A complaint was filed in FORM ‘M’ on 03.12.2021 by Mrs. Kiran Saini (hereinafter referred as “Complainant”) stating that she had approached M/s Diamond Multistate Co-operative Group Housing Society Limited (hereinafter referred as “Respondents or Respondent Society”) for booking of a residential unit in the Respondents project, “Delhi CGHS Yojna”, L-Zone, Dwarka, Delhi. This project was promised to be developed by the Respondents under the Land Pooling Policy (LPP) of DDA.
The Respondents had allotted membership no. 808/MH-37 on 28.02.2018 and issued Welcome Letter dated 03.03.2018 to the Complainant.
The Complainant has paid Rs.18,81,100/- (Rupees Eighteen Lakh Eighty One Thousand One Hundred only) to Respondents against the proposed flat of 1400 sq. ft. area in their project “Delhi CGHS Yojna” in five instalments.
The Complainant has stated that since the Respondents do not have any license and/or approval from the concerned Authorities for construction of the project, he is seeking refund alongwith interest from the Respondents.
A preliminary hearing in the case was held on 01.02.2022 and a notice to the Respondents was issued on 28.12.2021.
The matter was further heard in several hearings dated 30.03.2022, 28.04.2022, 27.07.2022, 12.10.2022 and 18.01.2023. The Respondents filed their reply on 22.03.2022.
We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of Respondents are summarized as under:
The Respondents have been in the business of construction and development for more than a decade and have successfully delivered projects in the NCR region and are developing many projects which are nearing completion in accordance with law.
In the year 2018, the Respondents launched project namely ‘Delhi CGHS Yojna’. The Complainant approached the Respondents for booking a residential apartment in the said project and accordingly signed and executed booking application form out of her own free will.
The Respondents have every intention to develop the said project but owing to the government policies, procedural and administrative factors which are beyond the control of the Respondents, they could not obtain 'Land Transfer Certificate' from DDA which is a pre-requisite for developing the project.
As soon as the Respondents realized that the project is delayed, an option was given to the investors to either stay invested and await for requisite clearances from the competent authorities or opt for a refund. The Complainant opted for refund.
A settlement agreement dated 23.03.2021 was entered into between the parties and in furtherance to that Respondents issued a few cheques in favour of the Complainant but due to some liquidity crunch, they requested not to present the cheques before the banker.
The Respondents are willing to settle the matter and refund the entire principal amount of Rs.18,81,100/- to the Complainant.
Analysis and Consideration:
A perusal of the documents available on record shows that the Respondents have issued five receipts dated 03.03.2018, 05.03.2018, 27.02.2019, 27.03.2019 and 20.09.2019 acknowledging deposits of Rs.21,000/-, Rs.4,50,000/-, Rs.2,00,000/-, Rs.2,58,100/- and Rs.9,52,100/- respectively. Hence, the payment of Rs.18,81,100/-(Rupees Eighteen Lakh Eighty One Thousand One Hundred only) by the Complainant to the Respondents is a recorded fact.
The Real Estate (Regulation and Development) Act, 2016 (hereinafter referred as “the RE (RD) Act, 2016 or Act”) has been enacted to induct professionalism and standardization in the real estate sector, thus paving way for its accelerated growth and investments in the long run.
Further, in the RE (RD) Act 2016, an exhaustive definition of "promoter" is provided section 2. The sub-clause (iv) of clause (zk) of section 2 defines “promoter” as:
“an apex State level co-operative housing finance society and a primary co-operative housing society which constructs apartments or buildings for its Members or in respect of the allottees of such apartments or buildings; or”
The Respondent Society is a Multi-State Co-operative Society, which advertised membership, made members for their housing projects and collected monies from them. The Respondents thus, fall within the definition of “promoter” as defined in the RE (RD) Act, 2016. Therefore, the Authority has jurisdiction to adjudicate the matter and pass appropriate orders on the complaint.
The statement of objects and reasons of the RE (RD) Act, 2016 attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.
An allottee/house buyer can seek refund of amount invested/deposited with the promoter under section 18 of RE (RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest including compensation and also under section 12 of RE (RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the project either through advertisement or otherwise.
In the present complaint, the Complainant intends to withdraw from the project on the ground of delay and is seeking refund of the amount paid to the Respondents in respect of above-mentioned unit under section 18(1) of the RE (RD) Act, 2016 which reads as under:
“Section 18: - Return of amount and compensation
18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building, —
(a). in accordance with the terms of the agreement for sale or, asthe case may be, duly completed by the date specified therein; or
(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason,
he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”
As stated earlier, section 12 of the RE (RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:
“Section 12:-Obligations of promoter regarding veracity of
the advertisement or prospectus
Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:
Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”
The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainant but also misled her at the time of allotment itself by concealing information that they do not have any license or approval from the concerned authorities for construction of project and that no housing project can be developed on agricultural land proposed to be purchased by them. They also did not disclose the risks associated with the project to the society members including the Complainant. It is a pure simple case of giving part information and cheating the members of public at large.
From the facts produced before us, it is clear that the Respondents have collected deposits from the Complainant for the flat in proposed project “Delhi CGHS Yojna” after 01.05.2017, the day RE(RD) Act, 2016 came into force, without registering the project with RERA, Delhi under Section 3 of RE (RD) Act, 2016. This action of the Respondents make them liable for action under Sections 59 of RE (RD) Act, 2016. We would take separate action against Respondents on this account.
The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authorities have exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors., Civil Appeal Nos. 6745-6749 of 2019).
It is noted by the Authority that the Respondents entered into a Memorandum of Understanding (MoU) with the Complainant on 23.03.2021 with the object of refunding the entire principal amount of Rs.18,81,100/-. Further, they issued four cheques of Rs.4,70,275/- each, which could not be encashed due to an insufficient balance in the account. Therefore, the Authority is of the considered view that the Respondents are liable to pay the entire principal amount of Rs.18,81,100/- with interest to the Complainant.
In the light of the aforesaid, we direct the Respondents, M/s Diamond Multi State Co-operative Group Housing Society Limited to refund the entire amount of Rs.18,81,100/- (Rupees Eighteen Lakh Eighty One Thousand One Hundred only) to the Complainant within 45 days of issuance of this order along with interest at the rate of 10% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.
The case is disposed of accordingly.
No order as to costs.