Tribunals and CommissionsDivision Bench(2025) 08 RERA CK 2153

Mr. Rajat Sharma vs M/s Diamond Multistate Co-operative Group Housing Society Ltd. & Anr.

Real Estate Regulatory Authority National Capital Territory Of Delhi · Decided on 27 August 2025

RESULT
Disposed Of
CASE NUMBER
Com/14/08/2024
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

Judgment

41 paragraphs · 1,838 words
CourtKutchehryPremium

Upgrade to Premium

Everything you need for focused legal research, in one membership.

  • Unlimited judgment reading
  • Advanced judgment search
  • AI judgment summaries
  • Original court PDFs
  • All related judgments
  • Bookmarks, notes & exports

Loading membership options…

1.

A complaint was filed in Form ‘M’ on 14.08.2024 by Mr. Rajat Sharma (hereinafter referred to as ‘Complainant’) stating that in the year 2018, he booked a 3BHK residential unit in the project, “Delhi CGHS Yojana”, having an area of 1150Sq. Ft. promoted by M/s Diamond Multistate Co-operative Group Housing Society Limited (hereinafter referred to as “Respondents or Respondent Society”) in Dwarka, Delhi, in L-Zone, Dwarka, Phase-2, Delhi.

2.

The Complainant paid a total sum of Rs. 15,46,100 /- (Rupees Fifteen Lakhs Forty-Six Thousand One Hundred Rupees Only) to the Respondents.

3.

The Respondents vide welcome letter dated 03.03.2018 confirmed membership of the Complainant and subsequently allotted him a 3BHK flat at proposed “Delhi CGHS Yojana” Project.

4.

The Complainant stated that despite the lapse of four years no progress has been made in the project by the Respondents till date, therefore, the Complainant wants to withdraw from the project and is seeking refund of amount deposited amounting to Rs. 15,46,100/- with the Respondents along with interest. The Complainant has further submitted that several efforts have been made to recover the amount but the Respondents failed to refund the money on the pretext of one reason or the other.

5.

A preliminary hearing in the case was held on 30.09.2024. Notice of complaint was sent to the Respondents on 24.10.2024 via registered post and on 24.10.2024 via e-mail.

6.

The matter was subsequently heard on 14.10.2024, 18.12.2024, 04.03.225, 24.04.2025 and 10.07.2025. The Respondents filed their reply on 24.02.2025 and thereafter, the Complainant filed their Rejoinder during the course of hearing held on 04.03.2025.

7.

We have heard the arguments and perused the records. For the sake of convenience, the arguments and submissions made on behalf of the Respondents are summarized as under:

i.

The Respondents have been in the business of the construction and development for more than a decade and have successfully delivered projects in the NCR region and are developing many projects which are near completion in accordance with law.

ii.

In the year 2018, the Respondents launched project namely ‘Delhi CGHS”. The Complainants approached the Respondents for booking a residential apartment in the said project and accordingly they signed and executed booking application form out of their own free will.

iii.

The Respondents had every intention to develop the said project but owing to the government policies and procedural and administrative factors which comes under the Force Majeure reason, which were beyond the control of the Respondents, the Respondents could not obtain the Land Transfer Certificate, which was a prerequisite for developing the project. As soon as the Respondents realized that the project is being delayed, they gave an option to its existing investors to either stay invested and await the requisite clearances from the competent authorities or, in an alternative opt for a refund. The Complainant opted for refund out of their own free will.

iv.

The Respondents are ready to refund the entire principal amount of Rs. 15,46,100/- (Rupees Fifteen Lakhs Forty-Six Thousand One Hundred Rupees Only) to the Complainants.

8.

We have heard the arguments of Ld. Counsels of both the parties and perused the records of the case

Analysis and Consideration

9.

A perusal of the documents available on record reveals that the Complainant in the instant case has claimed a refund of ₹ 15,46,100/- along with interest. The Respondent on the other hand had duly acknowledged the following amounts being deposited by the Complainant amounting to Rs. 15,46,100/- in two installments towards the proposed Flat and issued four receipts to the Complainant, the details of which are as under: -

S. No.Date of ReceiptAmount paid
1.03.03.2018Rs. 21,000/-
2.06.03.2018Rs. 4,00,000/-
3.28.02.2019Rs. 3,43,100/-
4.18.09.2019Rs. 7,82,000/-
TOTALRs. 15,46,100/-

A close perusal of the documents available on record shows that the Respondents have issued four receipts dated 03.03.2018, 06.03.2018, 28.02.2019 and 18.09.2019 acknowledging deposits of Rs. 15,46,100/-. Hence, a total payment of Rs. Rs. 15,46,100 /- (Rupees Fifteen Lakhs Forty-Six Thousand One Hundred Rupees Only) by the Complainant to the Respondents is a recorded fact.

10.

The RE (RD) Act, 2016 has been enacted to induct professionalism and standardization in the real estate sector, paving the way for catalyzing investments and accelerating growth of sector in the long run. To achieve these objectives, the Act created a Regulatory Authority to supervise the conception, initiation and completion of a real estate project. The RE (RD) Act, 2016 is a special law enacted to address issues in the real estate sector. Therefore, all disputes between homebuyers/allottees and promoters/developers relating to any real estate project covered under RE (RD) Act of 2016, can be raised before the concerned Real Estate Regulatory Authority (RERA). Section 79 of the RE (RD) Act, 2016 even bars jurisdiction of civil courts to entertain any suit or proceeding in respect of any matter which the Authority is empowered under the Act to determine. Moreover, section 89 of RE (RD) Act, 2016 says that provisions of this Act shall have an overriding effect on anything inconsistent in any other law in force.

11.

It must be appreciated that the statement of objects and reasons of RE(RD) Act, 2016 clearly states that the Act attempts to balance the interests of consumers and promoters by imposing certain responsibilities on both. It also seeks to establish symmetry of information between the promoter and purchaser, enhance transparency of contractual conditions, set minimum standards of accountability and a fast-track dispute resolution mechanism.

12.

An allottee/house buyer can seek refund of amount invested with promoter under section 18 of RE(RD) Act, 2016, if the promoter fails to complete project by the date specified in agreement to sale with interest including compensation and also under section 12 of RE(RD) Act, 2016 if he/she was misled by any information furnished by promoter with regard to the proposed project either through advertisement or otherwise.

13.

In the present complaint, the Complainants intend to cancel/withdraw from the said project and is seeking refund of the amount paid to Respondents in respect of subject unit under section 18(1) of the RE(RD) Act, 2016 on account of delay which reads as under:

“Section 18. Return of amount and compensation. -

18(1). If the promoter fails to complete or is unable to give possession of an apartment, plot, or building,

(a). in accordance with the terms of the agreement for sale or, as the case may be, duly completed by the date specified therein; or

(b). due to discontinuance of his business as a developer on account of suspension or revocation of the registration under this Act or for any other reason, he shall be liable on demand to the allottees, in case the allottee wishes to withdraw from the project, without prejudice to any other remedy available, to return the amount received by him in respect of that apartment, plot, building, as the case may be, with interest at such rate as may be prescribed in this behalf including compensation in the manner as provided under this Act.”

14.

Section 12 of the RE(RD) Act, 2016 casts a duty upon the promoter to provide correct and updated information to allottees regarding the project. It reads as under:

“Section 12. Obligations of promoter regarding veracity of the advertisement or prospectus.-

Where any person makes an advance or a deposit on the basis of the information contained in the notice advertisement or prospectus, or on the basis of any model apartment, plot or building, as the case may be, and sustains any loss or damage by reason of any incorrect, false statement included therein, he shall be compensated by the promoter in the manner as provided under this Act:

Provided that if the person affected by such incorrect, false statement contained in the notice, advertisement or prospectus, or the model apartment, plot or building, as the case may be, intends to withdraw from the proposed project, he shall be returned his entire investment along with interest at such rate as may be prescribed and the compensation in the manner provided under this Act.”

15.

The Respondents, in complete disregard to their duties, not only failed to furnish correct information to the Complainants but also misled them at the time of allotment itself by concealing information that they do not have any license or approval from the concerned authorities for construction of project. They also did not disclose the risks associated with the project to the society members including the Complainant. The promoters gave part information and cheated the members of public at large. Therefore, in view of the provisions in Section 18 and Section12 of RE(RD) Act, 2016, the Respondents are liable to refund the principal amount with interest.

16.

The law is well settled that the allottees/homebuyers hold an unqualified right to seek refund of the amount with interest at such rate as may be prescribed in this behalf. A conscious decision has been taken by the legislature to cast an obligation upon the promoter to refund the amount on demand along with interest at rate prescribed. It has also been held through the recent judgments of the Hon’ble Supreme Court that the Regulatory Authority has exclusive jurisdiction to direct refund of the amount, and interest on the refund amount to the allottees. (Vide: Imperia Structures Ltd. Vs. Anil Patni and Another, 2020 (10) SCC 783, and Newtech Promoters and Developers Pvt. Ltd. v. State of UP And Ors. LL 2021 SC 641).

17.

In the case in hand, the Respondents submitted that they had every intention to develop the project but for reasons beyond their control they could not obtain “Land Transfer Certificate” which is a pre-requisite for developing the project. Therefore, they gave an option to seek refund or awaits requisite clearance. Further, they are willing to refund the principle amount to the Complainant

18.

On perusal of the documents on record and submissions made by both the parties, the Authority is of view that the Respondents are in contravention of the sections 18 and 12 of RE (RD) Act, 2016.1 Accordingly, the Complainant is entitled to get the refund of the amount paid by them along with the interest at prescribed rate @ 10.80% p.a. (i.e., MCLR plus 2%) as per provisions of section 18 and 12 of RE (RD) Act, 2016 read with Rule 15 of the NCT of Delhi RE(RD) (General) Rules, 20162.

19.

In the light of the aforesaid, we direct the Respondents M/s Diamond Multi State Co-operative Group Housing Society Limited to refund the entire amount of Rs. 15,46,100/-/- (Rupees Fifteen Lakhs Forty-Six Thousand One Hundred Rupees Only) to the Complainant i.e. Mr. Rajat Sharma within 45 days of issuance of this order along with interest at the rate of 10.80% per annum (MCLR+2%) from the date of payment of each sum until the date of its actual return.

11.

The case is disposed of accordingly.

12.

No order as to costs.

Footnotes

  1. 1.The National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016
  2. 2.The National Capital Territory of Delhi Real Estate (Regulation and Development) (General) Rules, 2016