High CourtsSingle Bench(2026) 11 DEL CK 2594

Mbook Technology Pvt. Ltd. vs Skymax Infrapower Pvt. Ltd.

Delhi High Court · Decided on 6 November 2026

HON’BLE JUDGES
Vinod Kumar, J
RESULT
Partly Allowed
CASE NUMBER
O.M.P.(I) (COMM.) 503/2026, I.A. 29807/2026 & O.M.P.(I) (COMM.) 512/2026

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

CourtKutchehry membership

More clarity. Every judgment.

Download court copies, explore connected cases and make more of every research session.

Loading membership options…

Ask AI about this case

AI Structured Summary

Not yet generated for this judgment

Judgment

83 paragraphs · 3,659 words
1.

The disputes between the parties arose in the context of the execution of a solar power project under Component-C of the PM-KUSUM Scheme, situated in District Nanded, Maharashtra. In relation to the said project, Skymax Infra Power Limited (hereinafter referred to as “Skymax”) and Mbook Technology Private Limited (hereinafter referred to as “Mbook”) entered into a Sub-Contract Agreement dated 18.12.2025 (hereinafter referred to as “the Agreement”), whereby Mbook was entrusted with the execution of a part of the said project.

2.

The larger project was undertaken pursuant to a Power Purchase Agreement dated 16.01.2025 executed between Maharashtra State Electricity Distribution Company Limited (MSEDCL) and Skymax. Under the aforesaid arrangement, the project envisaged development of solar power generating stations at various locations in the State of Maharashtra. The work entrusted to Mbook under the Sub-Contract Agreement formed part of the larger project.

3.

In terms of the Agreement dated 18.12.2025, Mbook was entrusted with the execution of specified works forming part of the project in District Nanded. The initial scope of work under the Agreement related to the project locations at Degaon, Tuppa, Neela, Manjaram and Pardi. The project locations referred to in the pleadings also include Ardhapur, Bhokar, Himayatnagar and Wadgaon.

4.

The Agreement governed the contractual relationship between the parties and stipulated their respective obligations in relation to the execution of the works. It also contained provisions dealing with the timelines for completion, the consequences of default, termination of the Agreement and resolution of disputes. The Agreement provided for an arbitration mechanism under Clause 16.

5.

Disputes thereafter arose between the parties in relation with the execution and progress of the works under the Agreement. While Skymax alleges that Mbook failed to make adequate progress and did not fulfil its contractual obligations within the stipulated timelines, Mbook disputes the allegations and attributes the delay in execution of the works to various acts and omissions on the part of Skymax.

6.

In the course of their contractual dealings, the parties exchanged communications concerning the progress of the works, the pending activities at the project sites and the obligations required to be fulfilled under the Agreement.

7.

On 22.10.2026, Skymax issued a notice terminating the Agreement dated 18.12.2025. The said notice also called upon Mbook to demobilise from the project sites and contained directions and demands concerning the completion of the balance works and the amounts claimed by Skymax. The legality and validity of the termination, as well as the consequences flowing therefrom, have been disputed by Mbook in this petition.

8.

Mbook has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 seeking interim measures of protection on account of Skymax seeking to terminate the Agreement dated 18.12.2025 executed between the parties. The petitioner- MBook in its petition has prayed for the following reliefs:-

“A. Grant an ad-interim injunction, staying the operation and effect of the Termination Notice dated 22.10.2026 issued by the Respondent, and restrain the Respondent from giving effect to the same or terminating the Sub-Contract Agreement dated 18.12.2025 in any manner pending final adjudication of the disputes through arbitration.

B. Direct the parties to maintain status quo ante as existing prior to 22.10.2026 with respect to the operation, management, and functioning of the Project sites at Degaon, Tuppa, Neela, Manjaram, Pardi, Himayatnagar, Wadegaon, Ardhapur, and Bhokar in District Nanded, Maharashtra, and at the Petitioner's stores, under the Sub- Contract read with the Variation of Quantity Letters dated 03.02.2026 and 23.02.2026 including uninterrupted access and services by the Petitioner;

C. Grant an ad-interim injunction restraining the Respondent from interfering with, or otherwise obstructing the execution of the Project works at the Project sites by the Petitioner, in accordance with the terms of the Sub-Contract executed between the parties;

D. Grant a prohibitory ad-interim injunction restraining the Respondent, its officers, agents, contractors and any person claiming through it from, directly and/or indirectly, removing, using, installing, dismantling, altering, transferring, disposing off or parting with possession of the materials, equipment, machinery and work-in-progress supplied or executed by the Petitioner, and from carrying out any work at the said sites that alters their existing condition;

E. Grant a prohibitory ad-interim injunction restraining the Respondent from directly and/or indirectly, engaging, appointing or contracting with any other contractor, affiliates, subsidiaries, agency, or third party, for execution of the Project works awarded to the Petitioner under the Sub-Contract Agreement dated 18.12.2025 read with the Variation of Quantity Letters dated 03.02.2026 and 23.02.2026 issued by the Respondent;

F. Pass an order directing the Respondent to deposit with this Hon'ble Court an amount of INR 25,32,54,564/- (Rupees Twenty Five Crore Thirty-Two Lakhs Fifty-Four Thousand Five Hundred and Sixty Four) or in the alternative, furnish security for an amount of INR 25,32,54,564/- by way of bank guarantee or fixed deposit receipt or any other instrument as this Hon'ble Court may deem fit;

G. Grant a prohibitory ad-interim injunction restraining the Respondent from creating any third-party rights or interests in respect of the said works, the Project sites or the Petitioner's materials;

H. Pass an order directing the Respondent to disclose on affidavit, a list of all immovable and moveable assets of the Respondent along with encumbrances, if any, and the audited financial statements for the previous financial year;

I. Pass ad-interim ex-parte orders in terms of the prayers above, if required;”

9.

It is submitted by Mr. Sandeep Sethi, learned Senior Advocate for Mbook that the Termination Notice dated 22.10.2026 has been issued under Clause 9.2.2 of the Agreement, whereby Skymax has terminated the Agreement with "immediate effect". In terms of Clause 9.2.2 of the Agreement, Skymax was entitled to terminate the same only if Mbook failed to fulfill its obligations after affording the Mbook an opportunity of rectifying the breach within 30 days of receiving a written notice in this regard.

10.

Therefore, it is submitted that the termination notice is wrongful and constitutes as breach of Agreement and the emails sent by Skymax from March 2026 cannot be constituted as “notice” as per Clause 9.2.2 of the Agreement.

11.

Learned Senior Counsel further submitted that the delay in the execution of the project is solely attributable to Skymax and not to Mbook. Additionally, various Variation of Quantity Letters in terms of Clause 2.1 of the Agreement were issued by Skymax to the Mbook through which 4 (four) new locations were awarded to Mbook for carrying out the work. However, no revised date of competition after award of the works at the said additional location was communicated to the petitioner.

12.

Thus, learned Senior Counsel argued that it is a fit case for grant status quo on Termination Notice and consequences following from the same. It is submitted that the allotted work would be completed by Mbook within 30 days and thus, the work would be expeditiously carried out if operation of Termination Notice is stayed.

13.

Mr. Sandeep Sethi, learned Senior Counsel has again drawn my attention to Clause 9.2.2 of the Agreement dated 18.12.2025 in which it is stated that if either party fails to fulfill its obligation under the Agreement and does not rectified the breach within 30 days of receiving the notice, the aggrieved party shall be entitled to terminate the Agreement. It is submitted that no 30 days written notice was given to Mbook to cure the defects. Therefore, it is submitted that Termination Notice is illegal in the eyes of law.

14.

Mr. Sandeep Sethi, learned Senior Advocate has strongly relied upon Mahajan Imaging (P) Ltd. v. Pushpawati Singhania Research Institute, 2026 SCC OnLine Del 1779, in which this Court held that the parties are bound to adhere to termination mechanism embodied in the Agreement and that the proper course would have been to issue a notice identifying the alleged material breach and affording the aggrieved party a contractually mandated opportunity to cure the same within the prescribed period. It was further held that it is only upon the failure to rectify such breach within the stipulated time, that a right to issue a termination notice could have arisen.

15.

Learned Senior Counsel pointed out that in aforesaid case, no „cure notice‟ was issued before terminating the Agreement and therefore, a status quo order dated 29.10.2026 was passed by this Court with respect to operation, implementation and performance of the agreement as it is stood immediately prior to issuance of the said termination notice.

16.

Learned Senior Counsel submits that facts of the present case are similar to case of Mahajan Imaging (Supra).

17.

Countering the submissions of learned Senior Counsel for Mbook, learned Counsel for respondent-Skymax has drawn my attention to the fact that in Mahajan Imaging (Supra), the Agreement was for providing radiology services. It is submitted that the nature of agreement between the parties in Mahajan Imaging (Supra) should be differentiated with the infrastructure projects which have been categorized in Schedule to the Specific Relief Act, 1963 (in short „Act of 1963‟). It is submitted that the Category no. II in the Schedule is „Energy Sector‟.

18.

Learned Counsel for Skymax has drawn my attention to the Agreement dated 18.12.2025 which shows that the Agreement is in respect of a solar project. Therefore, the embargo of Section 20A and Section 41 (ha) of the Act of 1963 would come into play. It is argued that as the project falls in the category of infrastructure projects specified in the Schedule, no stay on termination of contract can be granted.

19.

I have carefully perused the material on record and considered the submissions advanced by learned Counsels for the parties.

20.

The fact that the Agreement in question pertains to Energy Sector, specified in the Schedule of the Act of 1963, has not been disputed. Now, I reproduce Section 20A of the Act of 1963 as under:

“Special provisions for contract relating to infrastructure project.

20A. (1) No injunction shall be granted by a court in a suit under this Act involving a contract relating to an infrastructure project specified in the Schedule where granting injunction would cause impediment or delay in the progress or completion of such infrastructure project.

Explanation.—For the purposes of this section, section 20B and clause (ha) of section 41, the expression "infrastructure project" means the category of projects and infrastructure Sub-Sectors specified in the Schedule.

(2)

The Central Government may, depending upon the requirement for development of infrastructure projects, and if it considers necessary or expedient to do so, by notification in the Official Gazette, amend the Schedule relating to any Category of projects or Infrastructure Sub-Sectors.

(3)

Every notification issued under this Act by the Central Government shall be laid, as soon as may be after it is issued, before each House of Parliament, while it is in session, for a total period of thirty days which may be comprised in one session or in two or more successive sessions, and if, before the expiry of the session immediately following the session or the successive sessions aforesaid, both Houses agree in making any modification in the notification or both Houses agree that the notification should not be made, the notification shall thereafter have effect only in such modified form or be of no effect, as the case may be; so, however, that any such modification or annulment shall be without prejudice to the validity of anything previously done under that notification.”

21.

Thus it is clear that Section 20A of the Act of 1963 proscribes the Court from issuing any injunction involving a contract relating to infrastructure project specified in the Schedule to the Act of 1963, in case it will cause impediment in completion of the project. Further, Section 41 (ha) of the Act of 1963 contains a general prohibition from granting a stay in any infrastructural project, even if the same does not fall in the Schedule of the Act of 1963. Section 41 (ha) of Specific Relief Act is reproduced as under:

“41. Injunction when refused

An injunction cannot be granted –

(a)

……………………..

(b)

…………………….

(c)

…………………….

(d)

……………………..

(e)

…………………….

(f)

……………………..

(g)

……………………...

(h)

………………………

(ha)

if it would impede or delay the progress or completion of any infrastructure project or interfere with the continued provision of relevant facility related thereto or services being the subject matter of such project;”

22.

Thus, Section 20A of the Act of 1963 clearly bars the Court from granting an injunction involving a contract relating to a infrastructure project specified in the Schedule to the Act of 1963 if it would cause impediment or delay in the progress or completion of such infrastructure project.

23.

Argument of learned Senior Counsel for Mbook is that, had the Skymax given a cure notice as per Clause 9.2.2, he would have complied with the same and this would have actually expedited the progress of the project. It is argued that even if today, „cure notice‟ of 30 days is given, the defects would be removed and thus, it would save Skymax from the trouble and expenses of bringing a third party for completion of the contract.

24.

I disagree with the submissions of Mr. Sandeep Sethi, learned Senior Counsel.

25.

It must be kept in mind that no party would like to terminate a contract midway unless serious disputes have arisen about the execution of the obligations. Therefore, to say that staying of Termination Notice would expedite the project is unacceptable. The impugned Termination Notice has mentioned that Mbook had abandoned the works without any justification and its persistent defaults have not only inordinately delayed the entire project but has also caused substantial loss to Skymax. It is also mentioned that such conduct of Mbook has also exposed Skymax to adverse action at the hands of principal employer i.e. Maharashtra State Electricity Distribution Company Ltd. It would be of course, a subject matter before the learned Arbitrator as to whether the said allegations are correct or not but, at this stage, this Court is looking at the prima facie case only.

26.

If the Skymax has wrongly terminated the contract, the only remedy with the Mbook is to claim compensation/damages. However, this Court cannot ignore the specific prohibition of Section 20A of the Act of 1963 from granting an injunction in a contract like the present one as well as general prohibition under Section 41 (ha) of the Act of 1963.

27.

I have carefully perused the judgment of Mahajan Imaging (Supra) and I agree with learned Counsel for the respondent-Skymax that in the said judgment, the Court was not dealing with an infrastructure project as specified in the Schedule of the Act of 1963, whereas the present project falls in the Schedule, in respect of which Section 20A of the Act of 1963 creates a prohibition.

28.

Hence, this petition is dismissed. The pending application also stands disposed of.

O.M.P (I) (COMM.) 512/2026

29.

Now, I take up the petition filed under Section 9 of the Act of 1996 by Skymax Infra Power Ltd. in OMP (I) (COMM.) 512/2026, in which it is prayed as under:

“A. Direct the Respondent to vacate the project site and restore possession of all related assets belonging to existing works, installations, equipment, materials, and technical records, for the 42/53.268 MW PMKUSUM Component-C Solar Project located in Nanded District, Maharashtra to Petitioner immediately; and/or

B. Direct the Respondent to forthwith hand over and deliver to Petitioner all project-related documents, records and deliverables required to be provided under the Sub-Contract Agreement dated 18.12.2025, including, without limitation, all original invoices, OEM/vendor warranty and guarantee certificates, equipment and material warranties, quality and inspection records, test reports, operation and maintenance manuals, pre-commissioning and commissioning records, insurance policies and endorsements, vendor payment clearances, No Objection Certificates (NOCs), and all departmental, statutory, regulatory, technical and other approvals, permissions, sanctions and clearances pertaining to the Project and the equipment, machinery and materials procured, supplied, installed or intended to be deployed thereunder, insofar as the same are in the possession, custody or control of the Respondent or are required to be procured or furnished by it under the Agreement; and/or

C. Pass such other or further orders as this Hon’ble Court may deem just, necessary and appropriate in the facts and circumstances of the case.”

30.

In a nutshell, Skymax is praying that Mbook may be directed to vacate the site project and restore the possession of all the assets to Skymax and also deliver all project related documents, records etc. to the Skymax.

31.

Mr. Sandeep Sethi, learned Senior Counsel for Mbook has assailed these prayers submitting that these prayers, being mandatory injunction, are beyond the scope of Section 9 of the Act of 1996.

32.

It is further argued that if the prayer of the Skymax are accepted, the same would amount to final adjudication of the issues. In support of his submissions, learned Senior Counsel for Mbook has referred to judgments of Division Benches of Delhi High Court in Deepak Balutia vs Anu Manglani, in FAO (COMM) 235/2026 dated 30.09.2026 and National Highways Authority of India vs. Bhubaneswar Expressway Private Limited in FAO (OS) (COMM) 66/2020 dated 11.05.2021.

33.

It is argued that the prayers of this petition are in nature of final relief and if allowed, same would reduce the arbitral Award to a mere paper decree.

34.

I have considered the rival submissions and have perused the judgment in Deepak Balutia (Supra). In this case, the Division Bench of this Court was dealing with an order passed by District Judge under Section 9 of the Act of 1996, whereby learned District Judge directed the landlord to restore electricity connection in the tenanted premises without any corresponding direction for payment of lease rent. Therefore, the said order was set aside. But it was nowhere held that the District Judge had no power to issue direction for restoration of the electricity. It was set aside because it was unreasonable as it ignored the corresponding rights of the landlord to receive the lease rent.

35.

I have also perused Bhubaneswar Expressway (Supra), which is a judgment of Division Bench of this Court.

36.

Perusal of the aforesaid judgment makes it clear that though the Court under Section 9 of the Act of 1996 can issue interim measures but it cannot pass an order which amounts to final adjudication of an issue. In the said judgment, the Division Bench was dealing with an order of the Commercial Division, which allowed an application under Section 9 of the Act of 1996, filed by Bhubaneswar Expressway Private Limited while holding that National Highways Authority of India was liable to make payment of Termination Notice equivalent to 90% of debt due. The Division Bench held that this was practically a final decision on the dispute between the parties and that this dispute could only be adjudicated by Arbitral Tribunal and cannot be adjudicated in proceedings under Section 9 of the Act of 1996.

37.

However, facts before this Court are totally different. As the agreement has been terminated by Skymax, Mbook-respondent can only claim the damages for breach of contract through arbitration. In a claim for damages, issue of vacation of the site would not arise. Skymax-petitioner wants to complete the project expeditiously and for that purpose it wants the project site to be vacated by Mbook.

38.

Issuing the directions as prayed would not amount to award of claim of Mbook, which would of course be a subject matter of the arbitration proceedings.

39.

Therefore, I am of the opinion that interim measures can be ordered by this Court for helping Skymax in timely completion of the project. I would like to reproduce relevant provisions of Section 9 of the Act of 1996, as under:

“9.

Interim measures, etc., by Court.- [(1)] A party may, before or during arbitral proceedings or at any time after the making of the arbitral award but before it is enforced in accordance with section 36, apply to a Court:

(i)

……………………;

(ii)

for an interim measure of protection in respect of any of the following matters, namely:

(a)

…………………..;

(b)

…………………..; (c) the detention, preservation or inspection of any property or thing which is the subject-matter of the dispute in arbitration, or as to which any question may arise therein and authorising for any of the aforesaid purposes any person to enter upon any land or building in the possession of any party, or authorising any samples to be taken or any observation to be made, or experiment to be tried, which may be necessary or expedient for the purpose of obtaining full information or evidence;

(d)

……………………;

(e)

such other interim measure of protection as may appear to the Court to be just and convenient, and the Court shall have the same power for making orders as it has for the purpose of, and in relation to, any proceedings before it.”

40.

The language used in Clause (c) and (e) of Section 9 of the Act of 1996 are wide enough, but short of passing any interim award, to pass any direction for protection or preservation of any property.

41.

Accordingly, with a view to protect and preserve the project site, I direct Mbook-respondent to vacate the project site within three weeks from this order. This order has been passed so that the project is not further delayed.

42.

In respect of other reliefs, the respondent-Mbook shall file reply.

43.

The petition is re-notified for 16.12.2026.

CONCLUSION

44.

The petition under Section 9 of the Act of 1996 filed by Mbook bearing OMP (I) (COMM.) 503/2026 along with pending application is dismissed.

45.

The petition under Section 9 of the Act of 1996, bearing OMP (I) (COMM.) 512/2026 is partly allowed with a direction to Mbook to vacate the project site. In respect of remaining reliefs, the respondent-Mbook may file reply within three weeks, rejoinder, if any be filed one week thereafter.

46.

The petition bearing OMP (I) (COMM.) 512/2026 is re-notified for 16.12.2026