024 by Mrs. Vishakha Goel (hereinafter referred to as "Complainant") under section 31 r/w section 18 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as ‘RE (RD) Act, 2016’ or ‘the Act’) stating that she booked Unit No. SB1-0203, 2nd Floor, Slab Block I in the project "Godrej South Estate Okhla" promoted by "Godrej Vestamark LLP" (hereinafter referred to as "Respondents") located in Delhi and paid a total of Rs. 45,32,151/- (Rupees Forty-Five Lakhs Thirty-Two Thousand One Hundred and Fifty-One Only) towards the unit for total consideration of Rs. 4,49,81,884/-.
The Complainant alleged that the Respondents made specific representations regarding their NRI scheme whereby she was required to pay only Rs. 5,00,000/- at the time of booking and initially only 10% of the total sale consideration, with 85% to be paid upon application for Occupancy Certificate and remaining 5% upon offer of possession within 2 months of receiving the Occupancy Certificate. The Complainant was allotted the unit vide Allotment Letter dated 11.06.2020 and subsequently made payments totalling Rs. 39,82,151/- in instalments on 31.07.2020, 04.08.2020, and 25.09.2020, completing 10% of the total consideration as agreed. The Agreement for Sale was executed on 03.10.2020.
It is averred that both the Complainant and the Respondents mutually assented to and executed the terms and conditions as delineated in the Allotment Letter dated 11.06.2020, as well as the subsequent Agreement for Sale dated 03.10.2020, pertaining to Unit No. SB1-0203 in the 'Godrej South Estate Okhla' project.
The Complainant further asserted that on 07.04.2024, the Respondents informed her via email that they had received a partial Occupancy Certificate on 06.04.2024 for the tower containing her unit and demanded payment of Rs. 3,80,98,283/- contrary to the original payment terms. The Complainant alleged that when she visited the project site on 13.04.2024, the project was incomplete and unsafe for occupation. The Respondents subsequently issued a pre-termination letter on 28.06.2024 demanding payment within seven days and terminated the allotment on 13.07.2024.
The preliminary hearings in the case were held on 02.09.2024 and 08.10.2024. Notice to the Respondents was issued on 24.10.2024 both through post and via email.
The matter was subsequently heard on 12.12.2024, 20.02.2025, 16.04.2025, 08.05.2025, 28.05.2025, 10.07.2025, 06.08.2025, 12.08.2025 and 02.09.2025. The Respondents filed their reply on 15.04.2025. The Complainant filed the rejoinder to the reply on 28.04.2025. Thereafter, the Complainant and Respondents also filed the written arguments on 22.08.2025 and 25.08.2025 respectively.
For the sake of convenience, the arguments and submissions made on behalf of the Complainant are summarized as under:
a. The Respondents made premature payment demands contrary to the NRI scheme representations and violated the agreed payment terms. The Complainant contended that despite obtaining only a partial Occupancy Certificate for one tower, the Respondents demanded 85% of total consideration when the entire project allegedly remained incomplete.
b. The Complainant submitted that during site inspections on 13.04.2024 and 25.04.2024, the project was found to be unsafe for occupation with ongoing construction work. The Complainant alleged that essential amenities including clubhouse, swimming pool, water bodies, cabana, play areas, greens and air purifying system remained incomplete.
c. The Complainant argued that the partial Occupancy Certificate for one tower does not satisfy the contractual obligation under Clause 7.1 of the Agreement for Sale for a single-phase project. Relying on the judgment in M. Ahuja Projects Pvt. Ltd. v. Green Glory Residents Welfare Society, 2024 SCC OnLine Chh 3680, the Complainant contended that completion certificates cannot be treated as conclusive in light of ground realities.
d. The Complainant submitted that the termination violated Clause 9.3(ii) of the Agreement for Sale as the Respondents allegedly failed to provide mandatory 30-day prior notice.
e. The Complainant sought the following reliefs:
direction to the Respondents to cancel/retract the pre-termination letter dated 28.06.2024 and cease all illegal demands for additional payments of Rs. 3,80,98,283/- along with interest that are contrary to initially agreed terms;
direction to desist from raising further illegal demands until the project is 100% complete with all amenities including clubhouse, swimming pool, water bodies, cabana, play areas, greens and air purifying system;
compensation for mental agony, inconvenience, and financial loss including costs incurred for visits and consultations;
costs of the present complaint; and;
any other relief deemed fit and proper.
For the sake of convenience, the arguments and submissions made on behalf of the Respondents are summarized as under:
a. The Respondents denied all allegations and characterized the complaint as vexatious, misleading, and filed with mala fide intentions to avoid legitimate payment obligations. The Respondents submitted that it is a reputed real estate developer holding registration for the project under Registration No. DLRERA2019P0003 as a single-phase development.
b. The Respondents submitted that it validly obtained Completion-cum-Occupation Certificate from MCD on 06.04.2024 after proper inspection by concerned authorities following due process. The Respondents emphasized that the Occupancy Certificate was issued only after thorough verification by competent authorities, establishing the habitability and completion of the concerned tower.
c. The Respondents contended that the demand for Rs. 3,80,98,283.09 was entirely lawful and in accordance with the agreed payment plan milestone "On application of OC" as stipulated in the Agreement for Sale. The payment became due on 26.04.2024 as per the contractual terms, and the Complainant's failure to pay constituted willful default.
d. The Respondents submitted that they provided adequate notice and opportunities to the Complainant to cure the default through multiple reminders and communications via emails dated 03.05.2024, 04.05.2024, 05.05.2024, 21.05.2024, 23.05.2024, 28.05.2024, 29.05.2024 and 30.05.2024, demonstrating their good faith efforts to resolve the matter before resorting to termination.
e. The Respondents argued that the Complainant misused past pictures of the project to create false evidence and made vague allegations without substantiating the claimed incomplete status. The Respondents maintained that the photographs submitted by the Complainant do not indicate when they were taken and are irrelevant to the actual status at the time of Occupancy Certificate issuance.
f. The Respondents contended that the termination was carried out in strict accordance with Clause 9.3(ii) of the Agreement for Sale after the Complainant's continuous default persisted for more than three consecutive months despite numerous notices and reminders.
g. The Respondents raised preliminary objections that the complaint is not maintainable as the Complainant ceased to be an "allottee" within the ambit of the Act after valid termination due to her own default, and thus has no locus standi to file the complaint under the principle "commodum ex injuria sua nemo habere debet".
h. The Respondents further contended that the demand raised in April 2024 was not an offer of possession but merely enforcement of the payment milestone "on application of OC," and that possession and OC are distinct contractual events with the final 5% payment due only at formal possession stage.
The Respondents argued that Part Occupancy Certificates are legally valid under the Unified Building Bye-Laws for Delhi, 2016, which expressly provide for Part OCC issuance for buildings complete in all respects from ground to terrace, irrespective of single-phase or multi-phase project classification.
We have heard the arguments of Ld. Counsels of both the parties and perused the records.
ANALYSIS AND CONSIDERATION
Before going into the determination of the issues in the matter, firstly the relief of compensation sought by the complainant needs to be settled. The complainant has claimed compensation as well. At the very outset, it is pertinent to shed light on the issue whether damages and compensation can be granted by the Authority. The Hon'ble Apex Court in the case of M/s. Newtech Promoters and Developers Pvt. Ltd vs. State of UP and Ors. (CIVIL APPEAL NO(S). 6745 - 6749 OF 2021) has categorically held, "when it comes to a question of seeking the relief of adjudging compensation and interest thereon under Sections 12, 14, 18, and 19, the adjudicating officer exclusively has the power to determine, keeping in view the collective reading of Section 71 read with Section 72 of the Act." It is thus clear that the Authority does not have the power to grant the relief of damages and compensation under Section 18 of the Act. As per Section 71 of the Act, the complainant may approach the Adjudicating Officer for the grant of compensation. In view of the same, we are not considering the relief as to compensation and damages in the present matter.
Having carefully examined the facts and circumstances, it is evident that several critical issues emerge for determination before this Authority. The following issues require detailed analysis:
a. Whether the Complainant retains locus standi to file and maintain the present complaint after the termination of her allotment by the Respondents.
b. Whether the demand raised by the Respondents for 85% payment (Rs. 3,80,98,283/-) was lawful, justified and in accordance with the contractual terms and statutory provisions upon obtaining the Occupancy Certificate.
c. Whether the final notice dated 28.06.2024 issued by the Respondents was rightfully served and in accordance with the contractual terms and legal requirements.
d. Whether the termination of allotment effected on 13.07.2024 was carried out in accordance with Clause 9.3 of the Agreement for Sale and the provisions of the RE(RD) Act, 2016.
This Authority shall address each issue in light of the factual matrix, the contractual terms, and the statutory framework under the RE (RD) Act, 2016.
Issue no. 1: Whether the Complainant retains locus standi to file and maintain the present complaint after the termination of her allotment by the Respondents.
The preliminary objection raised by the Respondents regarding the Complainant's locus standi to maintain the present complaint requires careful and detailed examination of the statutory definition of "allottee" under the RE(RD) Act, 2016, the circumstances and legality of the termination process, and the specific rights preserved for aggrieved persons even after cancellation of allotments.
Section 2(d) of the RE(RD) Act, 2016 provides the definition of "allottee" which reads as follows:
"allottee" in relation to a real estate project means the person to whom a plot, apartment or building, as the case may be, has been allotted, sold (whether as freehold or leasehold) or otherwise transferred by the promoter, and includes the person who subsequently acquires the said allotment through sale, transfer or otherwise but does not include a person to whom such plot, apartment or building, as the case may be, is given on rent;"
The evidence on record unequivocally establishes that the Complainant was duly and validly allotted Unit No. SB1-0203 through a formal Allotment Letter dated 11.06.2020 issued by the Respondents. Subsequently, both parties executed a comprehensive Agreement for Sale on 03.10.2020, which created binding legal obligations and established the framework for their ongoing relationship. The termination was later effected on 13.07.2024 allegedly due to the Complainant's failure to pay the demanded amount of Rs. 3,80,98,283/-despite multiple notices and opportunities provided by the Respondents.
Section 11(5) of the RE(RD) Act, 2016 specifically governs the cancellation of allotments by promoters and provides important safeguards:
"11(5) The promoter may cancel the allotment only in terms of the agreement for sale:
Provided that the allottee may approach the Authority for relief, if he is aggrieved by such cancellation and such cancellation is not in accordance with the terms of the agreement for sale, unilateral and without any sufficient cause."
The proviso to Section 11(5) of the Act contains a crucial legislative recognition that even after cancellation or termination of an allotment, an aggrieved person retains specific rights to approach the Authority for relief. This statutory provision acknowledges that cancelled allottees may have valid and legitimate grievances against improper, irregular, or legally unsustainable termination processes. The legislature has deliberately preserved the locus standi of such persons for the limited but important purpose of challenging the validity, legality, and procedural correctness of cancellation orders.
However, it is important to note that this preserved locus standi is not absolute or unconditional. The right to challenge cancellation exists specifically when the cancellation is "not in accordance with the terms of the agreement for sale, unilateral and without any sufficient cause." This creates a framework where this Authority must examine the substantive validity of the termination process to determine whether the Complainant's challenge has merit, regardless of her technical standing to file the complaint.
Based on the statutory framework and factual circumstances, this Authority holds that the Complainant retains locus standi to file and maintain the present complaint for the purpose of challenging the termination.
Issue no. 2: Whether the demand raised by the Respondents for 85% payment (Rs. 3,80,98,283/-) was lawful, justified and in accordance with the contractual terms and statutory provisions upon obtaining the Occupancy Certificate.
Upon examination of the facts, submissions, and documentary records presented in this case, this Authority finds it necessary to analyze the contractual payment obligations and the validity of the Respondent's demand for 85% consideration.
The Agreement for Sale dated 03.10.2020 contains specific and unambiguous payment terms that form the fundamental basis of the contractual relationship between the parties. The payment plan, which was negotiated and agreed upon by both parties, clearly stipulates a milestone-based structure: 10% at booking, 85% "upon application for Occupancy Certificate," and the remaining 5% at the time of intimation/offer of possession. This provision represents a milestone-based payment structure that is common in real estate transactions and provides certainty to both promoters and allottees regarding their respective obligations. The structure demonstrates that Occupancy Certificate achievement and formal possession are distinct contractual events, with separate payment obligations attached to each milestone.
The undisputed facts on record establish that the Respondents successfully obtained a Completion-cum-Occupation Certificate from the Municipal Corporation of Delhi (MCD) on 06.04.2024 specifically for the tower containing the Complainant's allotted unit. This certificate was issued by the competent statutory authority after comprehensive inspection and verification of compliance with all applicable building codes, safety standards, municipal bye-laws and regulatory requirements. The issuance of such certificate represents an official determination by expert municipal authorities that the concerned structure is fit for human habitation and meets all prescribed standards.
Section 11(4)(b) of the RE(RD) Act, 2016 provides:
“(4)The promoter shall—
(b)be responsible to obtain the completion certificate or the occupancy certificate, or both, as applicable, from the relevant competent authority as per local laws or other laws for the time being in force and to make it available to the allottees individually or to the association of allottees, as the case may be;”
The Complainant's argument that a single-phase project requires simultaneous completion of all amenities and common areas before any payment obligations crystallize cannot be properly adjudicated at this stage of the proceedings, as such matters are intrinsically linked to the actual physical handover and possession process, which is distinct from the payment milestone achieved upon making application for obtaining the Occupancy Certificate for the specific tower. The UBBL framework further clarifies under Bye-law 2.7.2 that internal/external wall finishing/plastering need not delay OCC issuance, provided safety and habitability standards are met. The Complainant's allegations regarding the completion status of all amenities and common areas cannot be adjudicated at this stage of the proceedings, as such matters pertain to the actual physical handover and possession process, which is distinct from the payment milestone achieved upon obtaining the Occupancy Certificate.
Section 11(4)(a) of the RE(RD) Act, 2016 emphasizes that the primary obligations between parties are governed by their mutually agreed contractual terms as embodied in the Agreement for Sale. Section 11(4)(a) of the RE(RD) Act, 2016 requires promoters to:
11.(4) The promoter shall— (a) be responsible for all obligations, responsibilities and functions under the provisions of this Act or the rules and regulations made thereunder or to the allottees as per the agreement for sale, or to the association of allottees, as the case may be, till the conveyance of all the apartments, plots or buildings, as the case may be, to the allottees, or the common areas to the association of allottees or the competent authority, as the case may be:
The Agreement for Sale executed between the parties contains the specifically negotiated and agreed payment milestone "upon application for Occupancy Certificate”.
The Complainant's reliance on the judgment in M. Ahuja Projects Pvt. Ltd. v. Green Glory Residents Welfare Society, 2024 SCC OnLine Chh 3680 is factually and legally distinguishable from the present case. That case dealt with specific situations where completion certificates were issued without actual completion or in circumstances suggesting fraudulent or irregular issuance. In contrast, the present case involves a validly issued Occupancy Certificate by the MCD after proper verification, inspection, and compliance determination for the specific tower containing the Complainant's unit.
The Complainant's allegation that she was not allowed to inspect her unit due to safety concerns lacks credibility. The MCD's issuance of the certificate after professional inspection establishes a legal presumption of the habitability, safety, and completion of the concerned tower for the purposes of occupation. The Complainant's allegations regarding amenities and common areas, while they may be relevant for possession-related proceedings, cannot affect the validity of the payment demand at this stage, as such matters are to be addressed during the actual handover process. The Respondents raised this demand based on the completion of the tower as certified by the competent authority, and the Complainant's obligation to make the payment crystallized upon the achievement of this agreed milestone.
Issue no. 3: Whether the final notice dated 28.06.2024 issued by the Respondents was rightfully served and in accordance with the contractual terms and legal requirements.
The third issue requires detailed examination of the final notice dated 28.06.2024 issued by the Respondents, its compliance with contractual requirements, and its adequacy under both contractual and legal standards for providing notice of potential termination to the Complainant.
The documentary evidence on record reveals a systematic and comprehensive pattern of communications from the Respondents to the Complainant following her failure to pay the demanded amount. The Respondents issued the initial demand for Rs. 3,80,98,283.09 on 08.04.2024, with the payment becoming due on 26.04.2024 as per the contractual payment schedule. When the Complainant failed to make this payment by the due date, the Respondents initiated a series of follow-up communications.
The Respondents sent multiple reminder notices and communications to the Complainant through emails dated 03.05.2024, 04.05.2024, 05.05.2024, 21.05.2024, 23.05.2024, 28.05.2024, 29.05.2024, and 30.05.2024. This pattern of communication spanning over two months demonstrates the Respondent's systematic approach to providing the Complainant with adequate notice of her default status and multiple opportunities to cure the breach before escalating to termination proceedings.
The final notice dated 28.06.2024 served a crucial function in the termination process by providing explicit and unambiguous intimation to the Complainant regarding the potential consequences of her continued default. This notice clearly stated that failure to make the required payment within seven days would result in termination of the allotment. The notice was specific in its terms, definite in its timeline, and unequivocal in its consequences, thereby providing the Complainant with clear understanding of the impending action.
The requirement for adequate notice in termination proceedings serves the fundamental principles of natural justice and procedural fairness. The notice must be sufficient to inform the defaulting party of the specific breach, the consequences of continued default, and reasonable opportunity to cure the breach. The final notice dated 28.06.2024 meets all these requirements by clearly identifying the payment default, specifying the exact amount due, providing a definite timeline for compliance, and explicitly stating the consequence of non-compliance.
While Clause 9.3(ii) of the Agreement for Sale requires 30 days advance notice before termination, this requirement must be interpreted in the context of the overall communication pattern between the parties. The Respondent's multiple communications beginning from 03.05.2024 onwards effectively put the Complainant on notice that continued default would lead to serious consequences including potential termination. The final notice dated 28.06.2024 represented the culmination of this progressive notice process.
The combination of multiple reminder communications spanning over two months, followed by the specific final notice providing an additional seven-day opportunity to cure the default, demonstrates that the Respondents provided more than reasonable opportunity for the Complainant to address her payment obligations. This extended period of forbearance shows good faith on the part of the Respondents and adherence to principles of fairness and natural justice.
Based on the analysis of the communication pattern, the content and timing of the final notice, and the overall procedural fairness provided to the Complainant, this Authority holds that the final notice dated 28.06.2024 was rightfully issued by the Respondents. The notice was appropriate in its content, adequate in its timing, and compliant with both contractual requirements and legal standards for providing fair warning of impending termination. The Respondents issued this final notice as part of the termination process.
Issue No. 4- Whether the termination of allotment effected on 13.07.2024 was carried out in accordance with Clause 9.3 of the Agreement for Sale and the provisions of the RE(RD) Act, 2016.
The fourth and most critical issue requires examination of whether the actual termination of the allotment effected on 13.07.2024 was carried out in accordance with Clause 9.3 of the Agreement for Sale and the relevant provisions of the RE(RD) Act, 2016 and the Real Estate (Regulation and Development) (Agreement for Sale) Rules, 2016 made thereunder.
Clause 9.3 of the Agreement for Sale provides the specific mechanism and conditions for termination in cases of allottee default. According to the record, Clause 9.3 establishes a framework that includes identification of default conditions, grace periods, notice requirements, and procedural safeguards. The relevant extract of Clause 9.3(ii) reads as follows:
"In case of Default by Allottee under the condition listed above continues for a period beyond 3 (three) consecutive months after notice from the Promoter in this regard, the Promoter may cancel the allotment...
Provided that the Promoter shall intimate the Allottee about such termination at least 30 (thirty) days prior to such termination."
This contractual provision creates a two-tier protection mechanism for allottees: first, a grace period of three consecutive months after notice of default, and second, a mandatory 30-day advance intimation before actual termination. Both these requirements are cumulative and mandatory, designed to provide adequate opportunity for allottees to cure defaults and receive fair warning before facing the drastic consequence of termination.
The factual chronology in the matter at hand reveals that the Complainant's payment default commenced on 26.04.2024, which was the contractual due date for the 85% payment demanded by the Respondents following the achievement of the Occupancy Certificate milestone. From this date until the termination on 13.07.2024, the Complainant remained in continuous default for a period of approximately two and a half months, which substantially exceeds the two-month grace period stipulated under Clause 9.3(ii) of the Agreement for Sale.
However, the issue for determination is whether the mandatory 30-day advance notice requirement under Clause 9.3(ii) was complied with by the Respondents. The evidence on record establishes that the pre-termination letter was issued on 28.06.2024 and the actual termination was effected on 13.07.2024, providing only 15 days between the formal termination notice and the actual termination action.
Section 19(6) of the RE(RD) Act, 2016 places clear and unequivocal statutory obligations on allottees regarding timely payments:
"Every allottee, who has entered into an agreement for sale to take an apartment, plot or building as the case may be, in a real estate project shall be responsible to make necessary payments in the manner and within the time as specified in the said agreement for sale and shall be liable to pay interest, at such rate as may be prescribed, for any delay in payment as per the terms and conditions of the agreement for sale:" This provision establishes that allottees have binding statutory duties to make timely payments as per contractual terms.
However, Section 11(5) of the RE(RD) Act, 2016 equally provides that promoters may cancel allotments "only in terms of the agreement for sale." This statutory language creates a mandatory requirement that all cancellation or termination procedures must strictly comply with the contractual terms agreed upon by the parties, including all procedural safeguards and notice requirements.
Rule 9 of the Real Estate (Regulation and Development) (Agreement for Sale) Rules, 2016, while primarily dealing with project registration matters, establishes the principle that all actions under the RERA framework must comply with both the Act and the contractual terms agreed upon by the parties. The Rules emphasize that contractual obligations are binding and must be performed in accordance with their terms.
The legal purpose behind the 30-day advance termination notice is to provide the defaulting allottee with a definitive and final opportunity to cure the default, arrange alternative financing, seek legal advice, negotiate with the promoter, or take other remedial measures. This period serves substantive purposes beyond mere procedural compliance and cannot be substituted by prior reminder communications; however extensive they may be.
The analysis of the communication pattern reveals that while the Respondent's multiple communications from May 2024 onwards demonstrated good faith and provided general notice of default status, they did not satisfy the specific requirement of 30-day advance intimation of termination as mandated by Clause 9.3(ii). The first communication that explicitly mentioned termination was the notice dated 28.06.2024, and therefore the 30-day period should be calculated from this date.
The failure to provide the complete 30-day advance notice as required under Clause 9.3(ii) of the Real Estate (Regulation and Development) (Agreement for Sale) Rules, 2016 constitutes a material procedural deficiency in the termination process. Even though the underlying payment default was clearly established and exceeded the contractual grace period, the non-compliance with the mandatory notice requirement affects the validity of the termination under Section 11(5) of the RE(RD) Act, which permits cancellation only "in terms of the agreement for sale."
Based on the detailed analysis of Clause 9.3(ii) of the Agreement for Sale, the actual timeline of communications, the legal requirements under Section 11(5) of the RE(RD) Act, 2016, and the established principles governing contractual termination procedures, this Authority finds that while the underlying payment default justified the initiation of termination proceedings, the termination process did not strictly comply with the mandatory 30-day advance notice requirement under Clause 9.3(ii) of the Agreement for Sale. This procedural deficiency affects the validity of the termination, notwithstanding the legitimacy of the underlying payment demands and the Complainant's established default.
It has to be appreciated that the Real Estate (Regulation and Development) Act, 2016 represents a carefully crafted legislative framework that seeks to establish a balanced regulatory regime in the real estate sector by protecting the legitimate interests of both promoters and allottees while ensuring accountability and compliance from all parties involved in real estate transactions. The Act creates a structured framework of mutual rights and obligations where both parties are expected to perform their respective duties in good faith and in accordance with the terms of their agreements.
The legislative intent behind the RE(RD) Act, 2016 is to bring transparency, efficiency, and accountability to real estate transactions while maintaining the sanctity of contractual relationships. Section 19 of the Act specifically places binding obligations on allottees to make timely payments as per agreed terms, while Section 11 of the Act ensures that promoters can enforce their rights but only through proper procedures. This Authority notes that the Act's protective provisions for allottees are designed to prevent exploitation and unfair practices by promoters, but these protections cannot be misused to avoid legitimate payment obligations or to seek unwarranted relief in cases of established default. The Act expects allottees to honour their commitments while providing them with procedural safeguards against arbitrary or unlawful actions by promoters.
In light of the aforementioned findings and comprehensive analysis, this Authority hereby orders as follows:
a. The demands raised by the Respondents for Rs. 3,80,98,283/- are upheld as valid, justified, and in complete accordance with the terms of the Agreement for Sale dated 03.10.2020 as the Respondents were fully within their rights to raise these demands upon obtaining the Occupancy Certificate from competent authority.
b. The final notice dated 28.06.2024 issued by the Respondents is held valid as having been rightfully issued in accordance with the circumstances and legal requirements for providing notice of default and its potential consequences.
c. The termination dated 13.07.2024 is found to be procedurally deficient due to non-compliance with the mandatory 30-day advance notice requirement under Clause 9.3(ii) of the Agreement for Sale. Accordingly, the said termination is hereby set aside subject to payment of Rs. 3,80,98,283/-(Rupees Three Crores Eighty Lakhs Ninety-Eight Thousand Two Hundred and Eighty-Three Only) alongwith interest @10.80% per annum (i.e. MCLR + 2%) from the date demand was raised by the Respondents till actual payment is made within 30 days from the date of this order.
d. Upon receipt of the above payment the allotment of Unit No. SB1-0203, 2nd Floor, Slab Block I, shall stand restored in favour of the Complainant.
The case is disposed of accordingly.
No order as to costs.