Tribunals and CommissionsDivision Bench(2023) 03 NCLAT CK 0011

Mohit Gupta Suspended Designated Partner of Innovation India Projects LLP vs Illuminar Engineering Services Pvt. Ltd. & Ors

National Company Law Appellate Tribunal · Decided on 7 March 2023

HON’BLE JUDGES
Rakesh Kumar Jain, Member (J) · Dr. Alok Srivastava, Member (T)
RESULT
Allowed
CASE NUMBER
Company Appeal (AT) (Insolvency) No. 291 Of 2023

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

12 paragraphs · 271 words

This appeal is directed against the order dated 28.02.2023 by which an application filed by the Operational Creditor under Section 9 of the Code, has been admitted.

Counsel for the Appellant has submitted that after the impugned order was passed, the parties have entered into a settlement agreement dated 02.03.2023.

It is submitted that the settlement amount has been arrived at Rs. 4,03,08,250/-. The said amount is to be paid by way of six installments which are reproduced as under: -

“a. Rs. 25,00,000/- (Twenty-Five Lacs) upon signing and execution of the present agreement.

b. Rs. 1,00,00,000/- (One Crore) on 06th March, 2023

c. Rs. 1,00,00,000/- (one Crore) on 2nd April, 2023

d. Rs. 50,00,000/- (Fifty Lacs) on 15th April, 2023 e. Rs. 50,00,000/- (Fifty Lacs) on 30th April, 2023.

f. Rs. 78,08,205/- (Seventy-Eight Lacs Eight Thousand and Two Hundred and Five).”

It is further submitted that Rs. 25 Lakh was paid at the time of signing and execution of the agreement and a cheque of Rs. 1 Crore dated 06.03.2023 has already been encashed. This fact has not been denied by the Counsel for the Operational Creditor and IRP.

The rest of the amount has been paid by the Appellant by way of post-dated cheques.

In view thereof, the present appeal is hereby allowed in terms of the settlement agreement dated 02.03.2023. As a consequence, the initiation of the CIRP and imposition of the moratorium are hereby set aside.

It is made clear that in case the Appellant makes any default in payment of the rest of the amount, the Respondents may file appropriate application for revival of impugned order.