The case was reserved for orders on 15.03.2022 and pronounced in open court on 24.05.2022.
The Complainant through email dated 05.07.2022 has requested the Authority to rectify the name of project from “Regalia” to “Krisha Heights” mentioned in the final order dated 24.05.2022.
Under Section 39 of RE (RD) Act, 20161, Authority can rectify error regarding the name of the project. Section 39 of RE (RD) Act, 2016 is reproduced below :
Section 39 : Rectification of orders
The Authority may, at any time within a period of two years from the date of the order made under this Act, with a view to rectifying any mistake apparent from the record, amend any order passed by it, and shall make such amendment, if the mistake is brought to its notice by the parties:
Provided that no such amendment shall be made in respect of any order against which an appeal has been preferred under this Act:
Provided further that the Authority shall not, while rectifying any mistake apparent from record, amend substantive part of its order passed under the provisions of this Act.
On perusal of the record, it is noticed by the Authority that the name of project in welcome letter and receipts issued by the Respondents is “Krisha Heights” and not Regalia”. This error being apparent from the record can be rectified by making an amendment in the final order. Therefore, the name of the project in the final order dated 24.05.2022 be read as “Krisha Heights” in the place of “Regalia”.
The final order dated 24.05.2022 stands rectified accordingly. This order shall be attached with the final order dated 24.05.2022.
Footnotes